Question # 204

During daily team coordination meetings, team members constantly ask which tasks they should focus on first. How should the project manager ensure the team is fully productive?

Options:

A.

Work with the product owner to ensure the product backlog is prioritized

B.

Review the project backlog during the team’s coordination meeting

C.

Encourage team members to prioritize the product backlog

D.

Ensure team members are working according to the project management plan

Buy Now
Question # 205

A project manager is assigned to a large complex project with cross-functional dependencies. The project enters a new phase requiring new stakeholders to be added with conflicting priorities. How should the project manager ensure successful engagement with the stakeholders?

Options:

A.

Invite all stakeholders to status meetings.

B.

Identify and categorize the stakeholders.

C.

Interact individually with the stakeholders.

D.

Recognize the diversity of the stakeholders.

Buy Now
Question # 206

A new project manager has been assigned to a recently approved project. The project has a multimillion-dollar budget and will require the purchase of expensive pieces of equipment. The project manager is aware that some purchasing amounts require higher levels of approval.

What should the project manager do to properly manage the purchase of equipment?

Options:

A.

Agree on a purchasing approval escalation method according to organizational governance.

B.

Ask the organization to allow the project manager to approve all of the purchases.

C.

Propose that the project sponsor approve all of the pieces of equipment that need to be purchased.

D.

Replace the most expensive pieces of equipment with cheaper ones to allow easier purchase approval.

Buy Now
Question # 207

A project manager is working on an agile project. The organization does not have experience with agile delivery. During business case development, the new product owner asks when the project deliverables are considered complete.

How should the project manager respond?

Options:

A.

Items are considered complete when they satisfy the definition of done (DoD).

B.

The scrum master will approve the user stories that are complete.

C.

Backlog items are considered complete when the product owner approves the demo.

D.

At the end of each sprint, the outcome is considered ready for production.

Buy Now
Question # 208

A project manager is executing a project on time and on budget. Before a stage gate review, the project manager receives the regular business management report, but this time it indicates a negative impact on the project success factors. What should the project manager do?

Options:

A.

Continue with execution since the project was successful up to this phase

B.

Call for business development to revalidate inputs at the next stage gate

C.

Provide the necessary analysis to enable examination of the business value

D.

Request a delay to the stage gate until business development provides the next update

Buy Now
Question # 209

A project manager is working with a team that is new to agile. One of the more

influential stakeholders struggles with the nature of agile. The project manager knows that this

stakeholder is needed as an advocate and wants to do everything possible to make the

stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project ' s

performance?

Options:

A.

Results of the MoSCoW assessment

B.

Cost-benefit analysis

C.

Return on investment (ROI) analysis

D.

Earned value analysis (EVA)

Buy Now
Question # 210

During project implementation, a critical performance issue is identified by team members.

What should the project manager do?

Options:

A.

Work with the project stakeholders to address the performance issue.

B.

Review the tender requirements on the related performance issue.

C.

Pass the performance issue to subject matter experts (SMEs) to handle.

D.

Submit a change request to handle the performance issue.

Buy Now
Question # 211

A new project manager is managing a hybrid project. The project manager wants to be

a servant leader to support the team by removing impediments but is not receiving feedback

from the team about the issues and risks they are facing.

What should the project manager do?

Options:

A.

Implement daily standups where the team can share their impediments, risks, andissues.

B.

Review the communications management plan and implement changes.

C.

Schedule weekly risk review meetings with the team to review project risks andconcerns.

D.

Distribute a copy of the communications management plan to the scrum master.

Buy Now
Question # 212

A project has been running for 2 months and now requires approval for a supplier to

begin some execution tasks. The project team has evaluated several suppliers and selected

their top two preferred suppliers. The project sponsor requested that another supplier who has

lower costs be added to the list. However, the project manager is aware that this supplier

does not always fulfill the project requirements.

What should the project manager do?

Options:

A.

Set up a requirements review session and obtain agreement for selection criteria.

B.

Recommend to the team to add the sponsor ' s preferred supplier to the list.

C.

