Weekend Sale Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

ISEB-PM1 Exam Results

Page: 19 / 23
Question 76

Which analysis uses beta and triangular distributions as a tool and technique?

Options:

A.

Quantitative risk analysis

B.

Qualitative risk analysis

C.

Perform quality assurance

D.

Perform quality control

Question 77

What is one of the KEY objectives during contract negotiations?

Options:

A.

Obtain a fair and reasonable price.

B.

Negotiate a price under the seller's estimate.

C.

Ensure that all project risks are thoroughly delineated.

D.

Ensure that an effective communications management plan is established.

Question 78

In a control chart, the consecutive measurements are 11, 13, 09, 07, 08, 09, 09, 09, 08, and 12. For the entire process, the goal is 10 and the standard deviation is 1.

For this data set, it is correct to say that the process:

Options:

A.

is under control.

B.

is out of control.

C.

has an increasing trend.

D.

has a decreasing trend.

Question 79

Which quality assurance tool and technique confirms the implementation of approved change requests, corrective actions, defect repairs, and preventive actions?

Options:

A.

Quality checklists

B.

Quality metrics

C.

Quality audits

D.

Process analysis

Page: 19 / 23
Exam Code: ISEB-PM1
Exam Name: BCS Foundation Certificate in IS Project Management
Last Update: May 16, 2024
Questions: 625
ISEB-PM1 pdf

ISEB-PM1 PDF

$28  $80
ISEB-PM1 Engine

ISEB-PM1 Testing Engine

$33.25  $95
ISEB-PM1 PDF + Engine

ISEB-PM1 PDF + Testing Engine

$45.5  $130