Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 4

A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.

What should the project manager do to address this situation?

Options:

A.

Inform the steering committee of the situation and request additional resources.

B.

Coordinate virtual and face-to-face meetings at each site to improve communication

C.

Coordinate virtual meetings to assess the project team's communication needs

D.

Inform the project sponsor of this situation and request cultural orientation training.

Buy Now
Question # 5

In the middle of a project, a business unit manager who regularly interacts with the project manager's team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.

After getting more information about the new manager, what is the project manager's next step?

Options:

A.

Contact the previous business unit manager to learn more about the new manager.

B.

Update the stakeholder register and the stakeholder engagement plan to include the new manager.

C.

Send the new manager a copy of the project charter to ensure the project objectives are understood.

D.

Schedule a meeting with the new manager to discuss the business analysis team's plans.

Buy Now
Question # 6

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?

Options:

A.

Submit new user stories to the product owner in order to put documentation in the product backlog.

B.

Introduce a document management tool to support the agile teams in preparing the documentation.

C.

Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.

D.

Add an additional team member to take up the role of scribe for the required documentation.

Buy Now
Question # 7

A company is transitioning from a predictive to agile delivery of projects. Based on

the requirements, the project team estimates the budget and decides to use a fixed-price

contract with its vendor. However, during the execution of the project, the requirements

evolve and priorities start to change constantly, which puts the project and the estimate at completion (EAC) off by 40%.

What should the project manager do next?

Options:

A.

Send a detailed status report highlighting the issue with funding to all of the stakeholders.

B.

Submit a change request to the financial manager to increase the funding and continue as is.

C.

Meet with the stakeholders to recommend the use of a time and materials (T&M) contract to address the problem.

D.

Wait until the next gate review meeting to highlight the risk of low funds to the stakeholders.

Buy Now
Question # 8

The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders

What should the project manager do first?

Options:

A.

Determine which agile software tools will be required to support agile delivery within the organization

B.

Select a current predictive project define the approach, and provide agile training to execute the remainder of the project

C.

Start with a pilot project of appropriate complexity and provide agile training to those who are impacted

D.

Determine how to transform the organization using agile techniques, including organizational training and communications

Buy Now
Question # 9

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

% What should the project manager do next?

Options:

A.

Update the assumptions log and change log, and implement the change control process.

B.

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.

C.

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.

D.

Deliver what was planned in the project management document according to the specifications.

Buy Now
Question # 10

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?

Options:

A.

Accept the change and use contingency funds to implement this change with minimal schedule impacts

B.

Reject the change because it is contrary to what was agreed to during earlier phases of the project

C.

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps

D.

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor

Buy Now
Question # 11

A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?

Options:

A.

Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project

B.

Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes

C.

Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.

D.

Explain that distribution of important news can only be done using traceable communication methods

Buy Now
Question # 12

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?

Options:

A.

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.

B.

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.

C.

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder's final product.

D.

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.

Buy Now
Question # 13

A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?

Options:

A.

Assign the feature to another team member, and have them try to complete the feature by the end of this iteration

B.

Review team capacity and reassign the functionality to additional iterations as required

C.

Determine if the team member can work from home to complete the functionality.

D.

Review the work in progress with the product owner to determine the next step

Buy Now
Question # 14

A project manager has been assigned to take over an existing software project. The project manager inherited a lean team comprised of key stakeholders, subject matter experts

(SMEs), and senior developers. While reviewing the project status with the team, the project manager observes that the team seems to lack direction and enthusiasm.

What should the new project manager do?

Options:

A.

Ensure everyone performs their assigned tasks as planned.

B.

Organize frequent team building sessions and update the risk register.

C.

Meet with the project sponsor and propose a corrective action for the project.

D.

Encourage participation in decision making and empower the team.

Buy Now
Question # 15

A supplier was supposed to mobilize a government-issued, licensed piece of

equipment two days ago, but did not. The procurement manager was informed that the

supplier failed to check the validity of the license, which expired last week. The supplier had

already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path.

Which action should the project manager take?

Options:

A.

Update the project team on the delay so that resources can be utilized elsewhere.

B.

Analyze the schedule and look for fast tracking and crashing alternatives.

C.

Review the terms of the contract in order to determine next steps.

D.

Update the lessons learned register to serve as an input for future material transactions.

Buy Now
Question # 16

A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

Options:

A.

Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.

B.

Document the request and escalate to upper management to consider a modification of the project charter.

C.

Agree on a predictive approach, but apply agile concepts under the project management umbrella.

D.

Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.

Buy Now
Question # 17

A project manager brings in a new team member from an agile environment to work in a predictive environment The project manager expects to leverage the new team member's agile experience with the existing team members.

What should the project manager do to integrate the new team member effectively?

Options:

A.

Train the new team member in the predictive project management approach.

B.

Acknowledge that hiring this new employee is a risk to the existing team

C.

Set expectations with the new team member and explain what is needed

D.

Meet with all team members and explain the new employee's position.

Buy Now
Question # 18

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?

Options:

A.

Obtain approval from the project sponsor.

B.

Update the project management plan and mark the milestone as completed.

C.

Ask the vendor to validate the agreement for any deviations.

D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.

Buy Now
Question # 19

A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.

What is the first thing the project manager should do"?

Options:

A.

Include the requirement into the project and schedule it as soon as possible

B.

Inform the project sponsor about the situation and request assistance

C.

Evaluate the impact that the inclusion of this new requirement will have on project performance

D.

Inform the stakeholder that it is impossible to add new requirements to an approved project scope

Buy Now
Question # 20

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?

Options:

A.

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve

B.

Develop the quality management plan, as quality is as equally important as cost and schedule management.

C.

Get confirmation from management that the team member has enough experience

to build software without quality control

D.

Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project

Buy Now
Question # 21

A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?

Options:

A.

Log a risk in the risk register and work with the new team member to mitigate it

B.

Motivate the new team member to perform.

C.

Share project documents with the new team member.

D.

Offer cross-training and mentoring to the new team member

Buy Now
Question # 22

Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?

Options:

A.

Sent the meeting minutes to the stakeholders after the kick-off meeting

B.

Reviewed all the approvals immediately after the kick-off meeting was over

C.

Ran separate kick-off meetings for each culture and time zone

D.

Validated each stakeholder's understanding during the kick-off meeting

Buy Now
Question # 23

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

Options:

A.

Evaluate the impact to the users and create a plan to address it.

B.

Inform users about the new changes and ask for their collaboration.

C.

Ask all managers to collaborate implementing this change to users.

D.

Start implementing the change so that users will eventually get used to it.

Buy Now
Question # 24

A project manager is working on a major construction project. Part of the

agreed-upon plan was to use a cloud-based system with a server that runs on high-speed

internet service since most of the team members work virtually. The company needs to

reduce operating costs as much as possible and management insists that the project will

now use a system running on a conventional dial-up service.

What should the project manager do next?

Options:

A.

Evaluate the impact of this decision and communicate with management.

B.

Agree with management and continue working the project management plan.

C.

Meet with management about their decision and ask them to get another project manager.

D.

Replace some of the team members that work virtually to help the company save money.

Buy Now
Question # 25

After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

Options:

A.

Comply with the project sponsor's request to not archive the project artifacts.

B.

Document the project sponsor's instructions as the archived project artifacts.

C.

Archive the project artifacts on the project manager's local computer for future reference

D.

Consult with the project management office (PMO) for guidance on project artifacts.

Buy Now
Question # 26

A project manager has been asked to participate in the procurement process for a

software application that allows customers to buy online e-learning courses. The project

manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?

Options:

A.

Ensure that the requirements for the project are understood and that the objectives

are verified before approval of an agreement.

B.

Inform the project sponsor that once the agreement has been signed, there cannot

be any changes to the scope of the project.

C.

Notify the project sponsor that the project manager cannot be involved in the

agreement negotiation process.

D.

Ask the project sponsor to involve the legal department in the negotiation for the project agreement.

Buy Now
Question # 27

A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.

What should the project manager do?

Options:

A.

Inform the stakeholder that the new requirement will be considered in the next release planning session.

B.

Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.

C.

Ask the product owner to determine if this requirement needs to be treated as a top priority.

D.

Direct the development team to work on this requirement right away.

Buy Now
Question # 28

A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.

How should the project manager prepare for the next steps of the project?

Options:

A.

Escalate to the management team to increase the timeline based on the complexity of the project

B.

Wait for the other project estimates before planning the schedule

C.

Prioritize and estimate the milestones for the high-level requirements based on historical data

D.

