Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 104

A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.

Which tool should the project manager use for this purpose?

Options:

A.

Cumulative flow diagram

B.

Earned value (EV)

C.

Burndown chart

D.

Forecast estimation

Buy Now
Question # 105

During a project planning meeting, a product manager and team are finalizing the project deliverables and notice that a key feature has a dependency from another team. A team member suggests removing the feature from the scope.

What should the project manager do?

Options:

A.

Advise the team not to reduce the scope of the feature because the product manager originally included that requirement.

B.

Discuss the issue with the team so the product manager can understand the trade-offs.

C.

Suggest the team and product manager go with the faster approach, reducing the scope.

D.

Prepare a presentation for the project sponsor with the team that includes both solutions and seek the sponsor's guidance.

Buy Now
Question # 106

Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.

What should the project manager do?

Options:

A.

Assess the benefit of using new technology versus old technology.

B.

Hire project resources with experience using the new technology.

C.

Propose training for the project team in batches on the new technology.

D.

Request incentives for the team to use the new technology.

Buy Now
Question # 107

A project manager is trying to define a project time line despite having incomplete and ambiguous information on requirements and regulations. What should the project

manager do to finish planning?

Options:

A.

Review project documents to identify and eliminate uncertainties and inconsistencies.

B.

Execute a root cause analysis to discover the underlying factors that might lead to risks and issues.

C.

Perform an assumption and constraint analysis to provide more opportunities and remove limiting factors.

D.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

Buy Now
Question # 108

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

Options:

A.

Prepare a risk report that captures the probability and impact of risks, and then shareit with the project sponsor.

B.

Share the organization's decision with the team and make plans to adopt an agileapproach in the upcoming project.

C.

Make a request to human resources for new team members who have agileexperience.

D.

Ask the project sponsor to change the approach back to predictive as that is theteam’s strength.

Buy Now
Question # 109

The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?

Options:

A.

Product owner

B.

Change control board (CCB)

C.

Project sponsor

D.

Project manager

Buy Now
Question # 110

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

Options:

A.

Finish to start

B.

Start to start

C.

Start to finish

Buy Now
Question # 111

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component

managed by an external vendor. How should the project manager address the team member's concern?

Options:

A.

Ask the team member to resolve the issue independently to minimize further delays.

B.

Ask the team member to provide details to address the issue with the vendor.

C.

Implement fast tracking to reduce the impact of the delay on the sprint.

D.

Update the communications management plan to prevent future reoccurrence.

Buy Now
Question # 112

In the middle of a project, a business unit manager who regularly interacts with the project manager's team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.

After getting more information about the new manager, what is the project manager's next step?

Options:

A.

Contact the previous business unit manager to learn more about the new manager.

B.

Update the stakeholder register and the stakeholder engagement plan to include the new manager.

C.

Send the new manager a copy of the project charter to ensure the project objectives are understood.

D.

Schedule a meeting with the new manager to discuss the business analysis team's plans.

Buy Now
Question # 113

An organization is implementing a solar power system at its production plant. During the execution phase, one of the key stakeholders noticed and communicated that authorities are developing solar power regulation, which might impact the overall feasibility of the project.

What should the project manager do first?

Options:

A.

Collect and analyze information about the new regulation.

B.

Put the project on hold and wait for the regulation information to be confirmed.

C.

Proceed with the project as long as the regulation is not yet finalized.

D.

Meet with the sponsor to discuss the regulation issue and determine the proper action.

Buy Now
Question # 114

A key project stakeholder recently joined the project and is questioning some of the previously made decisions. This starts to impact project execution.

What should the project manager do?

Options:

A.

Reach out to the stakeholder via phone to explain that all decisions have been agreed upon with their predecessor.

B.

Provide the stakeholder with a link to a file-sharing site where the supporting documents for decisions are filed.

C.

Schedule a meeting with the stakeholder to provide an overview of the project, including the agreed-upon decisions.

D.

Update the risk register with a new risk of potential project changes as a result of stakeholder misalignment.

Buy Now
Question # 115

The project team is conducting iteration planning and having difficulty evaluating a new technology that will be used in this iteration. What should the project lead do?

