Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 154

An agile team member discovers an impediment that is preventing them from doing their work efficiently. At which of the meetings should they bring up this impediment for resolution?

Options:

A.

Sprint review meeting

B.

Retrospective meeting

C.

Daily Scrum meeting

D.

Sprint planning meeting

Buy Now
Question # 155

A project team needs to create artifacts for an upcoming steering committee.

What should the project manager do first?

Options:

A.

Use templates from an existing project.

B.

Ask the project management office (PMO) for guidance.

C.

Surveying peers to understand what templates they have used.

D.

Lead the project team in finding the best templates.

Buy Now
Question # 156

The key stakeholder of an agile project has low visibility of the project's progress. The stakeholder expresses a concern to the project manager about whether or not the scope is moving in the right direction.

What should the project manager do?

Options:

A.

Determine alternative solutions to provide improved stakeholder visibility and engagement.

B.

Invite the stakeholder to the demo session and request their feedback about which direction to follow.

C.

Prioritize all of the requirements that are critical to the stakeholder in the next planning session.

D.

Review the scope with the stakeholder, request their feedback, and create an action plan.

Buy Now
Question # 157

A virtual project team has members located on four continents. The project director is concerned about the declining motivational levels of team members and feelings of noninclusion by other team members. The project director has tasked the project manager with finding a solution.

What should the project manager do?

Options:

A.

Develop a plan for individual team members' growth and organize more team-building events.

B.

Recommend that the project director appoint project managers for each continent.

C.

Set up ground rules for team engagement, taking into consideration different cultures.

D.

Take differences in time zones into consideration when scheduling team meetings.

Buy Now
Question # 158

A project manager is trying to define a project time line despite having incomplete and ambiguous information on requirements and regulations. What should the project

manager do to finish planning?

Options:

A.

Review project documents to identify and eliminate uncertainties and inconsistencies.

B.

Execute a root cause analysis to discover the underlying factors that might lead to risks and issues.

C.

Perform an assumption and constraint analysis to provide more opportunities and remove limiting factors.

D.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

Buy Now
Question # 159

A project manager has developed a communications management plan. A junior team member asks why they are duplicating efforts by producing different versions of the same newsletter.

How should the project manager respond?

Options:

A.

Explain that each stakeholder expects a different customized newsletter, ensuring it complies to all of their requirements.

B.

Explain that to prepare for all situations and as part of risk mitigation, many different newsletters are created just in case they are needed.

C.

Explain that customized newsletters are part of the organizational culture and that following this step-by-step process is of utmost importance.

D.

Explain that each individual newsletter is based on specific categories of communication for the intended audience.

Buy Now
Question # 160

The project team is conducting iteration planning and having difficulty evaluating a new technology that will be used in this iteration. What should the project lead do?

Options:

A.

Hire an external subject matter expert (SME) to help with design and implementation.

B.

Coach the team to determine a path forward to achieve an efficient solution.

C.

Provide technical guidance on complexity assessment.

D.

Guide the team with estimating the time required.

Buy Now
Question # 161

A scrum master is receiving conflicting status updates for the same task. How should an accurate status be obtained from the team?

Options:

A.

Encourage team members to work together.

B.

Establish a clear definition of done (DoD) for each task.

C.

Assign one person to be responsible for the task.

D.

Review the deliverable carefully and determine the right status.

Buy Now
Question # 162

A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.

Which three actions should the project manager take? (Choose 3)

Options:

A.

Develop the project management plan based on the requirements requested by the customer.

B.

Develop the application as requested by the customer, based on the approved project requirements.

C.

Plan a minimum viable product (MVP) to get early feedback from the customer.

D.

Facilitate a focus group to assess the functionality before development.

E.

Use an agile approach to deliver the product based on sprints.

Buy Now
Question # 163

A project manager was just assigned to an ongoing project. According to the project's status, all the increments produced passed the acceptance criteria. During the last meeting with the project sponsor, the prototype is far from the sponsor's original expectations.

What should the project manager do first?

Options:

A.

Cancel the ongoing project and start a new one.

B.

Invite the sponsor to the retrospective meeting so they can clarify expectations.

C.

Add additional sprints to modify the deliverables with the new information.

D.

Complete the project and start a new one for the updated scope.

Buy Now
Question # 164

A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.

What should the project manager ask the team to do?

Options:

A.

Perform collaborative work that is coordinated by the project manager.

B.

Rely on the expert judgment of the product owner.

C.

Use a market-based strategy.

D.

Engage the project sponsor.

Buy Now
Question # 165

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?

Options:

A.

Work to understand the key stakeholder's concerns and provide feedback in regular project status reports

B.

Arrange an ad hoc meeting to address the key stakeholder's concerns with team members

C.