Ask the project management office (PMO) to estimate the tasks for all the projects and share the project management plan

Buy Now
Question # 29

A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches

What should the project manager do about the development team's request"?

Options:

A.

Escalate the request for additional financial resources

B.

Forward the request to the project management office (PMO) to amend the organizational process assets

C.

Ask the project sponsor to obtain approval for implementation of the new approach

D.

Analyze the requirements that will need to be addressed under the requested method

Buy Now
Question # 30

A project manager for a building construction project is planning to go on vacation

midway through the project execution phase. What should the project manager do first to

ensure the team is empowered and deadlines are met?

Options:

A.

Allow the team to make decisions to stay on schedule.

B.

Postpone the vacation to a different time.

C.

Ask the project sponsor to make any necessary decisions.

D.

Analyze the impacts and create a plan for team decision making

Buy Now
Question # 31

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?

Options:

A.

The team with the higher velocity is performing better and should be rewarded.

B.

The issue should be addressed as part of a retrospective in the next iteration.

C.

The velocity should not be compared as teams can size items differently.

D.

The velocity of both teams should be compared at the end of every iteration.

Buy Now
Question # 32

A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.

How can the project manager convey these benefits to the stakeholders?

Options:

A.

Rebaseline the project schedule to show the current status of the project.

B.

Create a benefits management plan mapped to the organization's strategic objectives

C.

Perform a project cost-benefit analysis for the stakeholders

D.

Update the deliverables map against the agreed-upon project requirements

Buy Now
Question # 33

In a multinational project, stakeholders are in different time zones. The project

manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the

project sponsor that they know very little about the project.

What should the project manager do?

Options:

A.

Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.

B.

Ensure that the stakeholders who are complaining are present for the next project update meetings.

C.

Record the regular project update meeting and share it with all stakeholders after the meeting is completed.

D.

Change the meeting time to the working time zones of the stakeholders who are complaining.

Buy Now
Question # 34

A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?

Options:

A.

Determine a leadership style that is suitable for that location.

B.

Check if resources from headquarters can also be assigned to the project.

C.

Mentor the team members to perform project management.

D.

Assign a local resource to manage communication with the team.

Buy Now
Question # 35

An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?

Options:

A.

Provide feedback to the team and conduct a meeting to review the team rules.

B.

Provide feedback to the team and conduct a retrospective meeting to find a root cause.

C.

Provide feedback to the team and request agile training for the new member.

D.

Provide feedback to the team and coach the new team member in agile methodology.

Buy Now
Question # 36

A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?

Options:

A.

Request the team member to move to another team.

B.

Delegate other team members to complete this team member's tasks.

C.

Mentor the team member and provide the necessary training.

D.

Include this team member in an improvement program through a human resources request.

Buy Now
Question # 37

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

Options:

A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

Buy Now
Question # 38

The portfolio management office wants to cut costs by suspending some ongoing

projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio

management office has not backed down on their plan.

What should the project manager do to continue the project?

Options:

A.

Meet with the project team and revise the project goals.

B.

Update the project charter to make it align with organizational strategy.

C.

Demonstrate the project alignment to the organizational strategy.

D.

Escalate the issue with the project sponsor to request support.

Buy Now
Question # 39

A new agile project manager is trying to determine how the team is performing against the schedule for a release. Which tool will provide a deeper look into the team's progress?

Options:

A.

Release plan Sy

B.

Product roadmap

C.

Kanban board

D.

Burndown chart

Buy Now
Question # 40

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

Options:

A.

Meet with the team to reinforce their responsibilities and the consequences if the

project deliverables are not completed on time.

B.

Apply additional controls to the project deliverables to ensure that all milestones

are achieved on time.

C.

Contact the functional manager to ensure that team motivation remains high until

the end of the project.

D.

Schedule a team event with the project sponsor to highlight the importance of the

project and recognize the work of the team.

Buy Now
Question # 41

A newly hired team member just joined the project team and reports directly to the

project manager. In the first week, this new member tells the project manager that there is a

task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?

Options:

A.

Guide the team member on how to resolve the conflict.

B.

Analyze the project schedule and look for alternatives.

C.

Perform crashing and/or fast tracking of the schedule.

D.

Meet the team member and try to plan a course of action together.

Buy Now
Question # 42

A project manager is meeting with the project sponsor regarding a new project.

