Question # 24

You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub-Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.

The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.

The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to 10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.

As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your " Notice of the Engineer ' s determination " , what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?

Options:

A.

The Employer is entitled to deduct the amount directly paid.

B.

The Employer is not entitled to deduct the amount directly paid.

Buy Now
Question # 25

Through which two of the following documents may the Employer give information to the Contractor of a planned timetable of meetings such as management meetings, site meetings, technical meetings, and progress meetings?

Choose all of the correct answers (multiple possibilities).

Options:

A.

General Conditions of Contract

B.

Specification

C.

Special Conditions

D.

Employer ' s Requirements

Buy Now
Question # 26

Under the FIDIC Construction Contract (Red Book), which of the following amendments do NOT comply with the FIDIC Golden Principles? [1999 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor is responsible for the performance of the Nominated Subcontractors

B.

Deletion of Sub-Clauses 20.2 - 20.4 for a Project constructed in United Arab Emirates

C.

The DAB Decision is final and binding

D.

The Payment shall be released by the Employer within 180 days calculated from receiving the Contractor ' s Monthly Statement

Buy Now
Question # 27

Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)

Options:

A.

No, according to Sub-Clause 5.7 provisional operation and maintenance manuals are always required.

B.

No, because the Contractor has a duty to supply the Employer with every Document, given Sub-Clause 7.4.

C.

Yes, because otherwise the Contractor doesn ' t have to submit any Document until Completion of the Works as stated in Sub-Clause 1.8.

D.

Yes, the Employer should define which documents it wants to receive from the Contractor as Contractor ' s Documents in the Employer ' s Requirements, as stated in Sub-Clause 5.2.

Buy Now
Question # 28

Towards the end of implementing a varied work (initiated originally by the Contractor as a " Value Engineering Proposal " , relevant designs provided by the Contractor) it turned out, that there is some part of it not complying with the otherwise prevailing standards. Which statements are correct in this situation? [FIDIC Red Book, 2017 Edition]

Choose all of the correct answers (multiple possibilities).

Options:

A.

Since the design was approved by the Engineer, the Contractor might not be found responsible for such discrepancy, hence, to be fully compensated.

B.

In this situation, the whole of the varied works should be removed, and the original technical content reinstated.

C.

The Contractor shall immediately rectify, ensuring, that the varied work fully complies with the prevailing standards.

D.

In case it is necessary, the Contractor shall prepare designs for works subject to the Value Engineering, hence, it is up to the Contractor to ensure that the works are fit for the purposes, including that the designs are correct, regardless of any approval or " no-objection " of the Engineer.

Buy Now
Question # 29

The FIDIC Books are evolutions of earlier contract models, and although the different versions of a specific model are not the same, familiarity in definitions and structure makes it easier to work with different FIDIC books as well as with their different editions.

Is this statement true or false?

Options:

A.

True

B.

False

Buy Now
Question # 30

There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.

Which two of the following statements are NOT applicable reasons?

(Choose all correct answers — multiple possibilities)

Options:

A.

Delay the execution of the Works or a Section.

B.

Decrease the Contract Price.

C.

Adversely affect the work of the Contractor ' s Personnel.

D.

Increase the performance of the Works when completed.

Buy Now
Question # 31

In a drafted FIDIC Silver Book (edition 1999), the following sentence has been added to Sub-Clause 3.5:

" In case of an Instruction regarding a pending or proposed Variation, Contractor shall carry out any determination regardless of a possible notice of dissatisfaction. "

What GP(s) is/are breached?

Options:

A.

GP1 only

B.

GP3 only

C.

GP1 and GP3

D.

GP1, GP2 and GP3

Buy Now
Question # 32

(The Employer is a leading company in the hospital and medical care sector who wishes to build a new hospital. The Employer is considering approaching a financial institute to secure most of the funds; therefore, he requires clarity and stability in terms of the Project ' s budget and time for completion. Which book do you recommend?)

Options:

A.

Red Book

B.

Yellow Book

C.

Silver Book

D.

All the above

Buy Now
Question # 33

(If a Section or Part has been taken-over but the Taking-Over Certificate has not been issued for the Works, the Engineer has the right to instruct a Variation to that Section/Part. Is this statement true or false?)

Options:

A.

True

B.

False

Buy Now
Exam Code: CCM
Exam Name: Certified Contract Manager
Last Update: Apr 5, 2026
Questions: 140
CCM pdf

CCM PDF

$25.5  $84.99
CCM Engine

CCM Testing Engine

$28.5  $94.99
CCM PDF + Engine

CCM PDF + Testing Engine

$40.5  $134.99