Choose the sponsor ' s preferred supplier for the project to avoid conflict between theteam and sponsor.

D.

Recommend to the sponsor to review the results of the team ' s supplier evaluation.

Buy Now
Question # 213

One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.

What should the project manager do next?

Options:

A.

Arrange an additional meeting with the team to communicate the agreement made during the last meeting.

B.

Schedule a new meeting to evaluate the agreement and negotiate a new one.

C.

Talk with the team member and explain that once the meeting ended, the agreement must be respected.

D.

Meet with the team member and search for the root cause of their behavior.

Buy Now
Question # 214

During a blueprint review meeting, the finance department representative is not comfortable with a proposed solution that favors another department. As a result, document approval is delayed, which impacts the project schedule.

What should the project manager do?

Options:

A.

Arrange a meeting with the two departments to understand their differences and address their needs.

B.

Schedule a meeting with the project sponsor to seek advice on the approach of both departments.

C.

Work with the project team to find a compromise solution that suits both departments.

D.

Assess the risk of postponing this specific solution and advise both departments of the delay.

Buy Now
Question # 215

A project manager is leading an automation project. The project team is colocated

and includes people from both the technical and business units. The project manager

discovers that personal differences and work styles are affecting the project negatively.

How should the project manager address this?

Options:

A.

Develop a schedule that ensures people with personal differences work separately.

B.

Use an approach to the project that does not involve colocation.

C.

Meet with the team and agree on expectations from team members.

D.

Invite the functional managers of the different units to address their personal differences.

Buy Now
Question # 216

One of the main deliverables of a project is delayed due to a problem with a key provider. What should the project manager do?

Options:

A.

Create a change request to replace the provider with a more responsible one from the provider list

B.

Schedule a meeting with all relevant stakeholders to determine the best approach to resolve the issue

C.

Discuss with the sponsor and seek guidance to impose the penalty stipulated in the agreement

D.

Schedule a meeting with the provider to review impacts to the project timeline and deliverables

Buy Now
Question # 217

A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office ' s (PMO ' s) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO ' s status reports have sufficient enough information

How should the new project manager proceed*?

Options:

A.

Continue using the outgoing project manager ' s status reports as well as their approach for schedule reporting

B.

Explain to the PMO that the hybrid project team needs to keep an agile approach for reporting and will not be complying with the organizational standard

C.

Change the status reports according to the template supplied by the PMO and proceed with scheduled reporting

D.

Meet with the project stakeholders to explain the need to comply with the PMO standards and update the status report format accordingly

Buy Now
Question # 218

At the end of a project, one of the suppliers is facing financial difficulties and is

pushing the project manager to obtain financial, legal, and administrative approval in order to

communicate formal project closure and ensure the transfer of liability. What should the

project manager do next?

Options:

A.

Compare the achieved results to the contract requirements.

B.

Make the final payment as the project is completed.

C.

Transfer the remaining variances and close the project.

D.

Escalate to higher management to expedite the approval.

Buy Now
Question # 219

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

Options:

A.

Workstream leader and project sponsor

B.

Workstream leader alone

C.

Workstream leader and functional manager

D.

Workstream leader and project management office (PMO)

Buy Now
Question # 220

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?

Options:

A.

Conduct a consensus-building session to decide how to approach the next set of work.

B.

Escalate the issue to the product owner for resolution.

C.

Add this conflict to the agenda for discussion at the next daily standup meeting.

D.

Conduct a planning session to decide how to approach the next set of work.

Buy Now
Question # 221

A project lead was asked to support the team by subdividing the project tasks as necessary to help define the minimum viable product (MVP).

Which two steps should the project lead take to define the MVP? (Choose 2)

Options:

A.

Hold a team meeting to generate a work breakdown structure (WBS).

B.

Create a responsible, accountable, consulted, informed (RACI) chart.

C.

Develop a project management plan, including subtasks, to meet the requirements.

D.

Conduct an information gathering session to determine the project value.

E.

Refer to the stakeholder register to determine who should be consulted.

