An agile team member discovers an impediment that is preventing them from doing their work efficiently. At which of the meetings should they bring up this impediment for resolution?
A project team needs to create artifacts for an upcoming steering committee.
What should the project manager do first?
The key stakeholder of an agile project has low visibility of the project's progress. The stakeholder expresses a concern to the project manager about whether or not the scope is moving in the right direction.
What should the project manager do?
A virtual project team has members located on four continents. The project director is concerned about the declining motivational levels of team members and feelings of noninclusion by other team members. The project director has tasked the project manager with finding a solution.
What should the project manager do?
A project manager is trying to define a project time line despite having incomplete and ambiguous information on requirements and regulations. What should the project
manager do to finish planning?
A project manager has developed a communications management plan. A junior team member asks why they are duplicating efforts by producing different versions of the same newsletter.
How should the project manager respond?
The project team is conducting iteration planning and having difficulty evaluating a new technology that will be used in this iteration. What should the project lead do?
A scrum master is receiving conflicting status updates for the same task. How should an accurate status be obtained from the team?
A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.
Which three actions should the project manager take? (Choose 3)
A project manager was just assigned to an ongoing project. According to the project's status, all the increments produced passed the acceptance criteria. During the last meeting with the project sponsor, the prototype is far from the sponsor's original expectations.
What should the project manager do first?
A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.
What should the project manager ask the team to do?
A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?
During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.
How should the project manager properly address this situation?
A project leader is preparing to facilitate a sprint retrospective. The sales manager sends the project leader an email asking how a feature planned for the next shipment is being implemented.
What should the project leader do next?
A large and complex project is comprised of multiple regions. The estimate to complete (ETC) work is assumed to be performed at the same cumulative cost performance index (CPI) as that incurred by the project to date. As of now, the earned value (EV) is 145 person/day, the planned value (PV) is 145 person/day, the actual cost (AC) is 170 person/day, and budget at completion (BAC) is 285 person/day.
What is the estimate at completion (EAC)?
An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)
An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?
During the third iteration, the team encounters a major delay that has not had significant improvements over the last few weeks What should the project manager do?
A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.
What should the project lead do?
A team member increased the estimated completion time for their activities on the critical path. This action, however, has caused friction among the team members. The project manager reviewed the key performance indicators (KPIs) that show the issue.
What should the project manager do first?
The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?
A project manager is managing a project that will engage resources from multiple countries in different time zones. What should the project manager do to ensure that team members are effective?
A transformation project that is composed of agile streams has come to an end.
How should the project manager collect the experience gained during this project?
During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?
A sales director is upset that progress has been slow on the delivery of critical features to the customer. After consulting with the team, the project manager learns that a subject matter expert (SME) on the customer side is not cooperative in providing the input needed to complete the definition of ready (DoR).
What should the project manager do to avoid the same problem in future projects?
A strategic project using international funds for a government agency is going through the execution phase. The government transition will take place in 1 month, and authorities will change. There is a risk that the project will be suspended or team members will be removed. The project manager wants to ensure that the project will continue despite these changes.
Which action should the project manager take to address this situation?
During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?
One of the main deliverables of a project is delayed due to a problem with a key provider. What should the project manager do?
Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.
What should the project manager do when made aware of these issues?
A team is working on implementing a communications system when the client says that they are considering closing the project. The project manager schedules an urgent meeting with the client to understand why the project is at risk Which two tools or techniques can the project manager use to influence the client’s decision to keep the project active? (Choose two)
A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.
What should the project manager do?
During a contract renewal meeting, an organization's commercial team and the customer are disagreeing and negotiations are failing. What should the project manager do to reach an agreement that will satisfy all parties?
A project team is working on a critical release and the customer wants this feature to be made available as early as possible. The business owner suggests an enhancement during the product demo.
How should the project manager address this request?
An important project to build a new airport was suddenly stopped because of the complaints from residents in the surrounding communities. The residents stated that they were not consulted and that the project would cause ecological and pollution damage.
What should that project manager have done first in order to avoid this situation?
A project manager who is experienced in predictive and adaptive approaches has been assigned to a new project. Most of the project
stakeholders have only worked on predictive projects, and only a few have been exposed to adaptive projects.
What should the project manager do?
A project is starting its first iteration out of six. During one of the daily meetings, the project manager realized that one of the team members does not have experience working in agile environments.
What should the project manager do?
A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.
What should the project manager do next?
A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?
An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.
What should the project manager have done first to avoid this situation?
In an organizational upper-level management meeting, the CEO shows interest in a project of which they were not previously aware. After the meeting, what should the project manager do to ensure the CEO's support?
A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.
Which tool should the project manager use for this purpose?
A department lead requested additional items be included in the project during the execution phase. Their acceptance is mandatory before the project can be closed.
During a progress review meeting, the project sponsor requests a complete revamp of the product roadmap to meet the strategic objectives based on market conditions. This change will result in a completely new product.
What should the project manager do first?
A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter
What should the project manager do?
During project execution, a project manager is leading the team to work on the project schedule. During a meeting, the team has difficulty understanding the complexity of a task and is unable to provide an estimate for the required resources.
What should the project manager do first to resolve this issue?
A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.
What should the project manager do next?
A key project stakeholder recently joined the project and is questioning some of the previously made decisions. This starts to impact project execution.
What should the project manager do?
The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?
A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.
What should the project manager do?
Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.
What should the project manager propose?