Question # 204

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

Options:

A.

Motivate the team and deploy the necessary resources.

B.

Find a way to maintain the project schedule.

C.

Impose authority on the project.

D.

Request additional resources from the sponsor and motivate the team.

Buy Now
Question # 205

A railroad construction project is in the planning stage. During a monthly progress meeting, an external project manager from the sponsoring organization mentioned there is a potential delay in the design completion date. The external project manager wants to know the impact of this delay on the overall project completion date in the next monthly meeting.

Which three actions should the internal project manager take next? (Choose 3)

Options:

A.

Perform variance analysis.

B.

Validate the critical path method (CPM).

C.

Establish what-if scenario analysis.

D.

Determine the schedule performance index (SPI).

E.

Execute a Monte Carlo simulation.

Buy Now
Question # 206

A project team consists of several consultants from an external vendor. These consultants often change from month to month.

What should the project manager do to communicate the organizational values?

Options:

A.

Distribute the team charter to new team members.

B.

Host a question and answer (Q&A) session with the new team members.

C.

Schedule a collaborative team outing to strengthen team relationships.

D.

Review communications options with the vendor.

Buy Now
Question # 207

A newly hired project team lead was assigned a project using a hybrid delivery approach. As the project onboards a lot of new team members, the lead feels overwhelmed with the effort of explaining the project delivery process to each new team member.

What should the project lead do?

Options:

A.

Use Pareto techniques to identify the knowledge required by the majority of the team.

B.

Recommend putting the project temporarily on hold and focus on onboarding and training.

C.

Develop a training curriculum and schedule training delivery throughout the project.

D.

Document the processes and organize a week-long, off-site meeting with the project team.

Buy Now
Question # 208

A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.

What should the project manager do to have a high-performing team?

Options:

A.

Set up regular project status meetings and invite all team members.

B.

Encourage the team to define the ground rules for performance.

C.

Set up individual calls to follow up on each team member's progress.

D.

Invite team members to an informal meeting to get to know one another.

Buy Now
Question # 209

A project manager is working on an ongoing construction project. The designer notifies the project manager about materials that were not included in the budget due to a technical mistake.

What should the project manager have done to avoid this situation?

Options:

A.

Asked the project sponsor to review the budget

B.

Updated the budget before moving to another stage of the project

C.

Added enough budget to cover all uncertainties

D.

Used past projects as a reference during budget estimations

Buy Now
Question # 210

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

Options:

A.

Retrieve the documentation that shows the resource allocation.

B.

Examine ways of modifying the scope of the project.

C.

Adopt a resource leveling procedure to level the resources.

D.

Perform an impact analysis to see the effect on the project.

Buy Now
Question # 211

An experienced project manager is managing a multi-million dollar agile project The project manager communicates the ground rules to the team but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules.

What should the project manager do first to ensure team adherence to the ground rules?

Options:

A.

Schedule a meeting with the project team to reinforce the ground rules.

B.

Notify the project sponsor about this behavior and ask the sponsor to take disciplinary action

C.

Contact human resources to request a written warning letter be sent to team members not following the ground rules.

D.

Ask the functional manager to replace team members not following the ground rules

Buy Now
Question # 212

A project manager notices that an extroverted project team member appears to be increasingly controlling the direction of the entire team. The other team members are not complaining but seem to be more passive.

What should the project manager do?

Options:

A.

Meet with each team member to better understand the situation.

B.

Meet with the extroverted team member and ask them to be more sensitive to others.

C.

Address the situation in a team meeting and ask everyone to be more active.

D.

Observe the team dynamics closely and step in if a team member complains.

Buy Now
Question # 213

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?

Options:

A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs

B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team

C.

The project manager should allow the resources to periodically choose on which team they would like to work.

D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization

Buy Now
Question # 214

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

Options:

A.

Maintain a central repository of artifacts with a version control system.

B.

Maintain separate document control via regions to avoid discrepancies.

C.

Develop a document management software for version control.

D.

Facilitate training on version control and project artifacts,

Buy Now
Question # 215

Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?

Options:

A.

Sent the meeting minutes to the stakeholders after the kick-off meeting

B.

