Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CCM Exam Dumps - FIDIC Contract Manager Questions and Answers

Question # 14

(Regarding the FIDIC Red Book (edition 2017): what two answers provide for requirements regarding a notice and other communication?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

If a form of communication is to qualify as a Notice, it must be identified as a notice.

B.

If the recipient ' s address differs from the address stated in the Contract Data, notices and other communications may be delivered to that other correct address.

C.

If a form of communication does not qualify as a notice but as other communication, it must be identified as such and shall include reference of provision of Contract under which it is issued (if appropriate).

D.

Notices and other communications shall be delivered to the address of the Contractor ' s Representative.

Buy Now
Question # 15

Which of the following situations form legally binding contracts? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities)

Options:

A.

The Employer received the Contractor ' s Letter of Tender and issued a Letter of Intent.

B.

The Employer and the Contractor signed the Contract Agreement.

C.

The Employer received the Contractor ' s Letter of Tender and issued a conditional Letter of Acceptance.

D.

The Employer received the Contractor ' s Letter of Tender and issued Letter of Acceptance.

Buy Now
Question # 16

Which one of the following claim events does NOT allow profit?

Options:

A.

Under the Construction Contract, interference by the Employer with Tests on Completion.

B.

Under the Construction Contract, the Engineer ' s delay in supplying drawings or issuing instructions.

C.

Under the Construction Contract, the failure of the Employer to give right of access to the site.

D.

Under the Construction Contract, the relevant authority had unnecessarily delayed the approval.

E.

Under the Plant and Design-Build Contract, errors in the Employer ' s requirements.

Buy Now
Question # 17

A large sewage pump installation has been constructed under the FIDIC Yellow Book (edition 1999). Prior to commencement of the Tests on Completion, the Employer requires the Contractor to issue the Operation and Maintained Manuals. All contract documents are to be drafted in the English language as per Sub-Clause 1.4. However, the Employer discovers all documents are drafted in a different language: French. The Contractor explains that the territory where the Plant was constructed is a region with French as a second official language, as result of which, this approach is acceptable. This also works for the proposed maintenance company, which is Paris-based. The Employer is surprised and asks you what to do. Select the best fitting advice you should give the Employer.

Options:

A.

The Employer should check on the Appendix to Tender, Employer ' s Requirements and / or Particular Conditions. There could very well be specific requirements regarding the language in those. If that is not the case, the language of the Contract determined in Sub-Clause 1.4 and the language of the Operation and Maintained Manuals should in this case be English.

B.

If French is indeed an official second language of the region where the Plant is built, the Contractor is entitled to deliver the documents in French. The usability in terms of language is not described in Sub-Clause 5.7, so the Employer should accept the Operation and Mantained Manuals in French.

C.

Golden Principle no. 1 states: The duties, rights, obligations, roles and responsibilities of all the Contract Participants must be generally as implied in the General Conditions, and appropriate to the requirements of the project. In this case this means it is appropriate that the Operation and Maintenance Manuals are in French, as the maintenance is based in France.

D.

As the Contract is written in the English language, Sub-Clause 1.4 dictates that the Operation and Maintenance Manuals should be written in English as well.

Buy Now
Question # 18

Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?

Options:

A.

A declaration of joint and several liability

B.

A bank guarantee

C.

A surety bond

D.

A parent company guarantee

Buy Now
Question # 19

A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?

Options:

A.

If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.

B.

The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.

C.

In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.

D.

If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.

Buy Now
Question # 20

If a FIDIC Red, Yellow, or Silver Book (edition 2017) is applied, in which of the following two cases is the Contractor required to submit a revised programme?

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor shall revise the Programme only by request from the Engineer or the Employer (in case of FIDIC Silver Book).

B.

To accurately reflect the actual progress of the Works, but only if any Programme ceases to reflect actual progress with at least 42 days.

C.

To accurately reflect the actual progress of the Works, whenever any Programme ceases to reflect actual progress or is otherwise inconsistent with the Contractor ' s obligations.

D.

Upon a request from the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) notifying it that the Programme fails to comply with the Contract, to a specified extent, or no longer reflects actual progress or is otherwise inconsistent with the Contractor ' s obligations.

Buy Now
Question # 21

Regarding the FIDIC Red Book (edition 1999), which two statements are true?

Options:

A.

In emergency situations notices can also be submitted verbally (rather than (also) in writing).

B.

A notice is to be signed by the Engineer, Contractor ' s Representative or Employer ' s Authorised Representative.

C.

A notice and other communications may be delivered by hand, courier and mail. In each case with proof of receipt is required to qualify as legally valid.

D.

Notices and other communications may be sent in hand written, type written, in print or through an electronic original transmission system.

Buy Now
Question # 22

(Which of the following types of insurances belong to the basic (typical) scope of insurances? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).)

Options:

A.

Injury to persons and damage to property.

B.

Force Majeure Insurance.

C.

Insurance of Goods and other things brought to Site.

D.

Insurance for non-performance of the Works.

Buy Now
Question # 23

Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal through the Contractor ' s Proposal. Which two of the following statements are true in this respect, after it has been submitted?

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor is entitled to change the design by optimising the design, without approval of the Employer/Engineer.

B.

The Contractor is not allowed to make any changes regarding the design to optimise the design, unless approved by the Engineer/Employer.

C.

The Contractor may submit a proposal for Value Engineering.

D.

The Contractor is not allowed to submit a proposal for Value Engineering, as any value engineering should already have taken place before submitting its design proposal.

Buy Now
Exam Code: CCM
Exam Name: Certified Contract Manager
Last Update: Apr 5, 2026
Questions: 140
CCM pdf

CCM PDF

$25.5  $84.99
CCM Engine

CCM Testing Engine

$28.5  $94.99
CCM PDF + Engine

CCM PDF + Testing Engine

$40.5  $134.99