Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PK0-005 Exam Dumps - CompTIA Project+ Questions and Answers

Question # 14

A project manager must determine how ideas from the organization and results from the review committee should move through the enterprise for a new project. Which of the following does the project manager need to do?

Options:

A.

Establish communication channels

B.

Plan a kickoff meeting

C.

Develop a responsibility assignment matrix

D.

Identify the stakeholders

Buy Now
Question # 15

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

Options:

A.

Executing the approved contingency plan

B.

Constructing an Ishikawa diagram to determine the root cause

C.

Using a Pareto chart to prioritize the different causes

D.

Engaging the senior management team in regard to the issue

Buy Now
Question # 16

Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?

Options:

A.

Update the issue log.

B.

Apply the contingency plan.

C.

Transfer the risk.

D.

Submit a change request.

Buy Now
Question # 17

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

Options:

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

14 days and $4,000

Buy Now
Question # 18

A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).

Options:

A.

Company vision

B.

Global environment

C.

Brand value

D.

Mission statement

E.

Portfolio budget

F.

Local legislation

Buy Now
Question # 19

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

Options:

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

Buy Now
Question # 20

During an active project, the finished product is not meeting quality specifications Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?

Options:

A.

Communicate the change status.

B.

Document change recommendations

C.

Create a change request.

D.

Implement the changes

Buy Now
Question # 21

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

Options:

A.

Inform the CCB to stop communication.

B.

Establish a RACI matrix.

C.

Escalate the communication issues.

D.

Revise the communication plan.

Buy Now
Question # 22

Which of the following is the most important activity for the project manager during the closure of a project?

Options:

A.

Obtain project sign-off.

B.

Capture lessons learned.

C.

Document historical information.

D.

Release resources.

Buy Now
Question # 23

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

Options:

A.

Rollback plan

B.

Downtime stage

C.

Maintenance window

D.

Validation checks

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2026)
Last Update: Mar 11, 2026
Questions: 447
PK0-005 pdf

PK0-005 PDF

$25.5  $84.99
PK0-005 Engine

PK0-005 Testing Engine

$28.5  $94.99
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$40.5  $134.99