Weekend Special - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: certbig75

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 54

A logistics project is anticipating significant delays in the next few months. The project manager makes a list of the causes of the delays before thinking about how to minimize them.

How should the project manager prioritize which delays to take action on? (Select each box from the Items list and drag and drop it into either the Risk Register or Issue Log box.)

Options:

Buy Now
Question # 55

Akey stakeholder has been mostly silent until now. To optimize resources, the stakeholder wants to move one team member to another project but the project

manager does not agree.

What should the project manager do?

Options:

A.

Schedule a meeting to review the backlog assignments with the team.

B.

Suggest the stakeholder observe project activities first, then decide.

C.

Explain to the stakeholder that resource planning was already approved.

D.

Track the actual usage of resources and compare with estimated usage.

Buy Now
Question # 56

A project team had been developing their deliverables on a 2-week sprint. The deliverables were tested and proven to be functional. However, during the sprint

review, they were rejected because they failed to meet the end-user requirements.

What actions should the project manager have done?

Options:

A.

Rotated product owner role among the team to have brought in fresh perspectives during sprint planning.

B.

Included the project sponsor ' s requirements in the user stories during the sprint planning.

C.

Refined user personas with stakeholder input and ensured the team had used them to interpret the stories.

D.

Conducted additional tests and increased the definition of done criteria to have included stakeholder approval.

Buy Now
Question # 57

A project manager is leading a global project involving third-party contractors, internal stakeholders, and regulators. During a project board meeting, stakeholders are

informed of a regional compliance issue that could delay a critical milestone. One stakeholder demands immediate resolution, while another stakeholder thinks it is

not a priority.

What should the project manager do?

Options:

A.

Use the communications management plan to develop a message to stakeholders explaining the situation.

B.

Attempt to resolve the conflict within the project team to avoid unnecessary escalation.

C.

Escalate to the sponsor as it represents a serious compliance issue with implications for milestones.

D.

Escalate in accordance with the agreed escalation process to refer the issue to the appropriate deciding authority.

Buy Now
Question # 58

A project creating a new search engine has been ongeing for several years. Some original features are no longer relevant and will be replaced, due to advancements

with artificial intelligence (Al). A team member has raised concern that one backlog item falls in that category.

What should the project manager do?

Options:

A.

Use several Al tools to find an appropriate solution and implement it.

B.

Suggest the project team align and agree on Al items that are still relevant.

C.

Raise the concern with the product owner to determine if the item is still relevant.

D.

Ask the project sponsor to decide if the concern is valid and if it should be removed.

Buy Now
Question # 59

A project team is working across different time zones and all team members are unable to attend the daily coordination meetings at the same time. The tasks are split

across teams working independently in different regions; however, there are task dependencies between the two teams.

What should the team lead do?

Options:

A.

Ensure all team members participate in the meetings regardless of time zone challenges.

B.

Ensure each team creates and accesses relevant project artifacts to manage dependent tasks.

C.

Check if additional meetings are required with a time suitable for both teams.

D.

Assign the dependent tasks to team members in the same time zone to avoid issues.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (PMP) July 2026 Update
Last Update: Oct 3, 2026
Questions: 187
PMP pdf

PMP PDF

$99.75  $399
PMP Engine

PMP Testing Engine

$112.25  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$149.75  $599