Buy Now
Question # 222

A project has been running successfully for 2 months. At a regular project meeting,

the team raises several potential obstacles to future progress. The obstacles include vendor

delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

Options:

A.

Work with the team and others in the network to assess and prioritize the obstacles.

B.

Engage with the external stakeholders and the other division of the organization toresolve the issues.

C.

Escalate the obstacles to the project sponsor for assistance with resolution.

D.

Determine a change response to identify and resolve the obstacles to move the projectforward.

Buy Now
Question # 223

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?

Options:

A.

Analyze the problem with both teams to figure out If pan of the work must be redone.

B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.

C.

Demand that the business team stop wasting time and define final requirements for the product.

D.

Tell the business team and Scrum team to continue following the initial plan.

Buy Now
Question # 224

A project manager is leading a hybrid project. The self-organizing teams are

continually late in delivering their demos, resulting in low morale. The steering committee is

familiar with the reporting and planning associated with a predictive approach and is

concerned about the project because it is unclear if the expected value will be delivered.

What should the project manager do?

Options:

A.

Emphasize to the teams the importance of reaching the agreed deadlines and value.

B.

Request to coach the team to ensure motivated project team members are on board.

C.

Update the project schedule with a buffer to reflect the expected delays being incurredby the team.

D.

Suggest to the teams to limit the scope of work per iteration so they will start to delivermore reliably.

Buy Now
Question # 225

A retail company identifies that it is losing sales because customers are not promptly

informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.

Considering the objective to deploy customer value, which project life cycle approach should be chosen?

Options:

Buy Now
Question # 226

A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items

What should the project manager do as a servant leader?

Options:

A.

Ask the sponsor to submit a change request to the change control board (CCB)

B.

Support the product owners decision to change the priority of the product backlog items

C.

Accept the request and include the product backlog items in the next sprint

D.

Review the impact of the change on the schedule management plan baseline

Buy Now
Question # 227

A project manager Is working on the initial phases of a highly technical project that employs the " first of its kind " technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted

What should the project manager do?

Options:

A.

Request stakeholders who understand the technology.

B.

Recommend a change in technology to senior management.

C.

Plan to conduct informal sessions with the stakeholders.

D.

Include the issue in the Issue log and escalate to senior management.

Buy Now
Question # 228

A project sponsor asks the project manager to explore a hybrid approach for a new

project. The product manager for this project has already prepared a detailed specification for the product.

What should the project manager do to proceed with the project management plan?

Options:

A.

Ask the team to assess whether the product specification can be expressed in userstories to enable a Scrum or Kanban approach.

B.

Explore with the product manager to determine if there are viable opportunities todeliver value incrementally and increase business value.

C.

Recommend to the project sponsor that a predictive approach is appropriate for theproject due to the stable product requirements.

D.

Ask the product manager whether they are prepared to act as product owner for theproject in order to participate in iterative planning and reviews.

Buy Now
Question # 229

A company that uses a predictive approach and operates in a highly regulated market is losing profitability because its product life cycle is taking longer than those of its

competitors. A new project manager has been hired to change this scenario.

What approach should the project manager propose?

Options:

A.

Change to an agile model, focusing primarily on the incremental life cycle, leaving the iterative approach as a next step.

B.

Maintain a predictive approach, but increase the focus on better planning and tracking to anticipate problems and avoid delays.

C.

Migrate to an agile model, focusing primarily on an iterative approach, leaving the incremental life cycle as a next step.

D.

Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company’s industry.

Buy Now
Question # 230

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

Options:

A.

Meet with the stakeholder to discuss the impact of the deliverable

B.

Consider the stakeholder as a risk and evaluate possible solutions with the project team

C.

Improve communication with the stakeholder to obtain their assistance in the future

D.

Escalate to the project sponsor due to the political nature of the issue

Buy Now
Question # 231

During the project planning phase, a project manager called a meeting to discuss the

product backlog with multiple stakeholders who represent the end users in various capacities.

Only one executive manager attended the meeting.

What should the project manager do?

Options:

A.

Meet with each stakeholder individually to gather input to the product backlog andbegin project planning.

