Question # 24

A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.

What should the risk manager do first?

Options:

A.

Develop a residual risk management plan to manage the residual risks.

B.

Analyze, document, and communicate the residual risks to stakeholders.

C.

Record the residual risks in the watch list for future reference.

D.

Implement the contingency plan when the residual risks occur.

Buy Now
Question # 25

During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be

mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.

Which action should the risk manager take to address this risk?

Options:

A.

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.

B.

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder's team.

C.

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.

D.

Add the identified risk to the risk register for future probability and impact analysis.

Buy Now
Question # 26

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board's response?

Options:

A.

Engaging the key stakeholders during the prioritization process

B.

Prioritizing the risks based on the project sponsor's risk appetite

C.

Engaging with the project sponsor before presenting to the board

D.

Working with an established industry standard prioritization method

Buy Now
Question # 27

A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer’s requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this.

What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?

Options:

A.

Release this version and leave changes to be done at the end of the project phase.

B.

Arrange a workshop where all ideas will be discussed and take corrective actions ensuring value delivery.

C.

Ask the development team to brainstorm and come up with suggestions that will improve the delivery date.

D.

Run a spike, identify what went wrong during implementation, and request a change to enhance value delivery.

Buy Now
Question # 28

During a project's initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk's likelihood and impact with the risk manager.

What should the risk manager do?

Options:

A.

Assume the vendor will deliver on time and focus only on internal risks.

B.

Allocate contingency funds without first evaluating the risk's probability and impact.

C.

Wait indefinitely for the vendor's update before analyzing the risk.

D.

Assess the risk using a probability-impact matrix and prioritize it based on its score.

Buy Now
Question # 29

The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

What is this an example of?

Options:

A.

Risk responses

B.

Risk triggers

C.

Risk registers

D.

Risk categories

Buy Now
Question # 30

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.

How should the risk manager interpret such a low CPI value?

Options:

A.

The cost control processes is ineffective.

B.

The cost baseline is inaccurate.

C.

The actual reported costs are inaccurate.

D.

The cost related risks are effectively managed.

Buy Now
Question # 31

During the project's lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?

Options:

A.

Carry out the agreed risk response action should the risk occur.

B.

Provide a numerical estimate of the overall effect of risk on the objectives.

C.

Track identified risks and maintain the viability of response plans.

D.

Develop the overall risk management strategy for risk integration. 

Buy Now
Question # 32

During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.

What could have been done during project planning to avoid overspending?

Options:

A.

Met weekly with the finance team to monitor the cost

B.

Communicated with the stakeholders that the project costs might increase

C.

Properly documented the triggers and actions for the risk

D.

Engaged with the sponsor to buy the steel in advance of the project 

Buy Now
Question # 33

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

Options:

A.

Wait until the weather improves before sending the equipment.

B.

Ask the project sponsor to approve shipping the equipment.

C.

Proceed with the planned risk response to move the equipment.

D.

Request the shipment of the equipment to satisfy the client.

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Aug 22, 2025
Questions: 264
PMI-RMP pdf

PMI-RMP PDF

$29.75  $84.99
PMI-RMP Engine

PMI-RMP Testing Engine

$33.25  $94.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$47.25  $134.99