Question 24

A contractor wants to use an adhesive that exceeds the allowed Volatile Organic Compound (VOC) content limit under Indoor Environmental Quality Credit, Low Emitting Materials. This credit canbe earned if

Options:

A.

the VOC budget method is applied for VOC content

B.

the adhesive is not included in the LEED documentation

C.

75% of the adhesives used comply with the VOC content limit and emissions requirements

D.

95% of the adhesives used comply with the VOC content limit and emissions requirements

Question 25

Which of the following is required in determining the baseline for Water Efficiency Prerequisite, Indoor Water Use Reduction?

Options:

A.

Duration of use

B.

Building floor area

C.

Make and model of fixtures

D.

Proposed design fixture flow rates

Question 26

Which of the following project team members should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning?

Options:

A.

Owner

B.

Contractor

C.

Occupants

D.

Facility manager

Question 27

Which of the following documents contains the design team's interpretation of the Owner's Project Requirements?

Options:

A.

Basis of Design (BOD)

B.

Simple Box Energy Model Analysis

C.

System's manual

D.

Integrated Project Delivery report

Page: 6 / 17
Exam Code: LEED-AP-BD+C
Exam Name: LEED AP Building Design + Construction (LEED AP BD+C)
Last Update: May 19, 2024
Questions: 232
LEED-AP-BD+C pdf

LEED-AP-BD+C PDF

$28  $80
LEED-AP-BD+C Engine

LEED-AP-BD+C Testing Engine

$33.25  $95
LEED-AP-BD+C PDF + Engine

LEED-AP-BD+C PDF + Testing Engine

$45.5  $130