Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PgMP Exam Dumps - PMI Certification Questions and Answers

Question # 44

One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set.

If the tolerance range is too narrow on a program, what effect will multiple minor changes have on the program?

Options:

A.

Reduction in program quality

B.

Degradation of program communications

C.

Reduction in program risk

D.

Slow down in program implementation

Buy Now
Question # 45

You are the program manager of the NHQ Program for your organization. Your program is nearing the completion of one of its major phases and there are several resources that should be released at this time. What program management plan will guide you to release of the program resources and transfer the resources and benefits to operations within the organization?

Options:

A.

Resource management plan

B.

Transition plan

C.

Communications management plan

D.

Benefits management plan

Buy Now
Question # 46

Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?

Options:

A.

Fallback plan

B.

Risk response plan

C.

Mitigation management plan

D.

Mitigation plan

Buy Now
Question # 47

Which of the following statements is most accurate about the critical path?

Options:

A.

The critical path is always one path that shows the project duration.

B.

The critical path has no float.

C.

The critical path is the longest path because it has the most activities.

D.

The critical path reveals which path has the most risk of failure.

Buy Now
Question # 48

After an organization initiates a strategic program, several project managers express interest in joining the program team. The program manager’s supervisor recommends a list of project managers to be part of the team.

What should the program manager do to select the project managers?

Options:

A.

Complete a skill set inventory and select the most suitable resource(s)

B.

Ask interested project managers for their CV or résumé and conduct interviews

C.

Accept the recommendation of the program manager’s supervisor

D.

Contact the human resource manager for project managers’ availability

Buy Now
Question # 49

You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?

Options:

A.

Approved change requests

B.

Communications management plan

C.

Stakeholder analysis charts

D.

Performance reports

Buy Now
Question # 50

You are the program manager for a large program in your matrix organization. You need to define when the resources in your program will be brought into the program and then released from the program so that the project managers, operational managers, and your program team can plan accordingly. What program management plan defines when

resources are needed, how the resources will be obtained, and how the resources may be released from the program?

Options:

A.

Procurement management plan

B.

Resource management plan

C.

Team management plan

D.

Schedule management plan

Buy Now
Question # 51

You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

Options:

A.

.83

B.

-$20,000 C. .91

C.

Negative ten percent

Buy Now
Question # 52

You are a program manager for your organization. You have proposed a program to the management that will last four years and will cost $35 million to create. Management has asked to see the program charter and the proposed costs and benefits of the program.

Management agrees to your program charter and proposed to fund the program in increments at the completion of each milestone. What type of funding does management proposed for this program?

Options:

A.

Tentative

B.

Step funding

C.

Milestone approval

D.

Phase gate estimating

Buy Now
Question # 53

During program execution, a program manager receives feedback from an executive sponsor that some program stakeholders may not understand the intended benefits of the program.

Which will provide the greatest value to clarify stakeholder perceptions?

Options:

A.

Performing a stakeholder analysis

B.

Updating the stakeholder communications requirements

C.

Redistributing the benefits management plan

D.

Redistributing the program charter

Buy Now
Exam Code: PgMP
Exam Name: Program Management Professional (PgMP)
Last Update: Aug 22, 2025
Questions: 452
PgMP pdf

PgMP PDF

$29.75  $84.99
PgMP Engine

PgMP Testing Engine

$33.25  $94.99
PgMP PDF + Engine

PgMP PDF + Testing Engine

$47.25  $134.99