Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMI-RMP Exam Dumps - PMI Certification Questions and Answers

Question # 74

During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

What should the risk manager do to handle this situation?

Options:

A.

Revisit this risk in the risk register and redefine the mitigation strategy.

B.

Activate the contingency plan to handle this risk during execution.

C.

Mark this new risk as an extremely high priority and inform all stakeholders.

D.

Ask the project sponsor for more budget to deal with this risk.

Buy Now
Question # 75

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?

Options:

A.

Escalate the problem to the project sponsors.

B.

Execute the approved risk response plan.

C.

Negotiate with the supplier to resolve the problem.

D.

Assign a team member to update the issue leg.

Buy Now
Question # 76

A project team has failed to complete an important project milestone on time. The team was counting on an external provider to deliver key equipment on a specific date but the provider was delayed.

What should the risk manager have done to prevent missing the milestone?

Options:

A.

Better schedule monitoring and controlling.

B.

Identify and analyze project plan assumptions.

C.

Have a detailed work breakdown structure (WBS).

D.

Use management reserves to cover delays.

Buy Now
Question # 77

A project team is overseeing the construction of a new office building. The project is complex, involving multiple contractors, regulatory requirements, and a tight schedule. During a team meeting, the risk manager realizes that a formal risk identification exercise has not yet been conducted.

Given the project ' s complexity, what should the risk manager do?

Options:

A.

Wait until halfway through the project to identify risks, as most issues will be clear by then.

B.

Conduct the exercise with the key team members, excluding external stakeholders.

C.

Facilitate a risk identification exercise with key stakeholders, considering all factors.

D.

Focus only on identifying the most obvious risks to save time and project resources.

Buy Now
Question # 78

A project ' s design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.

What should the project manager have done differently?

Options:

A.

Executed the Monte Carlo sensitivity analysis prior to mobilization

B.

Added generic construction risks to the risk register before construction began

C.

Reviewed the assumptions/exclusions register in the project charter

D.

Performed risk identification exercises for the full lifecycle of the project

Buy Now
Question # 79

During the project ' s lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?

Options:

A.

Carry out the agreed risk response action should the risk occur.

B.

Provide a numerical estimate of the overall effect of risk on the objectives.

C.

Track identified risks and maintain the viability of response plans.

D.

Develop the overall risk management strategy for risk integration. 

Buy Now
Question # 80

A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite.

What should the risk manager advise the project team to do?

Options:

A.

Align the project risk thresholds with the risk appetite of a critical region.

B.

Align the project risk thresholds with the organizational risk appetite.

C.

Concentrate on the risk appetites of the influential stakeholders.

D.

Concentrate on the risk appetites of the vulnerable stakeholders. 

Buy Now
Question # 81

A risk manager has been assigned to prepare a risk management plan for a new project. Which factor should the risk manager prioritize when tailoring the risk management processes for the new project?

Options:

A.

Available funds for risk management activities

B.

Size and duration of the project

C.

Maturity of the organization ' s risk management processes

D.

Number of stakeholders associated with the project

Buy Now
Question # 82

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.

Who should the project manager hold accountable for missing the risks?

Options:

A.

The audit team

B.

The risk manager

C.

The risk owners

D.

The discipline engineers

Buy Now
Question # 83

During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?

Options:

A.

Utilize a Monte Carlo assessment to provide risk related impacts.

B.

React to the secondary and residual risks only if they occur.

C.

Include secondary and residual risks as part of the response.

D.

Transfer secondary and residual risks to the project sponsor.

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Jul 5, 2026
Questions: 284
PMI-RMP pdf

PMI-RMP PDF

$25.5  $84.99
PMI-RMP Engine

PMI-RMP Testing Engine

$28.5  $94.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$40.5  $134.99