Reinforce with the key stakeholder that the project is performing on schedule\

D.

Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress

Buy Now
Question # 166

During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.

How should the project manager properly address this situation?

Options:

A.

Align the project goals with the team member.

B.

Reassign the team member to another project.

C.

Nominate the team member to receive agile training.

D.

Allocate another resource to support the team member.

Buy Now
Question # 167

A project leader is preparing to facilitate a sprint retrospective. The sales manager sends the project leader an email asking how a feature planned for the next shipment is being implemented.

What should the project leader do next?

Options:

A.

Organize a meeting between the product owner and the sales manager.

B.

Invite the sales manager to the next sprint review.

C.

Organize a demo for the sales manager with the development team.

D.

Invite the sales manager to the sprint retrospective.

Buy Now
Question # 168

A large and complex project is comprised of multiple regions. The estimate to complete (ETC) work is assumed to be performed at the same cumulative cost performance index (CPI) as that incurred by the project to date. As of now, the earned value (EV) is 145 person/day, the planned value (PV) is 145 person/day, the actual cost (AC) is 170 person/day, and budget at completion (BAC) is 285 person/day.

What is the estimate at completion (EAC)?

Options:

A.

334 person/day

B.

285 person/day

C.

310 person/day

D.

315 person/day

Buy Now
Question # 169

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

Options:

A.

Ask the stakeholders about the priority of this change

B.

Ask the product owner to review the product backlog

C.

Ask the team members to analyze the impact of this change

D.

Ask the sponsor to approve the change request

E.

Ask the team members to include the change in the next iteration

Buy Now
Question # 170

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?

Options:

A.

Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace

B.

Review the velocity of the team over the last several sprnts and adjust the plan accordingly

C.

Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan

D.

Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap

Buy Now
Question # 171

During the third iteration, the team encounters a major delay that has not had significant improvements over the last few weeks What should the project manager do?

Options:

A.

Retrospect frequently and suggest improvements.

B.

Incorporate a predictive approach for this element.

C.

Implement mitigation strategies for this element

D.

Request additional team members to help with improvements

Buy Now
Question # 172

A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.

What should the project lead do?

Options:

A.

Accept the client's observations and pay the penalties as per the project contract details.

B.

Investigate the client's project reports and proceed to negotiate the levying of any penalties.

C.

Inform the project director of the change and complete the project so as to not incur any penalties.

D.

Request for the recall of the project director to investigate the situation and negotiate potential penalties.

Buy Now
Question # 173

A team member increased the estimated completion time for their activities on the critical path. This action, however, has caused friction among the team members. The project manager reviewed the key performance indicators (KPIs) that show the issue.

What should the project manager do first?

Options:

A.

Conduct a root cause analysis (RCA) and plan the correct actions to ensure completion of the tasks on time.

B.

Allocate another resource to help the team member to complete the tasks and meet the estimated activity time.

C.

Train the team member in the methodology to get the sufficient knowledge to meet the estimated activity time.

D.

Apply crashing to the strategic tasks to recover any time that was lost to bring the project on track.

Buy Now
Question # 174

The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?

Options:

A.

Assign a project team member to document exchanged communication for future reference.

B.

Assign the project sponsor as the point of contact for all provider communication.

C.

Ensure that all project stakeholders participate in the scope definition meetings.

D.

Establish a common language of terms with which to communicate with the provider.

Buy Now
Question # 175

A project manager is managing a project that will engage resources from multiple countries in different time zones. What should the project manager do to ensure that team members are effective?

Options:

A.

Schedule meetings every 2 days at the same time with all team members.

B.

Organize a daily meeting for all team members and extend it, if required.

C.

Schedule meetings every 2 days that align with team members' time zones.

D.

Organize a standard meeting time to engage all of the team members.

Buy Now
Question # 176

A transformation project that is composed of agile streams has come to an end.

How should the project manager collect the experience gained during this project?

Options:

A.

Organize a lessons learned session with the team.

B.

Create a document with the information from the last sprint retrospective.

C.

Ask for feedback during the next standup meeting.

D.

Conduct a session with the members of the project steering committee.

Buy Now
Question # 177

During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?

Options:

A.

Revisiting the project management plan to ensure deliverables are on time

B.

Increasing the frequency of project update meetings to keep stakeholders informed

C.

Revisiting the stakeholder engagement plan, focusing on specific overlooked stakeholders

D.

Reviewing the business case and identifying gaps within scope

Buy Now
Question # 178

A sales director is upset that progress has been slow on the delivery of critical features to the customer. After consulting with the team, the project manager learns that a subject matter expert (SME) on the customer side is not cooperative in providing the input needed to complete the definition of ready (DoR).

What should the project manager do to avoid the same problem in future projects?

