Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMI-RMP Exam Dumps - PMI Certification Questions and Answers

Question # 44

A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the

client ' s vendor, which apparently has been causing all of the issues.

What should the risk manager do first?

Options:

A.

Enhance risk identification.

B.

Review the contingency reserves.

C.

Create a risk response plan.

D.

Review the risk registry.

Buy Now
Question # 45

A project is underway to implement a new customer support software. During testing, the risk manager discovers that the integration with the existing customer relationship management system is more complex than initially planned, potentially delaying the project. The risk manager needs to update project documents to reflect this new infor mation.

Which steps should the risk manager consider when updating relevant project documents?

Options:

A.

Update the issue log with relevant information as the immediate concern for key stakeholders.

B.

Assume the delay will not affect the timeline and continue with the current scheduled activities.

C.

Update the project documents after the work has been completed and formally accepted.

D.

Assess the delay with the technical team, update the schedule and risk register, and inform stakeholders.

Buy Now
Question # 46

The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.

What is this an example of?

Options:

A.

Risk responses

B.

Risk triggers

C.

Risk registers

D.

Risk categories

Buy Now
Question # 47

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Options:

A.

Review the assumptions analysts

B.

Conduct a checklist analysis on each risk

C.

Create a risk response plan for those risks

D.

Review the risk register to check for the new risks

Buy Now
Question # 48

A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.

What three artifacts should the project manager consult or review during this process? (Choose three.)

Options:

A.

Project contracts

B.

Lessons learned registers from analogous projects

C.

Risk register

D.

Risk management plan

E.

Code of regulations

Buy Now
Question # 49

Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?

Options:

A.

Exclude risk averse stakeholders from future risk discussions

B.

Explain risk handling and mitigation strategies

C.

Increase the impact of all risks in the risk breakdown structure (RBS)

D.

Develop a generous probabilistic cash flow model

Buy Now
Question # 50

A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

Options:

A.

Highlight this situation to the project manager

B.

Conduct a cost-benefit analysis

C.

Change the risk response strategy

D.

Analyze the situation and meet with the risk owner

Buy Now
Question # 51

Some issues and unexpected results were found after completing the first phase of a project. The project team is planning the next phase and team members want to avoid the previous issues.

What should the risk manager do to avoid the previous issues?

Options:

A.

Use the information for a risk workshop.

B.

Improve monitoring and controlling of activities.

C.

Document the issues in the lessons learned.

D.

Create an issue log to share with the team.

Buy Now
Question # 52

In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.

How should the project manager address this concern with the health authorities?

Options:

A.

Suspend the project as the secondary risk will negatively impact residents ' health which is not acceptable.

B.

Consult with health experts to provide a risk trigger before using pesticides that will impact the residents.

C.

Assess and record associated secondary risks and proceed to treat them as any other risks.

D.

Proceed with the project as normal since a minor number of residents will be effected negatively.

Buy Now
Question # 53

Business rhythm can fluctuate greatly between different industries and vary between companies within the same industry. What should be used 10 determine how often a project ' s risk register should be updated or reviewed in a given year when the project is in an industry with a very high business rhythm?

Options:

A.

The risk management plan

B.

The risk triggers

C.

The risk prioritization criteria

D.

The portfolio management plan

Buy Now
Exam Code: PMI-RMP
Exam Name: PMI Risk Management Professional (PMI-RMP) Exam
Last Update: Apr 6, 2026
Questions: 278
PMI-RMP pdf

PMI-RMP PDF

$25.5  $84.99
PMI-RMP Engine

PMI-RMP Testing Engine

$28.5  $94.99
PMI-RMP PDF + Engine

PMI-RMP PDF + Testing Engine

$40.5  $134.99