Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMI-RMP Exam Dumps - PMI Certification Questions and Answers

Question # 4

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

Options:

A.

Strengths, weakness, opportunities, and threats (SWOT) analysis

B.

Delphi technique

C.

Decision tree analysis

D.

Probability impact matrix

Buy Now
Question # 5

A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?

Options:

A.

US$20.000 loss

B.

US$20,000 profit

C.

US$40,000 loss

D.

US$100,000 profit

Buy Now
Question # 6

When performing a risk analysis, a risk manager identifies not only negative risks but also positive risks, which might bring added value to the project. What should the risk manager do next?

Options:

A.

Prioritize opportunities as they are likely to bring benefits to the project.

B.

Analyze the risks and add them to the risk register to continue the process.

C.

Create a separate project to exclusively manage positive risks and threats.

D.

Assign separate stakeholder groups for positive risks and negative risks.

Buy Now
Question # 7

A company in the mining industry accommodates a lot of innovation and changing work conditions. Because of this, the company experiences difficulty in predicting long term business plans.

How should a professional risk manager manage the risks in such situations?

Options:

A.

Adopt a predictive approach to manage the risks.

B.

Adopt agile approaches to manage the risks.

C.

Utilize proper documentation to help manage the risks.

D.

Conduct weekly risk management meetings with all stakeholders.

Buy Now
Question # 8

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.

Risk assessment criteria

B.

Project management plan

C.

Project assumptions

D.

Risk management plan 

Buy Now
Question # 9

A software company has recently completed a project that delivered a new web application. Throughout the project, several issues were realized that resulted in cost and schedule overruns. The project ' s executive sponsor has requested a deep-dive into what went wrong since the company will be developing additional web applications in the future.

What should the risk manager do?

Options:

A.

Gather the project ' s status reports and meeting minutes to determine when issues occurred and how quickly the issues were addressed.

B.

Conduct a retrospective meeting with stakeholders and inquire about what went well and what could be improved on future projects.

C.

Work with the project manager to determine if additional resources could have prevented or mitigated the issues that arose on the project.

D.

Review the project ' s risk register and determine how comprehensive and effective each risk and issue response was.

Buy Now
Question # 10

A project has a significant impact on an organization. Multiple stakeholders expressed concerns regarding the overall project risk during construction of the risk management plan, and they agreed that the risk appetite is low.

What should the project risk manager monitor closely?

Options:

A.

Risk thresholds

B.

Risk response strategies

C.

Risk management reports

D.

Risk breakdown structure (RBS)

Buy Now
Question # 11

A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether.

What should the risk manager do in this situation?

Options:

A.

Accept the response because there are no secondary risks were identified.

B.

The response plan should be discontinued and the risk should be accepted and dealt with if it occurs.

C.

Accept the residual risk as it is compatible with the organization ' s risk appetite.

D.

All identified risks must be addressed because they might significantly impact the project if they occur. 

Buy Now
Question # 12

A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.

What should the risk manager do first?

Options:

A.

Perform an assumptions and constraints analysis.

B.

Use the Wideband Delphi method.

C.

Use the brainstorming technique.

D.

Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis. 

Buy Now
Question # 13

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project ' s risk register and asks the risk manager for an analysis of its effectiveness.

What two actions should the risk manager do next? (Choose two.)

Options:

A.

Check to ensure that the risk is supported by a Monte Carlo simul-ation.

B.

Check to ensure that the risks are gathered using Delphi technique.

C.

Check for risk classification and that probability and impact are identified.

D.

Check to ensure that risk origin, triggering event, and ownership is identified.

E.

Check to ensure the risk meeting agenda and supporting documents are distributed.

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Apr 6, 2026
Questions: 278
PMI-RMP pdf

PMI-RMP PDF

$25.5  $84.99
PMI-RMP Engine

PMI-RMP Testing Engine

$28.5  $94.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$40.5  $134.99