Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CCM Exam Dumps - FIDIC Contract Manager Questions and Answers

Question # 34

Both FIDIC Silver Book (SB) and Yellow Book (YB) (edition 1999) mention the Contractor scrutinising the Employer ' s Requirements. Which statement is correct?

Options:

A.

Scrutinising in FIDIC Yellow Book 1999 and Silver Book 1999 means that the Contractor must ask the Employer to check the Employer ' s Requirements very well to see if the Works can be built on that location according to the Employer ' s Requirements.

B.

Scrutinising in FIDIC Silver Book 1999 means that the Contractor should read the Employer ' s Requirements very thoroughly after the contract closes and see if the Employer ' s Requirements is complete or if something is missing.

C.

Scrutinising in FIDIC Yellow Book 1999 means the same as in FIDIC Silver Book 1999. In both models it means that after the contract closes and before starting the actual making of the design, the Contractor has to read the Employer ' s Requirements very thoroughly and check on any errors, omissions or conflicts.

D.

Scrutinising in FIDIC Yellow Book 1999 means that the Contractor has the opportunity after contract close to report on any errors, mistakes or conflicts in the Employer ' s Requirements. In the FIDIC Silver Book 1999 scrutinising provides that obligation during the tender period; Contractor has the opportunity to report on any errors, mistakes or conflicts in the Employer ' s Requirements and for Employer to change it; for after contract cl

Buy Now
Question # 35

You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter?

Options:

A.

Each index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works.

B.

The current index or price.

C.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever is more favourable to the Employer.

D.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever agreed by Parties.

Buy Now
Question # 36

In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions]

Choose all of the correct answers (multiple possibilities).

Options:

A.

... the Contractor may send a Notice to the Engineer, that the subject of the Variation was Unforeseeable (having regard to the scope and nature of the Works), hence, the Contractor is not to start implementing the varied work promptly.

B.

... the Contractor is required to commence implementing the varied works and take records of all the details ( ... regarding the details of the varied works executed, expenditures incurred, and impact on progress etc.)

C.

... the Contractor is required to commence implementing the varied works even if it would pose immediate hazard to the safety of public areas surrounding the Site

D.

... the Contractor within 28 days after receiving such instruction shall submit to the Engineer a description of the varied work, a programme for its execution and a proposal for adjustment of the Contract Price.

E.

... the Contractor is not bound to start implementing the varied works right up until the price for the varied works is fully agreed (or determined)

Buy Now
Question # 37

(Under the FIDIC Red, Yellow, and Silver Books (edition 1999), which of the following entitlements of the Employer can result in a deduction of the Contract Price and Payment Certificates subject to Sub-Clause 2.5? (2 correct answers apply))

Options:

A.

Paying the Nominated Subcontractor directly.

B.

Compensation for the costs of the initial review of the Contractor ' s Documents.

C.

Delay Damages.

D.

Cost of using the Employer ' s materials.

Buy Now
Question # 38

You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer ' s claim on Delay Damages. You have asked Y to consider whether the Contractor ' s delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor ' s payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?

Options:

A.

Both you and Y are both correct.

B.

You are correct, Y is wrong.

C.

You are wrong, Y is correct.

D.

Both you and Y are wrong.

Buy Now
Question # 39

(Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then… [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies))

Options:

A.

The Contractor shall submit a Notice to the Engineer or the Employer reminding him to give its approval on the revised programme.

B.

The Engineer shall be deemed to have given a Consent and the revised programme shall be the Programme.

C.

The Contractor cannot proceed in accordance with the Programme.

D.

The Engineer is deemed to have no objection to use the revised Programme for the Works.

Buy Now
Question # 40

(Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to give notice to the Employer if it discovers errors or defects of a technical nature. Is this statement true or false?)

Options:

A.

True

B.

False

Buy Now
Question # 41

In the FIDIC Silver Book (edition 1999), if the Employer has instructed the Contractor as per Sub-Clause 8.6 to provide a revised programme to stay within Time of Completion, the Employer can claim additional costs. This only applies if the revised programme is still too slow to complete the Works within the Time for Completion. Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Question # 42

Regarding the FIDIC Red Book (edition 1999): which two statements are true in respect of Building Information Modelling (BIM)?

Choose all of the correct answers (multiple possibilities).

Options:

A.

General Conditions of Contract require the use of BIM.

B.

BIM is one of the digital data technologies used in all aspects of project planning, investigation, design, construction and operation.

C.

BIM is not related to the improvement of quality, accuracy, delivery times and cost savings.

D.

For construction or building projects involving BIM, many Sub-Clauses of FIDIC Red Book (edition 2017) should be thoroughly reviewed when drafting the Particular Conditions.

Buy Now
Question # 43

(Under the FIDIC Yellow Book (edition 1999), any delay caused by Authorities will be considered as a cause of Delay under sub paragraph (b) of Sub-Clause 8.5 under the only condition that the Contractor has diligently followed the procedures laid down by the public authorities in the Country. Is this statement true or false?)

Options:

A.

True

B.

False

Buy Now
Exam Code: CCM
Exam Name: Certified Contract Manager
Last Update: Apr 5, 2026
Questions: 140
CCM pdf

CCM PDF

$25.5  $84.99
CCM Engine

CCM Testing Engine

$28.5  $94.99
CCM PDF + Engine

CCM PDF + Testing Engine

$40.5  $134.99