B.

Proceed with prioritization of the product backlog based on previous lessons learnedand complete the project planning phase.

C.

Reschedule the meeting to ensure the majority of stakeholders are present for theproduct backlog discussions.

D.

Proceed with the meeting in order to keep the project on track and start prioritizing the product backlog.

Buy Now
Question # 232

A project is on its sixth iteration out of seven. Select the two points where the team is

performing better than expected. (Choose two.)

Options:

Buy Now
Question # 233

A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee ' s request?

Options:

A.

Evaluate the employee ' s recommendation by reviewing the lessons learned from a similar project.

B.

Create a salience model to determine if the employee will have influence on the project.

C.

Ask the project sponsor to revisit the project charter to consider the employee ' s recommendation.

D.

Assess the influence and power of the employee to see if the employee will add value.

Buy Now
Question # 234

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.

What should the project manager do?

Options:

A.

Communicate the risk to the steering committee and request a mitigation plan from senior management.

B.

Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.

C.

Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.

D.

Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.

Buy Now
Question # 235

A project manager for a large multiyear industrial project has a project with diversified stakeholders from various geographical areas. Recently, the project manager encountered an issue with stakeholder engagement

Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose two)

Options:

A.

Five whys

B.

Communications management plan

C.

Ishikawa diagrams

D.

Issue log

E.

Open-space meetings

Buy Now
Question # 236

A project sponsor has requested a trend analysis of all risks that the project has

monitored over the past 12 months. What should the agile project manager do?

Options:

A.

Share the annual report with the sponsor.

B.

Organize a stakeholder meeting to brainstorm on general project risks.

C.

Extract this from the project risk register tracking tool and issues log.

D.

Refer the sponsor to the contract document.

Buy Now
Question # 237

A customer interacts directly with a Scrum team and continually requests changes in

priorities. This causes confusion among the team members and they complain to the project

manager.

What should the project manager do?

Options:

A.

Advise the customer to discuss changes with the product owner.

B.

Document this issue in the sprint backlog for discussion at a team meeting.

C.

Ask the customer to submit a change request to the project sponsor.

D.

Encourage the team to clarify the requests with the customer.

Buy Now
Question # 238

A project manager is assigned to deliver an innovative solution that is part of a

brand new offering. The project manager reviews the request for proposal (RFP) and realizes that key terms are restricted to technical resource assignments. There is also a gap in addressing compliance.

How should the project manager bridge the gap and ensure the project delivers the expected

business value?

Options:

A.

Determine the critical requirements.

B.

Document the risks and mitigations.

C.

Define the project schedule.

D.

Create a project scope statement.

Buy Now
Question # 239

In an agile team, some of the team members are coming forward to ask for more

autonomy on the project. What should the project manager do in this situation?

Options:

A.

Encourage the team members to make decisions.

B.

Discourage them as conflicts may be created.

C.

Encourage the team lead to make decisions.

D.

Discourage this request, as it is for the management team.

Buy Now
Question # 240

On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client. The project manager is now in the initial stage of a new project with the same subcontractors and client.

How should the project manager set up communications?

Options:

A.

Inform the client that all communications moving forward will go through the project manager

B.

Ensure that the communications management plan covers contractual obligations

C.

Consult the communications management plan from a recent project that has been closed

D.

Update the communications management plan to allow the subcontractors to communicate directly with the client

Buy Now
Question # 241

During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?

Options:

A.

Let the product go to market and wait for customer feedback regarding quality

B.

Ask the quality manager to include the final user tests in the quality management plan.

C.

Submit a change request to analyze a new set of quality tests

D.

Ask the product manager to include the final user tests in the quality management plan

Buy Now
Question # 242

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client ' s project manager has no agile experience.

How should the project manager ensure that the client is effectively represented in the daily meetings?

Options:

A.

Recommend agile training programs that best suit the client project manager ' s schedule.

B.

Realign the project to a predictive approach to ensure optimal collaboration between the teams.

C.

Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals

D.

Provide the client project manager with agile best practice documents and web resources.

Buy Now
Question # 243

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?

