A new stakeholder is unaware of the existence of the project a few weeks before the final deliverable and project completion. What should the project manager do first?
A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder ' s presence has had a negative impact on the team ' s morale, while also impacting productivity
How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?
A project manager was appointed to lead an already approved project. While reviewing the benefits management plan, the project manager finds out that the information about the forecasted value of the project may not be accurate.
What should the project manager do?
A project is almost complete when a key stakeholder raises a concern because the functionality of their preferred requirement was not showcased in the prototype. The prototype has already been approved and developers have started work on the final application. What should the project manager do next?
After difficult negotiations, a customer committed to pay the cost for changes to the
project scope. The team seems unhappy as the project completion time will take longer than
previously scheduled.
How should the project manager support the outcome of the new agreement?
A project manager is leading a project with a negative risk that has just become an issue. The risk has been recorded, and a response plan has been set. However, a project team member proposes a response that differs from the response recorded in the risk management plan, which the team member believes will be cheaper and equally effective.
What should the project manager do?
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.
What should the project manager do next?
A project manager is using a centralized management and leadership style for a project. The project design does not meet the expected outcomes at later stages of the project.
What is the most important action the project manager should have taken to prevent this?
During the planning phase of a project, there is one activity for which duration and cost cannot be estimated. A project team member recalls that this activity was performed previously in another project in the company.
What should the project manager do so the project can move forward?
A newly appointed product owner is working with a project team that is using agile
for the first time. The product owner is constantly disrupting various team members throughout
the day to discuss progress. This has resulted in the team feeling micromanaged and
frustrated because of the constant disruptions.
How should the project manager proceed?
A project team consists of several consultants from an external vendor. These consultants often change from month to month.
What should the project manager do to communicate the organizational values?
Phase 1 of a project has been implemented and moved into post-production support, while phase 2 development has started. During phase 1 closeout, team members are asked by the product manager to work on the phase 1 backlog items that are not in the approved requirements document. The team members complain that no one is in charge of production issues.
What two actions should the project manager take? (Choose 2)
An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern ' s mentor Two months later, the project goes into critical status, delaying the release milestone by a month.
What should the project manager have done to avoid this scenario?
A project manager has been informed by a vendor that a shipment with supplies needed for the project will be delayed by six weeks. What should the project manager do first?
A project manager recognizes that a key stakeholder is not engaged in the project and does not seem interested in the project status. The project manager is concerned that the project may go off track if the stakeholder expectations are not met
How should the project manager approach the stakeholder?
A project manager is leading a contract for a new market that was awarded to their company. The client has the desire to jump-start the market with informal sector traders. What should the project manager do?
A product owner asks a project manager for details about products that were added during the last iteration. What should the project manager do to gather this information and send it to the product owner?
A project manager is leading a project with a negative risk that has just become an issue. The risk was recorded and a response plan was set. However, a project team member proposes a response that differs from the response recorded in the risk management plan and believes it will be cheaper and equally effective. What should the project manager do?
A project manager is leading a project with a risk management plan detailing strategy and actions if any of the identified risks become an issue. One of the identified risks becomes an issue, but the project manager acknowledges that the response considered in the risk management plan may not be the best.
What should the project manager do?
Three months after creating a project schedule, the scope of a project significantly changed, resulting in a schedule rebaselining. One month after rebaselining, the project is two weeks behind schedule with a cost performance index (CPI) of 0.93. What should the project manager do to help get the project back on schedule?
Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget.
What should the project manager do first to obtain the funding to hire the needed resources?
A project has a very demanding and sensitive business stakeholder who functions as a subject matter expert (SME). The project manager has assigned two different team members to work with the stakeholder. However, both team members have complained that the stakeholder is difficult to work with.
What should the project manager do first?
A project manager has been assigned to a new agile project with rapidly changing knowledge areas. How should the project manager manage knowledge transfers on this project?
During a status meeting, a project manager reported that a project is on track. However, the project sponsor thinks the project is behind schedule because a few tasks have already passed their planned finish dates but are still in progress. How should the project manager revise the report and demonstrate the project is on schedule?
A project manager is trying to define a project time line despite having incomplete and ambiguous information on requirements and regulations. What should the project
manager do to finish planning?
A project manager is leading a team delivering new software to a finance team. The new software will streamline the finance team’s monthly closing activities and reporting. What should the project manager use to promote knowledge transfer for the new solution?
During the team’s daily meetings, the project manager notices that some team members are consistently experiencing blockers due to communication issues and misunderstanding process directions.
How should the project manager proceed in this situation?
An experienced project manager has recently joined a jeopardized project. The project is being impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot add a new vendor, and the project must be completed within a maximum of 90 days as agreed.
What should the project manager do?
An agile project has a documented list or requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.
What should the project manager recommend?
A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.
What should the project manager do?
The portfolio management office wants to cut costs by suspending some ongoing
projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio
management office has not backed down on their plan.
What should the project manager do to continue the project?
A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.
What should the project manager do?
A project manager has recently been appointed to lead a critical software development project in a hybrid environment. What should the project manager do first to understand the project quickly and manage the project effectively?
An increment was delivered to the customer at the end of a sprint. The customer complains that the product does not meet the expected quality and will require some rework. What should the project manager do next?
A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed.
What should the project manager do?
A project manager has been informed by a vendor that a shipment of supplies needed for the project will be delayed by 6 weeks.
What should the project manager do first?
A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received, demanding that the project be stopped.
What should the project manager do first?
A project management plan needs to be updated due to recent product requirements changes, but the latest version of the document is missing. What should the project manager do to prevent this from happening again?
A new project includes important product features that should be delivered as soon as they are completed during the following quarter. The project team consists of junior and senior technicians.
Which two actions should the project manager take to deliver product features as soon as possible? (Choose 2)
A company is engaged in a transformation journey, and the project manager for this endeavor is new to the project. During one of the project status update meetings, a key stakeholder, who is also the project manager’s functional manager, is dissatisfied with the work in progress and points to the project manager.
What should the project manager do?
A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed. What should the project manager do to deliver business value to the client?
A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.
What is the first step the project manager should take?
A project manager is working on a global project and realizes that one team member is not performing as expected. The project manager meets with the team member to find out what is causing this low performance. The project manager discovers the team member is experiencing conflict and feels uncomfortable with the team. The team member then asks to be moved to another project.
What should the project manager do?
Developers spend most of the sprint writing code for user stories, leaving little time for testing. As a result, user stories cannot be tested in time and the stories remain unfinished by the end of the iteration, resulting in poor metrics.
What should the scrum master do first in this situation?
During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project ' s cost and schedule.
What should the project manager do first?
A project manager recently took over an ongoing project. Within a few weeks on the project, the project manager discovers that there are continuous change requests from different project end users. What is the probable cause for this?
During a sprint planning meeting, a project team analyzes the effort required to complete some of the tasks before aligning on a sprint commitment. The project team faces issues when trying to estimate the testing effort for the tasks. What should the project manager do first?
A project team completed sprint planning, but at the end of the session the project lead receives a message from a stakeholder about a legislative change that requires a new validation rule in one backlog item committed for the sprint. What should the project lead do?
An agile project team is working on a large project involving multiple cross-functional teams in different geographical locations. Some team members are not clear on the next tasks.
Which strategy should the project lead implement to help the team?
Shipping problems are impacting the supply chain worldwide, and the project ' s primary vendor has indicated potential delays in supplying certain equipment that will be ordered later in the project. What should the project manager do with this information?