Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PK0-005 Exam Dumps - CompTIA Project+ Questions and Answers

Question # 24

Project A is running behind schedule. The team realizes that Project B is working on an API that was planned to be developed by Project A. The project manager from Project A decides to use the API from Project B. Which of the following risk management strategies describes this example?

Options:

A.

Exploit

B.

Share

C.

Transfer

D.

Accept

Buy Now
Question # 25

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

Options:

A.

Issue log

B.

Defect log

C.

Change log

D.

Task board

Buy Now
Question # 26

Which of the following would help a project manager identify that project goals have been reached?

Options:

A.

Audit report

B.

Key performance indicators

C.

Backlog

D.

Lessons learned

Buy Now
Question # 27

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

Options:

A.

Agile

B.

Waterfall

C.

Standard

D.

Hybrid

Buy Now
Question # 28

A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?

Options:

A.

Request a change control ticket.

B.

Review the schedule plan.

C.

Refine the project documentation.

D.

Revise the communication plan.

Buy Now
Question # 29

Which of the following concepts represents multiple resources interfaced to run reports?

Options:

A.

Code repository

B.

Data warehouse

C.

Storage server

D.

File-sharing system

Buy Now
Question # 30

During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:

Average worked hours

Which of the following describes the result?

Options:

A.

A negative correlation exists between the number of mistakes and the working hours.

B.

No correlation exists between the number of mistakes and the working hours.

C.

A low correlation exists between the working hours and the number of mistakes.

D.

A positive correlation exists between the number of mistakes and the working hours.

Buy Now
Question # 31

A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

Options:

A.

Data plan

B.

Contingency plan

C.

Rollback plan

D.

Recovery plan

Buy Now
Question # 32

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?

Options:

A.

Architect

B.

Project sponsor

C.

Scrum master

D.

Product owner

Buy Now
Question # 33

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Which of the following issues should be addressed FIRST?

Options:

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2026)
Last Update: Mar 11, 2026
Questions: 447
PK0-005 pdf

PK0-005 PDF

$25.5  $84.99
PK0-005 Engine

PK0-005 Testing Engine

$28.5  $94.99
PK0-005 PDF + Engine

PK0-005 PDF + Testing Engine

$40.5  $134.99