Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 4

A project is in midway and a time-sensitive initiative was approved but it was later found there was no remaining authorized budget in the project. A new project manager was brought in at the execution phase.

What should the project manager do first?

Options:

A.

Evaluate the current cost performance to determine the required budget for completing the future tasks and risks.

B.

Calculate the budget needed to complete the remaining tasks in the project and include ample contingency reserves.

C.

Review the project ' s current expenses and advise what risks may arise.

D.

Talk to leadership to stop the project until all needed funds are secured.

Buy Now
Question # 5

During the execution of an agile project, the quality of one vendor ' s deliverables decreases significantly. After analyzing possible solutions, the project manager identifies an alternative vendor who can deliver similar components in smaller batches.

What should the project manager do?

Options:

A.

Meet with the current vendor to discuss alternatives for solving the situation.

B.

Adjust the project execution cadence to consider the alternative vendor.

C.

Update the project management plan and inform all the stakeholders about the new iteration lengths with the current vendor.

D.

Register the occurrence in the issue log and continue the project execution with the new vendor and shorter iterations.

Buy Now
Question # 6

During a review session, the team reports that the daily coordination meetings have been unproductive. The team asks the scrum master to implement a standard

format for the daily coordination meetings.

What should the scrum master do?

Options:

A.

Ask one of the team leads to prepare a structure for the next meeting.

B.

Coach the team about the purpose and objectives of these meetings.

C.

Propose an agenda for the next meeting.

D.

Change the frequency of the meetings to weekly.

Buy Now
Question # 7

A project manager was assigned to lead a construction project where a hybrid approach is recommended. A team with high levels of knowledge and experience is

required.

What should the project manager do next?

Options:

A.

Develop a risk register that includes the risk of a lack of experienced professionals.

B.

Develop a resource management plan that includes the roles and responsibilities to be met.

C.

Develop a procurement strategy that includes hiring external resources with the right skill sets.

D.

Develop a financial management plan that includes the budget to hire dedicated professionals.

Buy Now
Question # 8

A project is delayed because of an unknown risk impacting the budget. The project manager requests the project management office review the recommendation for a

budget increase.

What should the project manager have done to avoid going over budget?

Options:

A.

Allocated a management reserve budget during planning.

B.

Asked the project sponsor to provide additional budget for the project.

C.

Reviewed the risk with the sponsor and advised on funding sources.

D.

Reviewed the risk management plan and activated the contingency actions.

Buy Now
Question # 9

A product owner who possesses a strong technical background has been actively involved with the project team for several years. The product owner has been quite

vocal about the expected duration of the work. As a result, the project team has ceased providing development estimates to avoid causing any dissatisfaction with the

product owner.

What should the project manager do?

Options:

A.

Conduct a meeting with the project team and the product owner to reset the ground rules for providing estimates.

B.

Ask the project team to send the estimates via email and not to discuss them during planning meetings.

C.

Facilitate the meetings and ask the project team for the estimates.

D.

Meet with the product owner and project team separately to find a compromise.

Buy Now
Question # 10

A digital health development team is tasked with designing a new product, which is a pioneering effort for the organization and one of the few available in a

‘competitive market. The planning and auditing processes have been notably time-consuming. The development team has reported limited rework and minimal

customer complaints; however, the current budget significantly exceeds the typical project baselines for previous product development initiatives within the

organization. The project manager is currently analyzing the total cost of quality for the project.

What should the project manager do?

Options:

A.

Maintain the planned investment, appraisal, and prevention cost plan to reduce failure costs.

B.

Increase prevention costs to maintain project stability, reduce failure costs, and support the pace of change.

C.

Reduce internal costs to increase time to deliver value on schedule and on budget and reduce failure costs.

D.

Increase internal failure costs to detect defects early and minimize risks.

Buy Now
Question # 11

A project manager is developing a project schedule in which only the high-level scope is defined; the detailed work breakdown structure (WBS) is to be developed at

the beginning of each project phase. Project teams are focusing on short-term objectives and can only detail the scope for work they are currently performing. Despite

this, the project sponsor asks for a master project schedule.

What two actions should the project manager take in this situation? (Choose 2)

Options:

A.

Create a rough order of magnitude (ROM) schedule for the project activities with unclear scope, copying it from a previous project.

B.

Switch the entire project to an agile approach, where the project management plan can be prepared in detail as the scope evolves with the project ' s progress.

C.

) Tell the project sponsor that the master schedule cannot be completed since the complete details of the scope have not been discovered yet.

D.

Tell the project team to go with the predictive approach and complete all the details of the project scope before starting any work.

E.

Create a thorough schedule for the activities the team is currently working on and retain a high-level schedule for the remaining scope.

Buy Now
Question # 12

A project is delivering a new e-commerce platform. During execution, external market trends show shifting customer preferences toward mobile-first experiences.

There is uncertainty about whether the current feature set will meet user expectations.

What should the project manager do?

Options:

A.

Complete the current release and evaluate customer feedback after launch.

B.

Continue the current scope to maintain alignment with the original business case.

C.

Change the current scope to remove low-priority features and reduce schedule risk.

D.

Conduct a survey to gauge customer interest in the existing feature set.

Buy Now
Question # 13

A project manager has proposed starting to use artificial intelligence (Al) on a project to senior management. Some of the team members are skeptical due to security

and privacy challenges.

What should the project manager do?

Options:

A.

Ask leadership to give clear guidance to the team regarding Al.

B.

Form a team to work on the introduction and risks of Al.

C.

Select some ambassadors in the team to promote the use of Al.

D.

Ask line managers to give clear guidance to the team regarding Al.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (PMP) July 2026 Update
Last Update: Aug 19, 2026
Questions: 187
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599