Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PK0-005 Exam Dumps - CompTIA Project+ Questions and Answers

Question # 14

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

Options:

A.

Executing the approved contingency plan

B.

Constructing an Ishikawa diagram to determine the root cause

C.

Using a Pareto chart to prioritize the different causes

D.

Engaging the senior management team in regard to the issue

Buy Now
Question # 15

A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?

Options:

A.

Update the risk register.

B.

Escalate the issue for exceptional approval.

C.

Communicate to the stakeholders.

D.

Submit a duplicate change request.

Buy Now
Question # 16

A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?

Options:

A.

Informal communication

B.

Formal communication

C.

Synchronous communication

D.

Asynchronous communication

Buy Now
Question # 17

During a phase review, two stakeholders discuss the approval of a deliverable. The project manager convinces the stakeholders to agree on a common solution. Which of the following best describes what the project manager did to gain approval from both stakeholders?

Options:

A.

Force

B.

Smooth

C.

Compromise

D.

Avoid

Buy Now
Question # 18

Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?

Options:

A.

Assign action items to attendees.

B.

Distribute an agenda.

C.

Email the minutes from the previous meeting.

D.

Schedule a convenient time.

Buy Now
Question # 19

A project stakeholder has asked the project manager to provide the performance data of a project. Which of the following should the project manager send to the stakeholder?

Options:

A.

Issue log

B.

Dashboard

C.

WBS

D.

Milestone chart

Buy Now
Question # 20

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

Options:

A.

Assign a scribe to take notes.

B.

Record the meeting and transcribe the notes later.

C.

Instruct each team member to take notes.

D.

Get a facilitator for the meetings.

Buy Now
Question # 21

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

Options:

A.

Software as a service

B.

Infrastructure as a service

C.

Data as a service

D.

Platform as a service

Buy Now
Question # 22

During project initiation, a project manager is drafting a document that includes an outline of the high-level goals, objectives, milestones, and requirements. This document will be modified and finalized as more information becomes available. Which of the following best meets the requirements?

Options:

A.

Preliminary scope statement

B.

Procurement needs assessment

C.

Project success criteria

D.

Work breakdown structure

Buy Now
Question # 23

A software engineer notices that the newest update to the reporting software includes many new features that were not defined in the requirements document. Which of the following steps should the engineer take next?

Options:

A.

Seek approval before continuing

B.

Edit the requirements document

C.

Disregard the update

D.

Notify the users of the new features

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2025)
Last Update: Oct 2, 2025
Questions: 386
PK0-005 pdf

PK0-005 PDF

$29.75  $84.99
PK0-005 Engine

PK0-005 Testing Engine

$33.25  $94.99
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$47.25  $134.99