Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 4

Four new teams have been formed to develop a new product. Several team members ask the project manager who will integrate the different work streams into one backlog.

What should the project manager do?

Options:

A.

Create integration tasks and schedule an additional team meeting following the standup meeting to plan the integration.

B.

Advise the teams to work individually and organize an integration iteration every four development sprints.

C.

Instruct the team to use the kanban board daily to facilitate alignment of their work item list, allowing them to do their best work.

D.

Advise the teams to collaborate with the product owner in prioritizing the stories, considering dependencies and preventing overlap.

Buy Now
Question # 5

A project manager who has been working on an ongoing volatile project is retiring. A new project manager is collaborating with the retiring project manager to ensure a smooth transition.

What should the new project manager first discuss, review, and clarify during the transition meetings?

Options:

A.

Resource management plan

B.

Change management plan

C.

Lessons learned log

D.

Risk register

Buy Now
Question # 6

A project manager is hired to work on a very large, complex project that requires the team to complete a significant number of specialized tasks. What strategy should the project manager incorporate to help organize, assign, and monitor these tasks?

Options:

A.

Create a list of the tasks and send it to the project sponsor for review and approval.

B.

Develop a work breakdown structure (WBS) that decomposes the project deliverables into work packages.

C.

Schedule a meeting with the stakeholders to determine which tasks can be eliminated.

D.

Prepare a resource management plan that details all the resources needed to complete the tasks.

Buy Now
Question # 7

A project manager is leading a major water pipeline project and realizes midway into

the project that the project completion date is not achievable. Local farmers who rely on the

water for irrigation may be affected due to the delay. The project manager is afraid of their

displeasure and reaction, which will affect the project.

How should the project manager plan the communication to the stakeholders?

Options:

A.

Document and accept this risk and communicate this decision to the project sponsor.

B.

Collect feedback from the farmers and keep the information within the project team.

C.

Deliver the information to the stakeholders with the project management office ' s (PMO)assistance.

D.

Propose a solution to the stakeholders and communicate it to the local farmers.

Buy Now
Question # 8

A project manager is leading a large-scale project to be deployed in another country, for an external company. After working with the project team, the project manager learns there are many stakeholders from the project manager ' s organization, the client organization, and the local community.

What should the project manager do after identifying the stakeholders?

Options:

A.

Prioritize stakeholders from the client ' s organization and the local community.

B.

Prioritize stakeholders from the project manager ' s own organization.

C.

Prioritize the stakeholders that are more interested in the success of the project.

D.

Prioritize the stakeholders that may have more impact on the development of the project.

Buy Now
Question # 9

A project manager is leading a team and wants each team member to produce their deliverables and be held accountable for the work product. What should the project manager do first?

Options:

A.

Engage with each project team member to explain the individual consequences of late delivery.

B.

Establish a daily standup meeting where each project team member reports their progress.

C.

Create a plan of action and milestones (POAM) to detail the deliverables for each project team member.

D.

Empower each project team member with ownership of a particular aspect of the project.

Buy Now
Question # 10

A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.

What should the project manager do next?

Options:

A.

Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body.

B.

Identify the missing requirements, prioritize the missing compliance work directly into the backlog, and assign the work to the team.

C.

Reschedule the launch of the product until the team can produce a prototype for inspection as required by the compliance team.

D.

Create an MVP that contains the scope for the prototype and that will be prioritized with the compliance team.

Buy Now
Question # 11

A project manager with global teams is managing a project that is progressing as expected. However, recently the project manager has learned of some team members missing the daily meetings. After investigating the issue, the project manager realizes different time zones is the main cause of the issue.

What should the project manager do next?

Options:

A.

Schedule a team-building workshop involving all teams to support better communication.

B.

Schedule a meeting and ask all teams to sort the issues and move ahead with full participation.

C.

Ask everyone to only invite team members in different parts of the world as necessary.

D.

Share the time-overlap schedule with the team to make meeting scheduling convenient.

Buy Now
Question # 12

A project manager is finalizing the project charter and has invited the project sponsor and key stakeholders to confirm the project estimates. The project manager suggests adding a budget reserve to meet unforeseen risks, but the project sponsor disagrees.

What should the project manager do?

Options:

A.

Demonstrate that risky projects are subject to change so adding reserves to the budget is a necessity.

B.

Explain to the project sponsor and key stakeholders the need to add the reserve and get their buy-in.

C.

Seek key stakeholders ' approval and finalize the budget with the reserve.