The project manager tells the sponsor that, as part of the communications management

plan, a weekly email will be sent with the status of the project, so the sponsor can be

informed of the progress. The sponsor indicates that the email is not necessary because

they will ask for a status update whenever it is needed.

What should the project manager do next?

Options:

A.

Advise the project sponsor to request a 15-minute meeting, whenever necessary, with prior notification.

B.

Agree to the project sponsor's request, but continue to copy them on the weekly email so they can be informed of progress in case it is needed.

C.

Tell the project sponsor that if they prefer to not receive the communication, there is no problem in removing them from the email distribution.

D.

Ask the project sponsor what sort of information is needed and agree on a frequency for the communication.

Buy Now
Question # 43

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.

What should the project manager do?

Options:

A.

Create an entry in the impediment board and assign it.

B.

Invite the project team to a swarming session to define a solution

C.

Leverage the network of the former department and ask for help

D.

Escalate the issue to the product owner to define the next steps

Buy Now
Question # 44

A project is ending and the final deliverables have been accepted by the customer. The project team is pleased that the project was a success: however, some groups within the customer's organization believe the objective of the project was not met.

What should the project manager have done to avoid this issue?

Options:

A.

Distributed a detailed quality management plan to the key stakeholders.

B.

Included the final report during the closing phase to ensure common understanding.

C.

Identified key stakeholders and included all of them in project agreement discussions.

D.

Performed project reporting according to the communications management plan.

Buy Now
Question # 45

A new facility project is being developed using a hybrid approach. After the third iteration, the project manager sees a decline in the team's productivity.

What should the project manager do next?

Options:

A.

Review the iteration duration with the team.

B.

Discuss the issue in the next retrospective.

C.

Encourage the team to improve their performance.

D.

Reduce the iteration backlog.

Buy Now
Question # 46

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

Options:

Buy Now
Question # 47

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?

Options:

A.

Ask stakeholders to communicate with the project manager and not directly with the team

B.

Empower the team members to remove obstacles and blockers

C.

Address and remove obstacles and blockers for the team

D.

Add blockers to the issue log and risk management plan

Buy Now
Question # 48

The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.

What strategy should the project manager use in order to keep delivering value in a restricted environment?

Options:

A.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance.

C.

Restrict the project scope only to basic critical features, and run the project with the current staffing level until all of the budget is consumed.

D.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction

Buy Now
Question # 49

During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.

What should the project manager do first?

Options:

A.

Communicate the problem to the sponsor to force the key member to be maintained on the project.

B.

Initiate a change request and replace the key member as soon as possible.

C.

Explain to the company the importance of maintaining the key member on the project according to the vision of the project.

D.

Evaluate the impact of the key team member's removal from the project, look for alternatives, and submit a change request if required.

Buy Now
Question # 50

The product team is progressing with a prototyping approach to deliver a multiyear business initiative A few user stones are taking longer to be delivered.

What should the project manager do?

Options:

A.

Determine the risks and identify a resolution during the retrospective meeting

B.

Inform stakeholders about the delay during project updates

C.

Determine cross-dependencies and plan a spike in the next spont

D.

Discover the gaps in the communications management plan and address them accordingly

Buy Now
Question # 51

According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

Options:

A.

Record it in the risk register

B.

Ask the client to help solve the problem

C.

Start procuring this material from another supplier.

D.

Engage the project team to look for alternatives to find a solution

Buy Now
Question # 52

A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.

How should the project manager communicate the organizational culture and project goal to these stakeholders?

Options:

A.

Hire a company to advertise the project and company through a media outlet.

B.

Prepare a report outlining the organizational structure and project parameters.

C.

Take the stakeholders out informally and verbally brief them about the organization and project.

D.

Ask a team member to directly address the information needs of the stakeholders.

Buy Now
Question # 53

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

Options:

A.

Conducted agile training for all employees ranging from the project teams through

mid-level to upper-level management.

B.

Conducted a postmortem and captured the learning in organizational process assets

(OPAs) for future use.

C.

Assessed the organization's culture, performed a suitability analysis, and determined

the future state.

D.

Hired a third-party agile delivery team to do the implementation.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2025 Version)
Last Update: Aug 22, 2025
Questions: 1988
PMP pdf

PMP PDF

$139.65  $399
PMP Engine

PMP Testing Engine

$157.15  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$209.65  $599