Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMI-RMP Exam Dumps - PMI Certification Questions and Answers

Question # 34

When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

Options:

A.

Select the strategies with the least overall impact to resources.

B.

Select the strategies with the least financial impact.

C.

Select the strategies with the greatest overall positive influence.

D.

Select the strategies with the greatest benefit to stakeholders.

Buy Now
Question # 35

The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X ' s project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X.

How should project X ' s project manager avoid this situation in the future?

Options:

A.

Prepare a contingency response plan to implement when delays occur

B.

Ask the other project manager to officially confirm the new date in writing

C.

Request that the other project manager be added to relevant reports

D.

Request that the other project manager inform if any additional delays are expected

Buy Now
Question # 36

A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.

How should the risk manager address this concern?

Options:

A.

Invite these stakeholders to regular meetings to engage them in the definition of project assumptions.

B.

Identify new stakeholders who might replace those involved thus far and are more closely aligned to the project goals.

C.

Review the risk thresholds to potentially accommodate the concerns raised by these stakeholders.

D.

Perform a stakeholder analysis to determine their interests and how they should be taken into account. 

Buy Now
Question # 37

A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.

What should the risk management professional do next?

Options:

A.

Perform a sensitivity analysis to the higher-level aggregate activities

B.

Develop a risk breakdown structure (RBS) identifying the potential risk categories

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Perform a base line Monte Carlo simul-ation to address overall threats to project objectives

Buy Now
Question # 38

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager ' s department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Options:

A.

Reformed the risk monitoring and closing process properly.

B.

Created the project work plan and budget more accurately.

C.

Educated the project team on budget change requests.

D.

Communicated better with the organization ' s CEO.

Buy Now
Question # 39

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

Options:

A.

Wait until the weather improves before sending the equipment.

B.

Ask the project sponsor to approve shipping the equipment.

C.

Proceed with the planned risk response to move the equipment.

D.

Request the shipment of the equipment to satisfy the client.

Buy Now
Question # 40

A financial service firm adheres to heavily regulated compliance legislation. During the firm ' s latest project, the Chief Financial Officer (CFO) and the Chief Information Officer (CIO) endorsed a risk-based approach. This approach ensured compliance with the legislative requirements for properly storing confidential employee salary information. The risk manager recorded this information in the project ' s risk management plan.

What is the organization ' s risk maturity level?

Options:

A.

No maturity

B.

Low maturity

C.

Medium maturity

D.

High maturity

Buy Now
Question # 41

A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.

Where should the project manager find this information?

Options:

A.

Industrial studies

B.

Commercial risk databases

C.

Organizational process assets (OPAs)

D.

Enterprise environmental factors (EEFs)

Buy Now
Question # 42

A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints

What should the project manager do next to determine risk impact of assumptions and constraints?

Options:

A.

Add all assumptions and constraints to the risk register.

B.

Add the risk impact of the assumptions in the risk register.

C.

Add the assumptions and constraints to the assumption log.

D.

Add the assumptions and constraints in the project charter.

Buy Now
Question # 43

A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.

Which data analysis tool should the risk manager use to forecast future performance?

Options:

A.

Sensitivity analysis

B.

What-if scenario analysis

C.

Regression analysis

D.

Decision tree analysis

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Aug 19, 2026
Questions: 333
PMI-RMP pdf

PMI-RMP PDF

$25.5  $84.99
PMI-RMP Engine

PMI-RMP Testing Engine

$28.5  $94.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$40.5  $134.99