D.

Agree with the project sponsor and finalize the budget without the reserve.

Buy Now
Question # 13

A project manager is leading a highly visible project initiative. A few weeks after kickoff, the project manager starts receiving requests for updates from various stakeholders. What should the project manager do?

Options:

A.

Remove those stakeholders from the project since they may negatively affect project goals

B.

Invite all project stakeholders to join the daily standup meeting to ensure they are informed

C.

Schedule a meeting with relevant stakeholders to review the project communications plan

D.

Explain to the stakeholders that they must request project updates from the project sponsor

Buy Now
Question # 14

A project manager is working on a project that is using a hybrid approach. One key input for the deliverable will be from the outcome of another project that is using an agile approach.

What should the project manager do next?

Options:

A.

Ask the other project manager to change the delivery methodology.

B.

Request that the other project manager develop a work breakdown structure (WBS).

C.

Participate in the other project ' s daily standup meetings.

D.

Align with the other project manager ' s high-level project time lines.

Buy Now
Question # 15

A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.

What should the project manager do?

Options:

A.

Implement the agile risk manifesto to ensure the proper tracking, analysis, and remediation of the project risks.

B.

Ask the product owner to act as a risk manager to assist with the remediation of risks.

C.

Implement the role of an agile risk manager to take care of the risk management process.

D.

Follow the risk management process while ensuring that risks are identified, analyzed, and managed during each iteration.

Buy Now
Question # 16

A project manager is leading a project with a risk management plan detailing strategy and actions if any identified risks become an issue. One of the identified risks becomes an issue, but the project manager believes the planned response may not be the best. What should the project manager do?

Options:

A.

Meet with the project team and sponsor to reevaluate all issue responses registered in the risk management plan

B.

Escalate the issue to the sponsor and register the new risk response in the project documents

C.

Adopt the action prescribed in the risk management plan since it was agreed to beforehand

D.

Submit a change request to perform a different issue response than what is registered in the risk management plan

Buy Now
Question # 17

A supplier that the company has used for years has trouble accepting the new terms of an agile contract. They do not understand the terms in the contract and feel they should not have to sign it because they have had a long relationship with the company.

Which action should the project manager take?

Options:

A.

Ask the team if they can do the work until there is an available supplier.

B.

Train the supplier in agile approaches to help them understand the contract.

C.

Issue a request for proposal (RFP) to find new suppliers with agile experience.

D.

Change contract terms and conditions to avoid losing the supplier.

Buy Now
Question # 18

The team ' s work assignments have been generically distributed. A new team member is performing slower than expected.

What should the project manager do?

Options:

A.

Extend the project timeline to allow the new team member to work at their own pace.

B.

Have all of the other team members retrain the new team member to improve team performance.

C.

Change the way the work assignments are distributed to facilitate new team member development.

D.

Assess the new team member ' s skills in order to determine additional training needs.

Buy Now
Question # 19

Construction work is preventing the project team members from entering the building where their offices are located.

What should the project manager do next?

Options:

A.

Inform the authorities so that they are aware of the situation and can take appropriate action.

B.

Continue business as usual since the construction work is not related to the project.

C.

Select the next action to be taken according to the risk management plan.

D.

Communicate with the stakeholders about the construction and ask for direction.

Buy Now
Question # 20

A project manager is working with a team that is demotivated and tired, as the project has been changing direction due to budget cuts from the sponsor.

What should the project manager do first?

Options:

A.

Meet with the team to define together a plan that would help them deliver despite the budget cuts.

B.

Work with the team to understand what can motivate them to try and complete the project.

C.

Remind the team of their commitment with the client and the need to adapt to the client ' s needs.

D.

Call the sponsor and ask for a meeting to clarify the scope before working any further on the project.

Buy Now
Question # 21

A high-tech borehole project was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPI) of 1.09 and a schedule performance index (SPI) of 0.93. Six months after its completion, it is determined that the villagers could not access water.

What caused this situation to occur?

Options:

A.

The project was completed behind schedule.

B.

The requirements gathering was inadequate.

C.

The risk analysis was inadequate.

D.

The project was delivered above budget.

Buy Now
Question # 22

A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.

What should the project manager of the contracting company do?

Options:

A.

Record that the delay is attributable to the client and request a meeting.

B.

Check the contractual terms about liquidated damages and reject if not applicable.

C.

Meet with the sponsor to analyze the delays and the associated liquidated damages.