Options:

A.

Hire an external subject matter expert (SME) to help with design and implementation.

B.

Coach the team to determine a path forward to achieve an efficient solution.

C.

Provide technical guidance on complexity assessment.

D.

Guide the team with estimating the time required.

Buy Now
Question # 116

A project manager is overseeing a 10-mile piping installation project that was supposed to spend US$15,000 per mile of piping installation and should complete the project exactly 20 weeks from its start. The project manager just found out that only 80% of the work has been completed.

What is the budget at completion (BAC)?

Options:

A.

US$100,000

B.

US$150,000

C.

US$300,000

D.

US$250,000

Buy Now
Question # 117

A project is 20% complete. The client has accepted a project order amendment that involves a major change. Without this major change, the project result will be useless for the client organization.

What should the project manager do?

Options:

A.

Update the project status from "active" to "on hold" until there is more clarity on the scope of the change.

B.

Initiate planning for the project with the modified scope as laid out in the client's purchase order.

C.

Set up a meeting with the client and the project team to identify ways to safeguard the project from the change.

D.

Consult the project sponsor to understand if the change must be processed for project execution.

Buy Now
Question # 118

An agile project is completing its second sprint and products are being finished. However, two groups with different levels of expertise disagree on the backlog priority.

What should the project manager do first to resolve this dispute?

Options:

A.

Escalate to the project sponsor to provide a solution to the conflict.

B.

Interpret the source and stage of the conflict and select a resolution approach.

C.

Apply a compromising resolution approach, involving both groups.

D.

Ask the functional managers of both groups to help find a workable solution.

Buy Now
Question # 119

An agile team recently started working on a project for a financial institution. The

project sponsor is concerned that an agile approach will not provide enough support for the

organization's compliance standards.

In order to mitigate this risk and avoid problems, what should the project manager do?

Options:

A.

Propose using a compliance review board that will be responsible for approving allproduct features prior to their release to the public.

B.

Liaison with the compliance group, making them responsible for understanding therequirements and keeping them prioritized in the backlog.

C.

Meet with the compliance team and make sure that their requirements are covered in thedefinition of done (DoD) for each story.

D.

Ensure that the peer review process also covers compliance requirements, creating asecond layer of security for the project.

Buy Now
Question # 120

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?

Options:

A.

Call for a team meeting to identify the root cause for the declining performance

B.

Estimate the baseline impacts and submit a change request.

C.

Implement compression techniques to bring the project back on track.

D.

Review the resource management plan and organizational assets

Buy Now
Question # 121

Due to their different ideas regarding the execution of a project, a conflict has occurred between two stakeholders.

What should the project manager do to resolve the conflict?

Options:

A.

Arrange a group meeting with the stakeholders to generate creative alternatives.

B.

Address the conflict in a planned meeting with all stakeholders and project team members.

C.

Assess the conflict based upon the stakeholders' past disagreements.

D.

Focus on the personal issues between the stakeholders.

Buy Now
Question # 122

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks

Drag each risk type on the left to its correct example on the right

Options:

Buy Now
Question # 123

An organization is undergoing an agile transformation and migrating most of its projects from a predictive approach. The CFO expressed a concern that predictability on both costs and scope will be lost with the new agile approach.

What should the project manager do?

Options:

A.

Provide mentoring to the CFO, who is a key stakeholder in the project, and clarify the benefits of an agile approach.

B.

Ask the CEO to intervene by asking for support from the executive board to accelerate the company's transformation.

C.

Apply influence with other key stakeholders on the board to mitigate any risks that may be generated by the CFO's position on the matter.

D.

Submit a report to all key stakeholders on the cost-benefit analysis of the new approach and detail how the company will save money.

Buy Now
Question # 124

During project planning activities, a project manager identifies potential delays in obtaining resources required for a project. This will significantly impact the construction timeline.

What should the project manager do?

Options:

A.

Review and update the project management plan to accommodate the delays.

B.

Speak with the project sponsors about changing the project management plan.

C.

Create a change request to increase the cost of resources.

D.

Delay the project until additional resources can be identified.

