Summer Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: dealsixty

APM-PFQ Exam Dumps - APM Project Fundamentals Qualification Questions and Answers

Question # 54

What information would be expected as content for a business case?

Options:

A.

A. detailed schedule of the project.

B.

An outline of the project management team.

C.

An outline of the estimated costs of implementing the project.

D.

detailed breakdown of the scope of the project.

Buy Now
Question # 55

The definition of benefits management includes which key activities?

Options:

A.

Planning, analysis and integration of project benefits.

B.

Justification, validation and acceptance of project benefits.

C.

Identification, tracking and realisation of project benefits.

D.

Realisation, acceptance and integration of project benefits

Buy Now
Question # 56

Which of the following defines the term 'deployment baseline'?

Options:

A.

The starting point for creating a resource histogram.

B.

The basis for creating an organisational breakdown structure.

C.

The starting point for the monitoring of project risks.

D.

The basis for progress monitoring.

Buy Now
Question # 57

Suppliers are stakeholders of a project management plan because they:

Options:

A.

contribute to the project's procurement strategy.

B.

help satisfy the project's resource requirements.

C.

provide acceptance certificates based on quality of resources supplied.

D.

determine the quality requirements of goods supplied.

Buy Now
Question # 58

Which of the following is not a key element of project scope management?

Options:

A.

Define outputs.

B.

Identify outputs.

C.

Share outputs.

D.

Control outputs

Buy Now
Question # 59

What is an example of a project management office activity that would be most likely undertaken to support a project?

Options:

A.

Developing the project management plan.

B.

Developing the business case.

C.

Carrying out A. health check.

D Carrying out day-to-day resource management.

Buy Now
Question # 60

An important aim of a post-project review is to:

Options:

A.

validate overall progress to date against the budget and schedule.

B.

capture learning and document it for future usage.

C.

ensure acceptance of all permanent documentation, signed by the sponsor.

D.

establish that project benefits have been identified.

Buy Now
Question # 61

One benefit of a gate review process is:

Options:

A.

it allows learning from one phase of the project to be passed on to the next phase.

B.

it stops projects that no longer meet the organisation's needs.

C.

it allows procurement to be planned into the project life cycle.

D.

it allows the project team to plan delivery of the next phase

Buy Now
Question # 62

When no other changes are being considered to the project, this is usually termed as a:

Options:

A.

scope verification.

B.

change freeze.

C.

consolidated baseline.

D.

configuration control.

Buy Now
Question # 63

What is the estimating method that uses data from a similar project as the basis for the estimate?

Options:

A.

Evaluative estimating.

B.

Risk based estimating.

C.

Analogous estimating.

D.

Analytical estimating.

Buy Now
Exam Code: APM-PFQ
Exam Name: APM Project Fundamentals Qualification (PFQ)
Last Update: Jun 15, 2025
Questions: 409
APM-PFQ pdf

APM-PFQ PDF

$34  $84.99
APM-PFQ Engine

APM-PFQ Testing Engine

$38  $94.99
APM-PFQ PDF + Engine

APM-PFQ PDF + Testing Engine

$54  $134.99