D.

Schedule a detailed analysis of the delays using cause and effect.

Buy Now
Question # 23

A project manager just took over a construction project which was already in its execution phase. Labor union representatives of the construction workers ask to revise the overtime per hour rate, as wage per hour have increased across the industry.

What should the project manager do first?

Options:

A.

Obtain approval from sponsors to increase the rates because it can affect project due to lack of resources.

B.

Carefully read the agreements and see if there was any clause if the per hour rate could be increased.

C.

Assign a team member to negotiate the increased wage per hour with the labor union representatives.

D.

Negotiate with the labor union representatives if the clause about increased wage per hour meets their requirements.

Buy Now
Question # 24

During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.

What should the project manager do next?

Options:

A.

Divide the team into small groups to avoid future arguments and delays.

B.

Ask the human resources (HR) department to replace the team members.

C.

Make a decision based upon the project manager ' s knowledge and expertise.

D.

Meet with the team members to discuss the priority of the project schedule.

Buy Now
Question # 25

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team ' s integration leads is a subject matter expert (SME) m this integration area. The other team ' s integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?

Options:

A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer

B.

Meet with both integration leads to understand the root cause and determine a resolution

C.

Escalate the issue to the program architect who developed the integration plan

D.

Assign the resolution of this issue to the integration lead who is a SME

Buy Now
Question # 26

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.

What should the project manager do next?

Options:

A.

Escalate the obstacle to a servant leader for resolution.

B.

Make changes to reprioritize the backlog because of the obstacle.

C.

Reject the obstacle and present the partial solution to the customer.

D.

Focus on generating business value despite the obstacle.

Buy Now
Question # 27

A major issue regarding conflicting priorities has been highlighted by the project team with respect to a few stakeholder requirements.

What should the project manager do?

Options:

A.

Escalate to the project management office (PMO) and request a solution for the requirements.

B.

Prioritize other items for the team and deal with the conflicting requirements later.

C.

Allow the project team to decide which requirement is the most appropriate to follow.

D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

Buy Now
Question # 28

A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.

What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?

Options:

A.

Involve all of the stakeholders in the escalation by setting up a conference call.

B.

Escalate to the other party ' s management and inform the steering committee.

C.

Reach out to peer managers for similar escalation situations and follow past experiences.

D.

Review the established project escalation process and take the appropriate action.

Buy Now
Question # 29

An important project to build a new airport was suddenly stopped because of the complaints from residents in the surrounding communities. The residents stated that they were not consulted and that the project would cause ecological and pollution damage.

What should that project manager have done first in order to avoid this situation?

Options:

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

Buy Now
Question # 30

An organization has successfully delivered many projects using only predictive approaches. The organization has now decided to add some agile development processes into their standard deployment framework.

What should the project manager take into account first when building the schedule for this new project?

Options:

A.

The benchmarked velocities of the previously completed projects

B.

The benchmarked baselines of the previously completed projects

C.

The compliance needs and categories of the new project

D.

The compliance measurement criteria of the new project

Buy Now
Question # 31

At the first retrospective meeting, a developer in a newly formed team points out that frequent delays in documenting the requirement solution are impacting the workflow. The developer wants to know why the analyst is not doing their job on time. Confronting the analyst causes a conflict that quickly escalates. The analyst is certain that the documentation process is not solely their function.

What should the project manager do to resolve the conflict and prevent future conflicts as the team matures?

Options:

A.

Facilitate a conflict discussion and find a win-win situation for both parties so that they can continue to work together.

B.

Allocate additional key resources and document who will be held accountable for the various aspects of the team ' s workflow.

C.

Clarify the role ambiguity and define resource responsibilities with the team using a responsibility assignment matrix (RAM).

D.

Set up a group discussion after each requirement is discussed to understand the dependencies that can impact workflow.

Buy Now
Question # 32

A company is working on the prototype of a new contract document that includes visual elements. The product owner shared the project sponsor ' s feedback about the elements to be included, but the project team pushed back. However, when the project sponsor spoke with the team, they confirmed that all of the changes are possible.

How should the project manager mitigate this situation?

Options:

A.

Execute a retrospective meeting to solve the misalignment.

B.

Review the actions listed in the risk management plan.

C.

Review and update the organizational process assets (OPAs).

D.

Submit a change request to replace the product owner.

Buy Now
Question # 33

A company has decided to create a new product to prepare itself for the changing economy. The technology required for the new product is not well understood yet, and the requirements are still being debated.