Reviewed all the approvals immediately after the kick-off meeting was over

C.

Ran separate kick-off meetings for each culture and time zone

D.

Validated each stakeholder's understanding during the kick-off meeting

Buy Now
Question # 216

A project is being executed The project's life cycle is defined as predictive however, a major deliverable will be handed over incrementally to the customer The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects

What should the project manager do?

Options:

A.

Schedule a steering committee meeting and obtain their approval on the request

B.

Support the decisions of the team and transfer the decision making responsibility to them.

C.

Inform the team that although this is a hybrid environment, the project managermust still be responsible for making decisions

D.

Consult the product owner about letting the resources make decisions

Buy Now
Question # 217

A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.

What should the project manager do next?

Options:

A.

Ask the other project manager to change the delivery methodology.

B.

Request that the other project manager develop a work breakdown structure (WBS).

C.

Participate in the other project's daily standup meetings.

D.

Align with the other project manager's high-level project time lines.

Buy Now
Question # 218

During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics

1,600 rpm (rate-per-minute) -> stops working and crashes the system

1.500 rpm (rate-per-minute) -> warns of max rate allowed

1.400pm (rate-per-minute) -> reduces the power and brakes the engine

Which of the following statements is correct?

Options:

A.

0 1,600 rpm is a project risk,1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project issue.

B.

1,600 rpm is a project issue,1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project risk

C.

1600 rpm is a project issue; 1,500 rpm is a project risk; and1,400 rpm is an event that triggers a response strategy

D.

1.600 rpm is an event that triggers a response strategy.1,500 rpm is a project issue and 1,400 rpm is a project risk.

Buy Now
Question # 219

A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity

issues joining team calls during the day.

What should the project manager do?

Options:

A.

Procure tools that consume less bandwidth for internet calls.

B.

Record the meeting to share with the team members who were unable to join.

C.

Ask the team members to use chat tools as an alternative to calls.

D.

Determine what the problem is and develop an action plan.

Buy Now
Question # 220

A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

Options:

A.

Mark the product backlog completion status and update the communications management plan.

B.

Ensure that knowledge transfer activities are executed as planned

C.

Release the resources and plan for a project completion celebration.

D.

Hold a steering committee meeting to inform them of the project completion

Buy Now
Question # 221

Drag the organizational characteristics on the left to the correct scenario on the right

Options:

Buy Now
Question # 222

An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

Options:

Buy Now
Question # 223

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

Options:

A.

Increased bum rate

B.

Increased cost

C.

Increased technical debt

D.

Decreased efficiency

Buy Now
Question # 224

A project manager assembled a team of 10 developers. Because the organization did not have a development team for this project, contractors were hired. In the kick-off meeting, one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.

What should the project manager do?

Options:

A.

Recommend that the team use industry-accepted guidelines.

B.

Contact the chief information officer (CIO) and request the enterprise development guidelines.

C.

Contact the previous team and ask for a copy of their guidelines.

D.

Recommend that the team develop their own guidelines.

Buy Now
Question # 225

A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?

Options:

A.

The project charter and scope statement

B.

The requirements traceability matrix

C.

The business requirement documents (BRD)

D.

The WBS dictionary

Buy Now
Question # 226

A project manager of a large company needs to categorize the stakeholders' involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams.

Drag each stakeholder scenario on the left to the correct engagement level on the right.

Options:

Buy Now
Question # 227

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration"?

Options:

A.

Request the product owner and team facilitator to provide the size of the story

B.

Average the story points provided by each team member for a story

C.

Continue multiple rounds of planning poker and arrive at the size of the story

D.

Collaborate with different teams and arrive at the size of the story

Buy Now
Question # 228

A project manager is in rapid development mode on a joint application development module The company wants delivery to occur in two weeks The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog

What should the project manager do?

Options:

A.

Push the team to deliver more so that the modules are developed and rolled out according to management's request

B.

Speak to the stakeholders to resolve the bottleneck and see how the entire process can be streamlined

C.

Have the team work toward the tighter deadline so that integration will be easier.

D.