Buy Now
Question # 125

A project is continuously overlapping phases. Due to a recent human error, the team, which is made up of senior members, is experiencing distrust issues from other departments and lacking initiative. This is impacting overall performance and putting the project objectives at risk.

What should the project manager do when executing the next sprint?

Options:

A.

Coach those responsible for the error so that the whole team understands they are not responsible for it.

B.

Explain high-level objectives and ask team members to self-organize around their tasks to meet the objectives.

C.

Request offsite team-building activities and deploy incentive plans around their tasks.

D.

Identify the poor performers and ask their functional managers to assign them a mentor.

Buy Now
Question # 126

During a sprint, the team is experiencing conflict because the customer asks for additional features that increase the complexity. The scrum master is trying to resolve the conflict.

Which approach should the scrum master use?

Options:

A.

Discuss the definition of done (DoD) with the customer.

B.

Approach the product owner to determine the next course of action and update the backlog.

C.

Discuss the acceptance criteria with customer.

D.

Perform backlog prioritization to ensure that everyone is working on the highest value features.

Buy Now
Question # 127

A project manager is confused when the operational results from previous iteration solutions have not been acceptable to the client. Team members have already delivered all previous solutions, which were accepted by the client as complete.

What should the project manager do?

Options:

A.

Recommend a change in the project methodology or the approach.

B.

Develop and execute a stakeholder engagement strategy.

C.

Determine the criteria and measuring systems for objective success.

D.

Allocate more time for mentoring project team members.

Buy Now
Question # 128

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?

Options:

A.

Execute the smaller estimated activities.

B.

Resize the story points.

C.

Negotiate the estimation so it gets smaller.

D.

Break down the larger activities into smaller ones.

Buy Now
Question # 129

A project manager leads a regulatory initiative with tight, non-negotiable timelines. During a status meeting, a key stakeholder asks if a critical milestone associated with the reporting functionality can be moved up by 4 weeks.

What should the project manager do first?

Options:

A.

Gather additional information and ask the team to perform a root cause analysis.

B.

Update the master schedule to reflect the reprioritized deliverables.

C.

Ask the team to work with the product owner to reprioritize the backlog.

D.

Request additional information and discuss the feasibility options and impacts with the team.

Buy Now
Question # 130

During a planning session, the development team and the product owner are arguing about the effort needed to deliver a specific feature in a software development project. The product owner says that the feature can be developed in one week, whereas the team estimates that it will take at least two weeks. After several hours of discussion, they have not reached an agreement.

What should the project lead do?

Options:

A.

Communicate to the stakeholders that the project has to be delayed for two weeks.

B.

Ask the project team to accept the shorter estimate as it is important to keep a good relationship with the product owner.

C.

Decide what should be the time estimate and proceed with the planning meeting.

D.

Educate the product owner that the project team members are the most appropriate group for assessing the effort.

Buy Now
Question # 131

A project is on schedule. However, during a site visit, a project manager notices that the contractor's productivity is low.

What should the project manager do?

Options:

A.

Assess the opportunity to deliver the project ahead of schedule and introduce a reward system.

B.

Discuss the need to increase productivity with the contractor.

C.

Plan the close-out activities since the project is on schedule.

D.

Update the project schedule to align with the contractor's productivity.

Buy Now
Question # 132

Generative artificial intelligence (AI) now helps produce documents on most projects across an organization and is yielding great benefits. Despite this change, a project manager notices that very few members of their current team know the AI tools available within the company. Consequently, they do not know how to use them effectively.

What should the project manager do?

Options:

A.

Identify more user-friendly generative AI applications in the industry and share with the team.

B.

Engage with some experienced personnel in the company and request they mentor the rest of the team.

C.

Document this issue as a lesson learned and hold a briefing at the end of the project.

D.

Invite the project sponsor to brief the team on the importance of generative AI and how to optimize the available applications.

Buy Now
Question # 133

In a hybrid project, the project manager has identified a few stakeholders. According to the stakeholder matrix, the head of development has a high rating of power/influence and a high likelihood of conflict.

Which action should the project manager avoid?

Options:

A.

Escalating a conflict within the project

B.

Creating a new communication channel

C.

Giving special attention to this stakeholder

D.

