Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMI-RMP Exam Dumps - PMI Certification Questions and Answers

Question # 64

In the middle of a project to improve internal workflows, the team realizes that some previously identified challenges, such as lack of stakeholder engagement, have diminished. However, the risk manager determines that concerns related to resource availability and regulatory compliance are becoming more significant.

Which measures should the risk manager implement?

Options:

A.

Concentrate on monitoring only high-visibility risks to conserve resources.

B.

Focus on tracking the risks identified at the project ' s start to maintain consistency.

C.

Reassess risk priorities carefully and update the risk register on a regular basis.

D.

Delegate all monitoring responsibilities entirely to individual team members for efficiency.

Buy Now
Question # 65

The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.

What should the project manager do first?

Options:

A.

Include the risk in the register and communicate with the stakeholders.

B.

Communicate with the client to provide the previous shutdown plan.

C.

Review and update the project schedule.

D.

Interview the other project manager to learn more details.

Buy Now
Question # 66

During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.

What should the risk manager do?

Options:

A.

Update the watchlist.

B.

Initiate a risk response when these risks occur.

C.

Address only the high-priority risk.

D.

Perform a risk urgency assessment. 

Buy Now
Question # 67

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

Options:

A.

Identify secondary or residual risks for associated risk plans.

B.

Develop risk response plans for all identified risks.

C.

Update the communications management plan to avoid future issues

D.

Monitor and control secondary and residual risks in the risk register.

Buy Now
Question # 68

The customer expresses concern about the increasing likelihood of delays from one of the subcontractors on the project. This risk was previously identified and planned for during the project planning phase. The project sponsor reassured the customer that this is a known risk and will be handled accordingly by the risk manager.

What should the risk manager do?

Options:

A.

Call an emergency meeting.

B.

Reinforce the customer relationship.

C.

Implement the risk response plan.

D.

Escalate risk to the owner.

Buy Now
Question # 69

In a large enablement project with strict time lines, risks need to be closely monitored. The risk manager publishes reports comparing planned enablement sessions with actual enablement sessions, which help identify potential risks to be addressed.

Which technique is the risk manager using?

Options:

A.

Variance analysis

B.

Residual impact analysis

C.

Sensitivity analysis

D.

Reserve analysis 

Buy Now
Question # 70

Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project ' s risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?

Options:

A.

The risk management plan

B.

The risk triggers

C.

The risk prioritization criteria

D.

The portfolio management plan

Buy Now
Question # 71

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Options:

A.

Review the assumptions analysts

B.

Conduct a checklist analysis on each risk

C.

Create a risk response plan for those risks

D.

Review the risk register to check for the new risks

Buy Now
Question # 72

At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it ' s complete since it is such a short and simple project.

How should the risk manager respond to this comment?

Options:

A.

The risk register must only be updated if a change is approved during the project.

B.

Agree on the condition that the risk register be updated if the project environment changes.

C.

Compromise by updating the risk register at the end of each phase only.

D.

Insist on continuous review and updating of the risk register during the project.

Buy Now
Question # 73

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?

Options:

A.

Ask the team to perform an earned value analysis.

B.

Review the lessons learned from other projects.

C.

Ask the team to prepare a Monte Carlo analysis.

D.

Ask the risk expert to perform a PESTLE evaluation.

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Jul 5, 2026
Questions: 284
PMI-RMP pdf

PMI-RMP PDF

$25.5  $84.99
PMI-RMP Engine

PMI-RMP Testing Engine

$28.5  $94.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$40.5  $134.99