Speak to the team and slow the current pace to ensure the team is in alignment with the release date

Buy Now
Question # 229

A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce

the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December

might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.

What should the project manager do about this risk?

Options:

A.

Update the risk register and take advantage of the opportunity.

B.

Review the supplier's contract to understand the terms of sale.

C.

Accept the risk and update the risk register.

D.

Insist that the supplier deliver the goods on the agreed date.

Buy Now
Question # 230

A project manager is m the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence The project is ahead of schedule and running under budget

Which two actions should the project manager take initially to resolve this problem? (Choose two)

Options:

A.

Check the risk register for a prepared response to a resource being suddenly unavailable.

B.

Check if the team member's activities are sufficiently documented to facilitate handover

C.

Check the project's responsibility assignment matrix (RAM) to determine which activities will be affected

D.

Reassign responsibilities across the remaining members using the available float for training.

E.

Obtain the project sponsors support to replace the team member on leave

Buy Now
Question # 231

A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.

What should the project manager do to support the business analyst?

Options:

A.

Assign resources to coach the business analyst

B.

Ask the business analyst to focus on their work allocation for the needs of the project

C.

Create reports to inform the business analyst about the schedule and project cost

D.

Provide the business analyst with access to the financial and scheduling information

Buy Now
Question # 232

A project manager for a government organization often deals with stakeholder engagement issues Drag the interpersonal skill the project manager should use on t he left to the correct situation on the right

Options:

Buy Now
Question # 233

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

Options:

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

Buy Now
Question # 234

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>

What should the project manager do?

Options:

A.

Move to a Kanban strategy so that work can be reallocated more easily

B.

Decrease the sprint cycle to the average repriontization request by calculating it in days

C.

Set up a meeting with the project team and ask for their opinion on what to do

D.

Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle

Buy Now
Question # 235

A company just started managing a project using an agile approach Due to this change the general manager is worried about the scope definition process for upcoming projects

What should the project manager do to ensure the project scope is completely defined?

Options:

A.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk.

B.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

C.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations

D.

Ask the general manager to review every requirement to ensure all projects will deliver the requested products

Buy Now
Question # 236

In an agile team, some of the team members are coming forward to ask for more

autonomy on the project. What should the project manager do in this situation?

Options:

A.

Encourage the team members to make decisions.

B.

Discourage them as conflicts may be created.

C.

Encourage the team lead to make decisions.

D.

Discourage this request, as it is for the management team.

Buy Now
Question # 237

The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .

What should be the priority order in the product backlog?

Options:

A.

Risk3, Risk 1, Risk2, Requirements, Requirement 1. Requirement2

B.

Requirement 3, Risk 3, Requirement 1, Requirement 2, Risk 2

C.

Requirements, Requirement 1, Requirement2

D.

Requirement 3. Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2

Buy Now
Question # 238

A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.

What should the project manager do?

Options:

A.

Wait for the team to identify and solve the problem independently.

B.

Move the team member to another task that is more skill appropriate

C.

Have a confidential discussion with the team member to identify the root cause

D.

Start a discussion with all team members to help resolve the issues

Buy Now
Question # 239

A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty

What should the project manager have done to avoid this situation?

Options:

A.

Ensured the team charter was developed by the team members

B.

Ensured the team members are fully supportive of all decisions.

C.

Distributed the project charter to all team members.

D.

Used a charismatic leadership style

Buy Now
Question # 240

A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget

What should the project manager do?

Options:

A.

Request to use the management reserve to keep the schedule

B.

Mitigate risks associated with the workaround to avoid project delays

C.

Proceed with the approved risk response plan.

D.

Discuss the options with the client as part of the change control process

Buy Now
Question # 241

A product owner has indicated there is strong customer interest in adding a new set of functionalities to a product. Using agile approaches, the project manager evaluates the new functionalities of the product.

What should the project manager do?

Options:

A.

Negotiate with the product owner to determine which functionality should be pushed out of the scope of the project.

B.

Discuss with the team how this change in scope impacts development at the next retrospective to determine next steps.

C.

Negotiate with the product owner to determine what might be removed from the backlog that is of similar size.

D.

Add the functionality to the product backlog for inclusion once a change request is created and approved.