Which approach should the project manager advise for this project?

Options:

A.

Lean

B.

Predictive

C.

Agile

D.

Hybrid

Buy Now
Question # 34

A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.

What type of contract and project approach should the project manager consider?

Options:

A.

Time and materials (T & M) with an agile approach

B.

Cost reimbursable contract with a predictive approach

C.

Fixed-price contract with a predictive approach

D.

Memorandum of understanding (MOU) with an agile approach

Buy Now
Question # 35

While an iteration is in progress, a project manager notices a delay in the prototype. The sponsor reaches out to the project manager and suggests engaging with cross-functional stakeholders.

What should the project manager do?

Options:

A.

Analyze the delay and discuss the findings with the subject matter expert (SME).

B.

Ask the developers to discuss the delay at a retrospective.

C.

Request that the product owner assess whether the team needs an external subject matter expert (SME).

D.

Record this in the issue log and define further steps.

Buy Now
Question # 36

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager ' s expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?

Options:

A.

Attend only the program meetings where the market launch is being monitored

B.

Provide an answer via email recommending a division of tasks between both roles.

C.

Politely inform the program manager that attending these meetings is no longer required.

D.

Schedule a meeting to discuss the different perspectives and agree on a decision.

Buy Now
Question # 37

An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team ' s performance is not good, and some team members want to leave the team.

How should the project manager approach this situation?

Options:

A.

Measure the team ' s psychological safety.

B.

Reschedule the team ' s retrospective meeting.

C.

Coach the team to be more inclusive.

D.

Rotate the team ' s daily meeting roles frequently.

Buy Now
Question # 38

A project manager is executing a project on time and on budget. Before a stage gate review, the project manager receives the regular business management report, but this time it entails a negative impact on the project success factors.

What should the project manager do?

Options:

A.

Request a delay to the stage gate until business development provides the next update.

B.

Call for business development to revalidate inputs at the next stage gate.

C.

Provide the necessary analysis to enable examination of the business value.

D.

Continue with execution since the project was successful up to this phase.

Buy Now
Question # 39

A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

Options:

A.

Ensure that relevant stakeholders and expectations are identified and assess the component delay.

B.

Perform a detailed analysis of the release content for each component of the solution.

C.

Propose a new design of the solution to replace the external component with an internal one.

D.

Ask for expedited delivery of the component to mitigate the risk of schedule delays.

Buy Now
Question # 40

An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.

What should the project manager have done first to avoid this situation?

Options:

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

Buy Now
Question # 41

A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.

What should the project manager do?

Options:

A.

Give some advice to the team member to reduce their stress and anxiety.

B.

Review team participation in the next retrospective meeting with all team members.

C.

Reach out to the team member to discuss and address their concerns as soon as possible.

D.

Evaluate upcoming project deadlines and reorganize team member assignments.

Buy Now
Question # 42

A project is using a Scrum team from a new vendor to deliver a component. Engaging a new vendor was identified as a delivery risk that, if eventuated, must be escalated to the board. The project manager and product owner work well with the Scrum team, but the vendor misses the first release by a couple of weeks.

What should the project manager do?

Options:

A.

Escalate the issue to the board with opportunities to recover the delay as soon as possible.

B.

Work with the product owner and the Scrum team to add 2 weeks to the release schedule.

C.

Work with the product owner and the Scrum team to recover the delay before the last release.

D.

Escalate the issue to the board and plan for the engagement to be terminated.

Buy Now
Question # 43

A project manager is facilitating meetings with a diverse team, considering that the team members come from different cultures and have different backgrounds. What should the project manager do to facilitate effective communication?

Options:

A.

Create incentives to promote better communication among team members.

B.

Assign the work packages based on geographical working groups.

C.

Understand and consider the emotions of each team member.

D.

Plan for communication training workshops for all team members.

Buy Now
Question # 44

During planning, a virtual project team agreed to the project reporting structure and established a meeting cadence that fits multiple time zones. One month into execution, the project manager notices that certain members are disengaged during project meetings.

What should the project manager do to resolve this issue?

Options:

A.

Work with the team to review the effectiveness of the agreed project practices.

B.

Set up follow-up sessions on all action items for team members.

C.

Distribute the meeting agenda and objectives the day before the project meetings.

D.

Review the project reporting structure to clarify the project objectives.