Options:

A.

Review the responsibility matrix at the customer kick-off meeting.

B.

Rely on internal SMEs for expert input on implementing the user stories.

C.

Include a contractual penalty for delays created by the customer.

D.

Require customer SMEs to attend at least half of the daily meetings.

Buy Now
Question # 179

A strategic project using international funds for a government agency is going through the execution phase. The government transition will take place in 1 month, and authorities will change. There is a risk that the project will be suspended or team members will be removed. The project manager wants to ensure that the project will continue despite these changes.

Which action should the project manager take to address this situation?

Options:

A.

Stop the project until the government transition has taken place.

B.

Ask the sponsor to send a communication to the president-elect team with the progress of the project.

C.

Ask the main stakeholders to document their progress on the project before the transition.

D.

Accept the risk as these changes are part of the organizational culture.

Buy Now
Question # 180

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?

Options:

A.

Check the approved list of requirements to see if there are any missing items.

B.

Work with the stakeholder to improve the requirements' acceptance criteria

C.

Review the requirements traceability matrix with the concerned stakeholder

D.

Discuss with the stakeholder which additional requirements should be added

Buy Now
Question # 181

One of the main deliverables of a project is delayed due to a problem with a key provider. What should the project manager do?

Options:

A.

Create a change request to replace the provider with a more responsible one from the provider list

B.

Schedule a meeting with all relevant stakeholders to determine the best approach to resolve the issue

C.

Discuss with the sponsor and seek guidance to impose the penalty stipulated in the agreement

D.

Schedule a meeting with the provider to review impacts to the project timeline and deliverables

Buy Now
Question # 182

Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

Options:

A.

Ask for advice on how to be a better mentor to these team members.

B.

Set up a team building event to bring synergy back to the project team.

C.

Adjust the project manager's management style to better fit senior team members.

D.

Meet daily with each senior team member to monitor project status

Buy Now
Question # 183

A team is working on implementing a communications system when the client says that they are considering closing the project. The project manager schedules an urgent meeting with the client to understand why the project is at risk Which two tools or techniques can the project manager use to influence the client’s decision to keep the project active? (Choose two)

Options:

A.

Alternatives analysis

B.

Voting

C.

Cost-benefit analysis

D.

Multi-criteria decision making

E.

Autocratic decision making

Buy Now
Question # 184

A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.

What should the project manager do?

Options:

A.

Analyze the communication needs of the stakeholders.

B.

Communicate the project details to the stakeholders.

C.

Communicate progress more frequently to the stakeholders.

D.

Introduce a separate stakeholder engagement meeting.

Buy Now
Question # 185

During a contract renewal meeting, an organization's commercial team and the customer are disagreeing and negotiations are failing. What should the project manager do to reach an agreement that will satisfy all parties?

Options:

A.

Reinforce the initial rules of the negotiations.

B.

Engage a facilitator to support the negotiations.

C.

Concentrate on meeting the customer's requests.

D.

Set clear expectations among the participants.

Buy Now
Question # 186

A project team is working on a critical release and the customer wants this feature to be made available as early as possible. The business owner suggests an enhancement during the product demo.

How should the project manager address this request?

Options:

A.

Determine the additional funding needed and seek the sponsor's guidance.

B.

Support value-based delivery that is aligned with the project objectives.

C.

Follow the project change control process to formalize the change.

D.

Estimate the additional funding needed and seek the client's approval.

Buy Now
Question # 187

An important project to build a new airport was suddenly stopped because of the complaints from residents in the surrounding communities. The residents stated that they were not consulted and that the project would cause ecological and pollution damage.

What should that project manager have done first in order to avoid this situation?

Options:

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

Buy Now
Question # 188

A project manager who is experienced in predictive and adaptive approaches has been assigned to a new project. Most of the project

stakeholders have only worked on predictive projects, and only a few have been exposed to adaptive projects.

What should the project manager do?

Options:

A.

Propose a hybrid approach and determine which stakeholders will be engaged in each phase of the project.

B.

Follow a predictive approach to reduce the training effort, even though there are incremental deliveries in the project.

C.

Use an adaptive approach, engage the stakeholders who have been exposed to adaptive projects, and train those who have not.

D.

Understand the scope complexity and project magnitude prior to determining which approach to use.

Buy Now
Question # 189

A project is starting its first iteration out of six. During one of the daily meetings, the project manager realized that one of the team members does not have experience working in agile environments.

What should the project manager do?

Options:

A.

Give the team member some time to learn agile practices.

B.

Assign an agile mentor and follow the training process.

C.

Ask to increase the capacity of the team to finish on time.

D.

Ask the sponsor for additional budget for training.

Buy Now
Question # 190

A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.

What should the project manager do next?