Buy Now
Question # 242

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

Options:

A.

Reject the risk because the team is not in agreement on escalating it

B.

Include the risk in the risk assessment and evaluate it with the team

C.

Accept the risk and immediately enter the risk into the risk register

D.

Discuss with the consultant to understand why the risk was escalated

Buy Now
Question # 243

A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component

What should the project manager have done to prevent this delay from happening?

Options:

A.

Updated the risk management plan and registered lessons learned for the project

B.

Reorganized the team for the project based on the work breakdown structure (WBS)

C.

Maintained constant communication with the stakeholders of the other projects

D.

Used the resource management plan to identify the impacts of the other projects

Buy Now
Question # 244

Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.

What should the project manager do next?

Options:

A.

Discuss the topic with the team members in a team meeting.

B.

Replace the two team members with other resources.

C.

Contact the functional managers of each team member.

D.

Schedule a meeting with both team members.

Buy Now
Question # 245

One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.

What should the project manager do?

Options:

A.

Coordinate design document preparation

B.

Perform a qualitative risk analysis

C.

Request further clarification of the requirement

D.

Manage the engagement of this stakeholder.

Buy Now
Question # 246

A project manager is reviewing the status of a large project with team members in different countries. Through the status review, the project

manager notices that one team is consistently behind schedule and their work often needs to be corrected.

What should the project manager do to improve the quality of this team's work?

Options:

A.

Evaluate the issue with the team to determine if they have the necessary skills to perform assignments.

B.

Review the issue with the project sponsor and work to reduce the scope for that team.

C.

Guide all team members and bring in external consultants to complete the work.

D.

Ask a local subject matter expert (SME) to assist the team in reviewing the project requirements.

Buy Now
Question # 247

A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.

What should the project manager do?

Options:

A.

Review the requirements on a weekly basis.

B.

Implement a requirements traceability matrix.

C.

Add the requirements to the project charter.

D.

Understand the project management plan.

Buy Now
Question # 248

One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority

What should the project manager do to mitigate the risk of not having the materials printed on time?

Options:

A.

Meet with the manager to set a high priority for printing the materials

B.

Create a change request to modify the print requirements

C.

Include a risk response in the resource management plan

D.

Purchase a high-volume printer specifically for this project.

Buy Now
Question # 249

A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?

Options:

A.

Ask the product owner, who is the key stakeholder, to choose among the different ideas.

B.

Propose ideas to the group, ask everyone to vote, and then choose the most popular idea

C.

Schedule a session to give everyone the chance to express their opinions about each idea, then vote and decide.

D.

Offer an opinion about the pros and cons of each idea and try to reach a consensus in a facilitated meeting

Buy Now
Question # 250

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

Options:

A.

Encourage frequent small team meetings with two or three team members.

B.

Give up the daily standup and replace it with a daily report

C.

Let the team members decide themselves if they want to join the meeting.

D.

Require all team members to join the daily standup regardless of the meeting time

Buy Now
Question # 251

A product company is transforming the way it develops and releases products in the market Executives believe that this is a high-risk initiative, and this initiative must be successful

What should the project manager do in this scenario?

Options:

A.

Develop a business case with assumptions for the new model

B.

Develop a communications management plan to inform the employees about the new business model

C.

Adopt an iterative rollout approach that delivers the highest business value earlier

D.

Develop a detailed sprint plan with clear deliverables

Buy Now
Question # 252

In an organization with good work-life balance, one team was continuously overloaded, thereby delivering the product ft quality. What should the project

manager do?

Options:

A.

Request the team to work more for on-time delivery.

B.

Request the team to focus on doing better planning.

C.

Request the replacement of certain team members.

D.

Request management for a high-performing team.

Buy Now
Question # 253

A new project manager has been assigned to an ongoing project because of the promotion of their predecessor. The new project manager needs to understand the levels of decision-making authority on the team.

Which document should the incoming project manager review?

Options:

A.

Resource management plan

B.

Communications management plan

C.

Information management plan

D.

Stakeholder engagement plan

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (PMBOK 7th Version)
Last Update: Apr 6, 2026
Questions: 2191
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599