Dismissing the stakeholder's opinions

Buy Now
Question # 134

During a sprint planning, the development lead highlights the importance of working on technical debt tasks that are critical for the product performance. However, the tasks will consume most of the team's capacity and they will not be able to work on product feature development.

What should the project manager do?

Options:

A.

Invite technical stakeholders for backlog prioritization.

B.

Work on the features already prioritized by the product owner.

C.

Ask the sponsor for more resources to continue at the same pace.

D.

Add the technical debt tasks to the sprint backlog.

Buy Now
Question # 135

A project to support an organizational transformation is in the planning phase. Transformation is the project sponsor's idea and is not aligned with key stakeholders because they all have different opinions about the project outcomes.

What should the project manager do next?

Options:

A.

Ask the project sponsor to help with engagement of the key stakeholders.

B.

Communicate project outcomes and results with the key stakeholders.

C.

Define a high-level project scope and share it with the key stakeholders.

D.

Conduct a workshop on project goals and deliverables with the key stakeholders.

Buy Now
Question # 136

A project team member contacts the project manager to say they are not familiar with the regulations to complete some activities. What should the project manager do?

Options:

A.

Ask the team member to contact the learning and development team for additional help.

B.

Share the required documents with the team member.

C.

Arrange a required training session for the team member.

D.

Raise this issue in the next team meeting and ask the rest of the team to clarify.

Buy Now
Question # 137

A strategic project using international funds for a government agency is going through the execution phase. The government transition will take place in 1 month, and authorities will change. There is a risk that the project will be suspended or team members will be removed. The project manager wants to ensure that the project will continue despite these changes.

Which action should the project manager take to address this situation?

Options:

A.

Stop the project until the government transition has taken place.

B.

Ask the sponsor to send a communication to the president-elect team with the progress of the project.

C.

Ask the main stakeholders to document their progress on the project before the transition.

D.

Accept the risk as these changes are part of the organizational culture.

Buy Now
Question # 138

An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.

What should the servant leader do?

Options:

A.

Escalate this to the project director for a resolution.

B.

Escalate this to the agile lead of the second team.

C.

Review the process and remove the impediment.

D.

Remove the certification need from the project scope.

Buy Now
Question # 139

A functional team member often becomes disruptive during status meetings and attempts to derail progress with the key stakeholders. This team member often discusses why the project will not be successful.

What should the project manager do?

Options:

A.

Investigate alternatives for team member needs.

B.

Evaluate the engagement needs for stakeholders.

C.

Identify the root cause of the team member's misunderstanding.

D.

Build trust and influence stakeholders.

Buy Now
Question # 140

In an organization transitioning to agile, the project team is in the norming phase. Team members became uncomfortable when the project manager assigned reporting responsibilities to the newest team member. Team members began questioning the project manager's decision.

What should the project manager do?

Options:

A.

Invite team members to volunteer for roles for which they feel qualified.

B.

Revoke the delegated responsibilities to keep the team members harmonious.

C.

Remind team members that administrative decisions are the project manager's duties.

D.

Explain the rationale for delegating responsibilities to team members.

Buy Now
Question # 141

A large and complex project is comprised of multiple regions. The estimate to complete (ETC) work is assumed to be performed at the same cumulative cost performance index (CPI) as that incurred by the project to date. As of now, the earned value (EV) is 145 person/day, the planned value (PV) is 145 person/day, the actual cost (AC) is 170 person/day, and budget at completion (BAC) is 285 person/day.

What is the estimate at completion (EAC)?

Options:

A.

334 person/day

B.

285 person/day

C.

310 person/day

D.

315 person/day

Buy Now
Question # 142

A project sponsor indicates that the time frame for a project needs to be shortened. The project network diagram cannot be modified, but there are extra resources available in the company.

What action should the project manager take?

Options:

A.

Crash the project schedule.

B.

Conduct earned value management (EVM) analysis.

C.

Fast track the project.

D.

Perform Monte Carlo analysis.

Buy Now
Question # 143

During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.

What should the project manager do next?

Options:

A.

Divide the team into small groups to avoid future arguments and delays.

B.

