Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CCM Exam Dumps - FIDIC Contract Manager Questions and Answers

Question # 4

You are the Contract Manager of the Employer ' s Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer ' s Requirements require that: " the Contractor design in accordance with international and national technical regulations, and standards, [etc.] " .

For piling works, the Employer ' s Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for 200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer ' s Requirements.

In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m. However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding. The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.

As the Employer ' s Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.

In your " Notice of the Employer ' s Representative ' s determination " , what is your determination for the Contractor?

Options:

A.

The Contractor is not entitled to either of the Claims.

B.

The Contractor is entitled to the Claim for additional costs in relation to the piling, based on errors in the Employer ' s Requirement only.

C.

The Contractor is entitled to the Claim for the additional flood wall based on Unforeseeable difficulties only.

D.

The Contractor is entitled to both Claims.

Buy Now
Question # 5

Which two statements are true under the FIDIC Red Book (edition 1999)?

(Choose all of the correct answers — multiple possibilities)

Options:

A.

The Performance Certificate is deemed to constitute the acceptance of the Works.

B.

The Performance Certificate constitutes acceptance of the Works and full performance of all obligations of each Party.

C.

The Engineer shall issue the Performance Certificate within 28 days at the latest: by the end of the Defects Notification Periods, and once the Contractor has supplied all the Contractor ' s Documents and completed and tested all Works including remedying any defects in accordance with the Contract.

D.

The Performance Certificate is deemed to be issued on fulfilment of certain conditions stated in the respective Sub-Clause.

Buy Now
Question # 6

What are two differences between a notice and other communications under the FIDIC Red Book (edition 2017)? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Notice is a defined term, while other communications are not defined as a term in the General Conditions.

B.

Contractually there is no difference between a notice and other communications.

C.

Both ' Notice ' and ' Other Communications ' are defined terms under the Conditions of Contract.

D.

The Parties and Engineer shall be given original or copy of any Notice, Notice of Dissatisfaction (NOD) and Certificates, which is not always the case for other communications.

Buy Now
Question # 7

A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Question # 8

Under the FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the initial time Programme?

Options:

A.

The date on which the right of access to and possession of (each part of) the Site is to be given to the Contractor.

B.

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.

The sequence and timing of the remedial work.

D.

All key delivery dates of Plant and Materials.

Buy Now
Question # 9

(In a region experiencing civil unrest and armed conflict under a FIDIC Red Book 1999 Contract, violence escalates into an insurrection, forcing the Contractor to stop work and retreat to a secured compound. The Contractor issues a notice claiming this is an Employer’s Risk under Sub-Clause 17.3 (a) and (b), requesting Extension of Time and Cost. What is the most appropriate position for the Engineer at this stage?)

Options:

A.

This is an Employer’s Risk under Sub-Clause 17.3 (a)/(b), and the Contractor is entitled to EOT and Cost. The Engineer will assess actual entitlement after the event; no further notices are required.

B.

Violence is an Employer’s Risk; however, the Contractor can only claim after the situation ends. The Engineer cannot determine EOT or Cost yet, and the Contractor must submit a fully detailed claim later.

C.

The Contractor should have foreseen such risks due to the region’s history; therefore, Clause 19 is not applicable.

D.

The Employer is in breach of its obligation to provide safe working conditions under Sub-Clause 2.1; therefore, the Contractor can claim on that basis.

Buy Now
Question # 10

(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)

Options:

A.

The Employer and the Contractor have identified an issue and disagreement, and have agreed between themselves that they want the DAAB to provide assistance and/or informally discuss and attempt to resolve that issue/disagreement.

B.

The Engineer has made a non-objection letter, in which it is stated that the issue/disagreement does not concern the matter that is being dealt with by the Engineer.

C.

The Employer and the Contractor have made a " joint request " in writing before the DAAB gives the requested assistance.

D.

Both Parties should be present at the meeting in which the DAAB provides assistance.

Buy Now
Question # 11

Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Question # 12

The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.

Options:

A.

True

B.

False

Buy Now
Question # 13

Choose which one statement consists of an example of an unclear and ambiguously drafted Particular Conditions.

Options:

A.

Provisions of the General Conditions are deleted and replaced in the Particular Conditions solely by the words " not used " .

B.

All deletions of a General Conditions are replaced with new Particular Conditions that cover the same scope.

C.

Clarifications to the meaning of tender documents together with answers to tenderers ' inquiries made during the tender period by the Employer should be e-mailed in a Excel table in both PDF and XLS file format.

D.

The clarifications to the Contract given during the tender period are never to be attached to the Contract, as such clarifications are reflected by amending the Particular Conditions.

Buy Now
Exam Code: CCM
Exam Name: Certified Contract Manager
Last Update: Apr 5, 2026
Questions: 140
CCM pdf

CCM PDF

$25.5  $84.99
CCM Engine

CCM Testing Engine

$28.5  $94.99
CCM PDF + Engine

CCM PDF + Testing Engine

$40.5  $134.99