Options:

A.

Document the risk register in the project charter.

B.

Speak to the customer and add the issue to the issue log.

C.

Review user roles and update the team charter.

D.

Involve the product owner to rewrite the user stories.

Buy Now
Question # 244

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

Options:

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal andexternal resource requirements.

B.

Commit each team member ' s time and deliverables and aim for overall projectcompletion.

C.

Continue the project implementation without the site engineers to ensure the scheduleis maintained.

D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.

Buy Now
Question # 245

A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.

What should the project manager do to avoid these challenges?

Options:

A.

Increase the project budget by 10% for team-related activities and awards.

B.

Plan to implement team-building strategies throughout the project.

C.

Ask the functional manager to motivate the team outside of the project.

D.

Colocate the team to encourage more motivational team activities.

Buy Now
Question # 246

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

Options:

A.

Ensured that all defects identified during testing were resolved before implementation

B.

Ensured that all of the required tasks identified in the scope were completed successfully

C.

Ensured that all documentation was completed post implementation before closing the project

D.

Ensured that all the required approvals were received per the organizational procedures

Buy Now
Question # 247

A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline

What two actions should the project manager take ' ? (Choose two)

Options:

A.

Send letters to the neighbors and ask them kindly not to disturb the project.

B.

Set up a meeting with neighborhood representatives to win their cooperation

C.

Analyze the situation and find out what is causing the neighborhood ' s negative attitude.

D.

Ask the customer to extend the project deadline to allow time for conflict resolution

E.

Ask the mayor of the city to use their authority to stop neighborhood resistance

Buy Now
Question # 248

Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished

What should the project manager have done differently?

Options:

A.

Formed a separate quality assurance team to test all items coming from each team at the end of each sprint

B.

Performed a Scrum of Scrums on a regular basis to help the teams remove impediments

C.

Ensured frequent and continuous integration of work to obtain early feedback and continuous learning

D.

Arranged an online session on the integration concept and suggested tools to the teams

Buy Now
Question # 249

During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?

Options:

A.

Asking and listening

B.

Being collaborative

C.

Managing expectations

D.

Building trust

Buy Now
Question # 250

A project is in the execution phase During a few planning sessions the team brought up dependencies and risks based on their knowledge of other project. The project manager also received questions from the company in terms of how and when the team planned to perform acceptance testing and training activities

What should the project manager do next?

Options:

A.

Document the project management plans and share them with the company and all team members via email for review

B.

Create a log to track risks assumptions issues and dependencies and establish a periodic review with the stakeholders

C.

Add contingency m the schedule to account for dependencies and risks then review rt with the team

D.

Engage with the company and the project team to determine the best course of action

Buy Now
Question # 251

A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is

seeking the project manager ' s recommendation on how to approach this request.

What should the project manager do to help the product owner?

Options:

A.

Provide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.

B.

Invite the product owner to future demonstrations where they can provide feedback.

C.

Provide access to the latest user acceptance test (UAT) environment so they can see the solution.

D.

Remind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.

Buy Now
Question # 252

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.

What should the project manager have done to prevent this situation?

Options:

A.

Performed a stakeholder analysis when the sponsor joined the project

B.

Held a governance meeting to review the project increment

C.

Conducted a product iteration review with the new project sponsor

D.

Escalated the issue to ensure the increment would be approved

Buy Now
Question # 253

A CEO of a general contracting company urgently asks the project manager to sign up two project team members to participate in a specific training course. Halfway

through the training, both team members complain that the training is too difficult, above their experience level, and that the material does not align with their tasks.

What should the project manager have done to prevent this situation?

Options:

A.

Communicated with the two team members that the purpose of the training is to provide material that might be useful to them in the future

B.

Sent an immediate request to the human resources (HR) department to replace the current team members with higher skilled candidates

C.

Observed and assessed the competencies and skills of the team members and analyzed the training material beforehand

D.

Planned a training to follow the specific course to bring the two team members to the required experience level

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (PMBOK 7th Version)
Last Update: Jul 5, 2026
Questions: 2196
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599