Ask the human resources (HR) department to replace the team members.

C.

Make a decision based upon the project manager's knowledge and expertise.

D.

Meet with the team members to discuss the priority of the project schedule.

Buy Now
Question # 144

A high-tech borehole project was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPI) of 1.09 and a schedule performance index (SPI) of 0.93. Six months after its completion, it is determined that the villagers could not access water.

What caused this situation to occur?

Options:

A.

The project was completed behind schedule.

B.

The requirements gathering was inadequate.

C.

The risk analysis was inadequate.

D.

The project was delivered above budget.

Buy Now
Question # 145

A project manager has been asked to participate in the procurement process for a

software application that allows customers to buy online e-learning courses. The project

manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?

Options:

A.

Ensure that the requirements for the project are understood and that the objectivesare verified before approval of an agreement.

B.

Inform the project sponsor that once the agreement has been signed, there cannotbe any changes to the scope of the project.

C.

Notify the project sponsor that the project manager cannot be involved in theagreement negotiation process.

D.

Ask the project sponsor to involve the legal department in the negotiation for the project agreement.

Buy Now
Question # 146

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

Options:

A.

Service level agreement (SLA)

B.

Statement of work (SOW)

C.

Scope management plan

D.

Memorandum of understanding (MOU)

Buy Now
Question # 147

A company has decided to create a new product to prepare itself for the changing economy. The technology required for the new product is not well understood yet, and the requirements are still being debated.

Which approach should the project manager advise for this project?

Options:

A.

Lean

B.

Predictive

C.

Agile

D.

Hybrid

Buy Now
Question # 148

A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.

What should the project manager of the contracting company do?

Options:

A.

Record that the delay is attributable to the client and request a meeting.

B.

Check the contractual terms about liquidated damages and reject if not applicable.

C.

Meet with the sponsor to analyze the delays and the associated liquidated damages.

D.

Schedule a detailed analysis of the delays using cause and effect.

Buy Now
Question # 149

The velocity of the team is decreasing at every iteration. The project team members are complaining that the user stories are being rejected by the quality assurance team.

Which three actions should the project manager take? (Choose three)

Options:

A.

Conduct a root cause analysis (RCA) and identify a solution.

B.

Elaborate on the plan to implement a solution and execute it.

C.

Increase the working time to recover the lost time.

D.

Negotiate with the teams involved to manage team dependencies.

E.

Evaluate the effectiveness of the proposed solution.

Buy Now
Question # 150

A project team has not been meeting its deliverables because they are not receiving adequate resources to do their job. What should the project manager do for the team to meet the upcoming deliverables?

Options:

A.

Ask the team to adapt based on their current resources.

B.

Plan a meeting with the stakeholders to get more resources.

C.

Replan the upcoming deliverables based on the available tools.

D.

Ask the project sponsor to provide the needed resources.

Buy Now
Question # 151

A compliance manager announces a new policy issued by the government that may impact project development.

How should the project manager respond?

Options:

A.

Continue with project execution as per the previously approved project plan.

B.

Maximize delivery by including this policy in the process.

C.

Address any blockers to the project due to this policy and resolve them.

D.

Analyze the circumstances that brought about this new policy.

Buy Now
Question # 152

An ongoing project with company A is impacted by the recent acquisition of company B. This could affect the current suppliers for the ongoing project.

What should the project manager do next?

Options:

A.

Retain company A's supplier based on the long-term relationship with them.

B.

Consolidate the list of suppliers for companies A and B.

C.

Engage the suppliers of company B to validate the current list of suppliers.

D.

Evaluate the project suppliers of company B for future use.

Buy Now
Question # 153

A department lead requested additional items be included in the project during the execution phase. Their acceptance is mandatory before the project can be closed.

Options:

A.

Find a way to accommodate the requested additions.

B.

Schedule a meeting to gain better understanding.

C.

Politely refuse the request stating the project baselines.

D.

Initiate a change request for the additional scope.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2025 Version)
Last Update: Nov 20, 2025
Questions: 2040
PMP pdf

PMP PDF

$139.65  $399
PMP Engine

PMP Testing Engine

$157.15  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$209.65  $599