Options:

A.

Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body.

B.

Identify the missing requirements, prioritize the missing compliance work directly into the backlog, and assign the work to the team.

C.

Reschedule the launch of the product until the team can produce a prototype for inspection as required by the compliance team.

D.

Create an MVP that contains the scope for the prototype and that will be prioritized with the compliance team.

Buy Now
Question # 191

A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?

Options:

A.

Add more items to the sprint backlog that will add value.

B.

Complete the sprint and seek a waiver from the regulator.

C.

Complete the sprint, but do not release the deliverable.

D.

Perform a sprint risk assessment and analyze challenges.

Buy Now
Question # 192

An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.

What should the project manager have done first to avoid this situation?

Options:

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

Buy Now
Question # 193

In an organizational upper-level management meeting, the CEO shows interest in a project of which they were not previously aware. After the meeting, what should the project manager do to ensure the CEO's support?

Options:

A.

Update the stakeholder engagement plan to include the CEO.

B.

Meet with the CEO to review the current deliverables for the project.

C.

Identify the CEO's preferred method of communication.

D.

Send the updated project management plan and documents to the CEO.

Buy Now
Question # 194

A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.

Which tool should the project manager use for this purpose?

Options:

A.

Cumulative flow diagram

B.

Earned value (EV)

C.

Burndown chart

D.

Forecast estimation

Buy Now
Question # 195

A department lead requested additional items be included in the project during the execution phase. Their acceptance is mandatory before the project can be closed.

Options:

A.

Find a way to accommodate the requested additions.

B.

Schedule a meeting to gain better understanding.

C.

Politely refuse the request stating the project baselines.

D.

Initiate a change request for the additional scope.

Buy Now
Question # 196

During a progress review meeting, the project sponsor requests a complete revamp of the product roadmap to meet the strategic objectives based on market conditions. This change will result in a completely new product.

What should the project manager do first?

Options:

A.

Put the current project work on hold and revisit the scope based on the impacts.

B.

Perform a root cause analysis to assess which deliverables can be reused by the team.

C.

Discuss with the team and implement the revisions that were requested by the sponsor.

D.

Update the business case and seek sponsor approval on the modified project scope.

Buy Now
Question # 197

A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter

What should the project manager do?

Options:

A.

Modify the baseline of the project for minor impact changes to the project scope

B.

Use a focus group and brainstorming sessions to gather more details about the project scope

C.

Register the changes in the configuration management plan and send it to the change control board (CCB).

D.

Explain to the sponsor that these requests could endanger the schedule and cost of the project

Buy Now
Question # 198

During project execution, a project manager is leading the team to work on the project schedule. During a meeting, the team has difficulty understanding the complexity of a task and is unable to provide an estimate for the required resources.

What should the project manager do first to resolve this issue?

Options:

A.

Register the issue as a risk in the risk register.

B.

Report to the sponsor that there is a new challenge in the project.

C.

Engage an external expert to provide the estimation.

D.

Refer to the organization's lessons learned from past projects.

Buy Now
Question # 199

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.

What should the project manager do next?

Options:

A.

Escalate the obstacle to a servant leader for resolution.

B.

Make changes to reprioritize the backlog because of the obstacle.

C.

Reject the obstacle and present the partial solution to the customer.

D.

Focus on generating business value despite the obstacle.

Buy Now
Question # 200

A key project stakeholder recently joined the project and is questioning some of the previously made decisions. This starts to impact project execution.

What should the project manager do?

Options:

A.

Reach out to the stakeholder via phone to explain that all decisions have been agreed upon with their predecessor.

B.

Provide the stakeholder with a link to a file-sharing site where the supporting documents for decisions are filed.

C.

Schedule a meeting with the stakeholder to provide an overview of the project, including the agreed-upon decisions.

D.

Update the risk register with a new risk of potential project changes as a result of stakeholder misalignment.

Buy Now
Question # 201

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?

Options:

A.

Issue log

B.

Project management plan

C.

Risk management plan

D.

Risk register

Buy Now
Question # 202

A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.

What should the project manager do?

Options:

A.

Give some advice to the team member to reduce their stress and anxiety.

B.

Review team participation in the next retrospective meeting with all team members.

C.

Reach out to the team member to discuss and address their concerns as soon as possible.

D.

Evaluate upcoming project deadlines and reorganize team member assignments.

Buy Now
Question # 203

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

Options:

A.

Develop requirements and designs to support a faster product release.

B.

Emphasize the adoption of a predictive approach to minimize ambiguity.

C.

Recommend an agile approach so the project can be delivered iteratively.

D.

Outsource development of the product to a third party with more experience.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (PMBOK 7th Version)
Last Update: Apr 6, 2026
Questions: 2191
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599