Last Update Apr 11, 2026
Total Questions : 140
With Comprehensive Analysis
Last Update Apr 11, 2026
Total Questions : 140
Certified Contract Manager
Last Update Apr 11, 2026
Total Questions : 140 With Comprehensive Analysis
Why Choose CertsBoard
Customers Passed
FIDIC CCM
Average Score In Real
Exam At Testing Centre
Questions came word by
word from this dump
Try a free demo of our FIDIC CCM PDF and practice exam software before the purchase to get a closer look at practice questions and answers.
We provide up to 3 months of free after-purchase updates so that you get FIDIC CCM practice questions of today and not yesterday.
We have a long list of satisfied customers from multiple countries. Our FIDIC CCM practice questions will certainly assist you to get passing marks on the first attempt.
CertsBoard offers FIDIC CCM PDF questions, web-based and desktop practice tests that are consistently updated.
CertsBoard has a support team to answer your queries 24/7. Contact us if you face login issues, payment and download issues. We will entertain you as soon as possible.
Thousands of customers passed the FIDIC Designing FIDIC Azure Infrastructure Solutions exam by using our product. We ensure that upon using our exam products, you are satisfied.
You are the Contract Manager of the Employer ' s Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer ' s Requirements require that: " the Contractor design in accordance with international and national technical regulations, and standards, [etc.] " .
For piling works, the Employer ' s Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for 200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer ' s Requirements.
In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m. However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding. The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.
As the Employer ' s Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.
In your " Notice of the Employer ' s Representative ' s determination " , what is your determination for the Contractor?
Which two statements are true under the FIDIC Red Book (edition 1999)?
(Choose all of the correct answers — multiple possibilities)
What are two differences between a notice and other communications under the FIDIC Red Book (edition 2017)? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).