Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PMI-RMP Exam Dumps - PMI Certification Questions and Answers

Question # 64

The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin.

The project manager would like the risk manager to take full advantage of opportunities.

Which response should the risk manager take?

Options:

A.

Mitigate

B.

Accept

C.

Transfer

D.

Exploit

Buy Now
Question # 65

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

Options:

A.

Each cause has a degree of uncertainty

B.

Each cause has well defined owner

C.

The causes represent actual conditions

D.

The causes must be validated by the risk owner

Buy Now
Question # 66

A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue.

What should the risk manager do?

Options:

A.

Execute the risk response plan defined for the risk.

B.

Postpone the software launch to sort out the technical issue.

C.

Assess the impacts and define the response actions with the subject matter experts (SMEs).

D.

Meet with the project manager to revisit the project schedule.

Buy Now
Question # 67

In the early stages of a manufacturing project, a risk manager has identified a risk with a component provided by an external supplier that might be delayed. The delay may or may not be significant to the project.

What should the risk manager do?

Options:

A.

Agree with the external supplier on the timeline.

B.

Register the risk with a medium impact.

C.

Align with stakeholders on the risk threshold.

D.

Engage another supplier with shorter delivery times.

Buy Now
Question # 68

A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.

Which type of analysis should the project manager use in this instance?

Options:

A.

Check list analysis

B.

Cause and effect

C.

Specialized meeting

D.

Quantitative analysis

Buy Now
Question # 69

The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

Options:

A.

Implement the risk response strategies into the risk plan.

B.

Inform the sponsor that these risks should be added according to experience.

C.

Add the risks to the risk register and determine a contingency.

D.

Discuss and evaluate the identified risks with the project team.

Buy Now
Question # 70

When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.

How does centralizing the risk management function help resolve the problem?

Options:

A.

Enhance the process of identification of different Individual project risks.

B.

Allows monitoring the impact against the overall project risk exposure.

C.

Establishes risk sources and ownership for trigger monitoring.

D.

Creates a single repository for all project risk documents.

Buy Now
Question # 71

The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

Options:

A.

Proximity dales for open risks

B.

Backlog of change orders to be submitted to client

C.

Risks that have materialized and the overall risk profile

D.

Number of schedule baseline changes approved

E.

Risks due to the number of claims submitted to the client

Buy Now
Question # 72

During a project's planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.

What should the risk manager document as the risk trigger?

Options:

A.

The probability and impact rating of the supplier's delay on the project

B.

The response strategy, such as increasing inventory or finding an alternative supplier

C.

The specific event or condition, such as the supplier missing a delivery deadline

D.

The threshold for acceptable delay, such as a maximum of three days before impacting project milestones

Buy Now
Question # 73

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

Options:

A.

A potential need to share the space with other machinery

B.

A different type of equipment received before installation

C.

A time delay during air conditioning installation activities

D.

A quality nonconformance issue raised during the inspection

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Aug 22, 2025
Questions: 264
PMI-RMP pdf

PMI-RMP PDF

$29.75  $84.99
PMI-RMP Engine

PMI-RMP Testing Engine

$33.25  $94.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$47.25  $134.99