Buy Now
Question # 45

A virtual project team has members located on four continents. The project director is concerned about the declining motivational levels of team members and feelings of noninclusion by other team members. The project director has tasked the project manager with finding a solution.

What should the project manager do?

Options:

A.

Develop a plan for individual team members ' growth and organize more team-building events.

B.

Recommend that the project director appoint project managers for each continent.

C.

Set up ground rules for team engagement, taking into consideration different cultures.

D.

Take differences in time zones into consideration when scheduling team meetings.

Buy Now
Question # 46

A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.

What should the project manager do to address this concern?

Options:

A.

Register the issue as a risk with the project team members.

B.

Review the project schedule with project team members and the suppliers.

C.

Advise the procurement department to develop a new supplier strategy.

D.

Use the procurement and risk management plans to manage this issue.

Buy Now
Question # 47

An organization is implementing a solar power system at its production plant. During the execution phase, one of the key stakeholders noticed and communicated that authorities are developing solar power regulation, which might impact the overall feasibility of the project.

What should the project manager do first?

Options:

A.

Collect and analyze information about the new regulation.

B.

Put the project on hold and wait for the regulation information to be confirmed.

C.

Proceed with the project as long as the regulation is not yet finalized.

D.

Meet with the sponsor to discuss the regulation issue and determine the proper action.

Buy Now
Question # 48

A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.

Which three actions should the project manager take? (Choose 3)

Options:

A.

Develop the project management plan based on the requirements requested by the customer.

B.

Develop the application as requested by the customer, based on the approved project requirements.

C.

Plan a minimum viable product (MVP) to get early feedback from the customer.

D.

Facilitate a focus group to assess the functionality before development.

E.

Use an agile approach to deliver the product based on sprints.

Buy Now
Question # 49

A project manager is new to an organization that typically follows a hybrid approach but is shifting to incorporate more agile. A dedicated project team has been provisionally assigned. The new project manager needs to review the internal environment in order to build a high-performing team.

To build a high-performing team, which three factors should the project manager evaluate? (Choose 3)

Options:

A.

Review the team ' s capability to determine if they have the skill set needed to proceed forward.

B.

Evaluate the infrastructure to determine if the team has the appropriate equipment and communication channels.

C.

Perform a benchmark analysis across similar sectors to determine if the structure can be followed.

D.

Review the customer governance documents so that they align with the set expectations.

E.

Assess the organizational culture to determine if more needs to be done to foster psychological safety.

Buy Now
Question # 50

A product owner is continuously adding requirements to a project that will significantly impact project delivery. How should the project manager address this?

Options:

A.

Reprioritize the work and add all new work to the product backlog.

B.

Check with the project team about their availability to continue project work.

C.

Consult with senior managers on how to address this to ensure the product owner ' s expectations are fully met.

D.

Ask the product owner to reprioritize and consider the project done when the highest priorities are delivered.

Buy Now
Question # 51

A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.

What action should the project manager take?

Options:

A.

Organize a training for the new team member on the processes the team is currently using.

B.

Speak with the new team member at the retrospective and discuss potential improvements.

C.

Formalize the new processes and implement the team member ' s proposed changes.

D.

Hold a team meeting on governance, operating policies, procedures, and practices.

Buy Now
Question # 52

A project manager is leading a diverse global team. The team members disagree about the requirements for a recently approved change request. The conflict among the team members has resulted in low morale and decreased performance.

What should the project manager do?

Options:

A.

Allow the most senior team member to make a decision and communicate the decision to the team members.

B.

Speak with the team members about their disagreement and seek clarity regarding the requirements.

C.

Ask for advice from the human resources (HR) department about how to handle the situation.

D.

Escalate to the change control board (CCB) and have them seek clarity on the requirements of the change.

Buy Now
Question # 53

A project manager is assigned to lead a design for a new version of an existing

product with the technology and operations teams. The project manager organizes a joint

requirements session to determine the most practical ideas. The project manager was advised

that the session may become chaotic.

What should the project manager do to ensure the session is interactive, productive, and

efficient?

Options:

A.

Pick the senior and experienced staff members from both teams and arrange face-toface interviews.

B.

Organize a formal session led by a skilled facilitator with defined rules for howparticipants will interact with one another.

C.

Distribute a questionnaire on the key features of the product and encourage the teamsto respond with their design recommendations.

D.

Hold multiple sessions of manageable sizes with participants from both teams todiscuss their ideas.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (PMBOK 7th Version)
Last Update: Jul 5, 2026
Questions: 2196
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599