Labour Day Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PDF C_TS412_2021 Study Guide

Page: 3 / 3
Question 12

Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

Options:

A.

An activated Scheduling indicator in the control key of the internal processing activity

B.

Whether the work for the internal activity is greater than its duration

C.

The unit (for example, hour, day) of the field Normal Duration field of the activity

D.

The relationships between activity elements

E.

The factory calendar in the work center used for the internal processing activity

Question 13

Project Structures

You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the

project.

What are the prerequisites?

Note: There are 3 correct answers to this question

Options:

A.

A bill of material with sales views

B.

A material master with sales views

C.

Assignment between material and standard network

D.

Standard network with activities

E.

A production order

Question 14

For which objects can billing plans be created? Note: There are 2 correct answers to this question

Options:

A.

WBS elements

B.

Project definition

C.

Sales order items

D.

Milestones

Question 15

Where do you control whether a project stock is managed as valuated or non-valuated project stock?

Options:

A.

In the network activity

B.

In the project definition

C.

In the WBS element

D.

In the material master

Page: 3 / 3
Exam Code: C_TS412_2021
Exam Name: SAP Certified Application Associate - SAP S/4HANA Project Systems
Last Update: May 5, 2024
Questions: 110
C_TS412_2021 pdf

C_TS412_2021 PDF

$28  $80
C_TS412_2021 Engine

C_TS412_2021 Testing Engine

$33.25  $95
C_TS412_2021 PDF + Engine

C_TS412_2021 PDF + Testing Engine

$45.5  $130