Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 254

A project is impacting several business units with different expectations and priorities. The project manager leading this project is meeting every month with each of these groups individually. During these meetings, each group has expressed dissatisfaction with the project and uses every opportunity to replace other groups' priorities with their own.

What should the project manager do to address these challenges?

Options:

A.

Establish consensus on project priorities by meeting with all the groups together.

B.

Develop a project schedule that accommodates all requirements from all groups.

C.

Escalate the priorities of all the groups to the project sponsor and ask them to facilitate the process.

D.

Meet with each group separately to avoid confrontation and send meeting notes at the end of each meeting.

Buy Now
Question # 255

One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization

How should the project manager acknowledge this team member’s commitment?

Options:

A.

Send this person to a meeting to negotiate the scope with the client

B.

Appreciate this team member’s performance throughout the project life cycle

C.

Promote this team member to a coaching role after this project is completed

D.

Document it in the team member’s end of year performance review

Buy Now
Question # 256

The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?

Options:

A.

Seek expert legal advice on the interpretation of the clauses in the contract

B.

Hold a meeting with the project team project sponsor and the client to agree to the further work required to close the project and add to lessons learned

C.

Close the project and hand over the deliverables to the client

D.

Hold a lessons learned workshop with the project team and project sponsor to avoid contractual compliance issues arising in future projects

Buy Now
Question # 257

An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply

Which two actions should the project manager take? (Choose two)

Options:

A.

Ask the team members to analyze the impact of including this regulation

B.

Ask the stakeholders about the priority of this regulation

C.

Ask the product owner to include the requirements in the product backlog

D.

Ask the security department for details about regulations

E.

Ask the team members to include the requirements in the next iteration

Buy Now
Question # 258

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

Options:

A.

Recruit the best resources within the organization to be part of the virtual team

B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls

C.

Identify the types and quantities of resources required for each work package or activity

D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress

E.

Verify if team members are on more than one team and cannot devote enough time to this team

Buy Now
Question # 259

A project manager is implementing a new software system Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes

What should the project manager have done at the start of the project to prevent this resistance?

Options:

A.

Created a communications management plan that outlined the method of communicating to stakeholders.

B.

Ensured that the company culture encourages changes before accepting the project

C.

Encouraged leadership to discuss the change with departments that are typically resistant to change

D.

Involved stakeholders from all levels of the company so everyone understands the change

Buy Now
Question # 260

During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible

What approach should be used in this situation?

Options:

A.

The team facilitator gets support from external team members.

B.

The team members bring in a specialist to help them

C.

The product owner moves it to the product backlog.

D.

The cross-functional team member work together to complete the activity

Buy Now
Question # 261

A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?

Options:

A.

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables

B.

Request more funding from the project sponsor to hire additional skilled resourcesand to incorporate additional quality in the project delivery approach and outcome

C.

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions

D.

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives

Buy Now
Question # 262

During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.

What two actions should the project manager take to prevent the team from being unqualified? (Choose two)

Options:

A.

Exclude the activities from the roadmap

B.

Encourage working in pairs and knowledge sharing

C.

Teach the entire team the new skill.

D.

Facilitate a training event with an external trainer

E.

Increase the time estimates on the activities that require such abilities

Buy Now
Question # 263

The product team is progressing with a prototyping approach to deliver a multiyear business initiative A few user stones are taking longer to be delivered.

What should the project manager do?

Options:

A.

Determine the risks and identify a resolution during the retrospective meeting

B.

Inform stakeholders about the delay during project updates

C.

Determine cross-dependencies and plan a spike in the next spont

D.

Discover the gaps in the communications management plan and address them accordingly

Buy Now
Question # 264

A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.

What should the project manager do next?

Options:

A.

Escalate the issue to the purchasing department for review.

B.

Evaluate the procurement contract to determine the agreed-upon specifications.

C.

Hire a company in country B to perform a quality check before shipment.

D.

Add an additional task to cut the received part according to the specifications,

Buy Now
Question # 265

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control

How should the project manager report the project status to key stakeholders?

Options:

A.

Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results

B.

Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget.

C.

Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control.

D.

Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away

Buy Now
Question # 266

A company has a lot of experience with predictive projects The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.

What should the project manager do?

Options:

A.

Prepare and submit a status report to the steering committee to update performance monitoring

B.

Determine the data to be monitored during the project as well as the expected performance and targets.

C.

Update the communications management plan to consider performance review meetings with the project stakeholders

D.

Conduct reviews with stakeholders to discuss the potential benefits the approach may have to the project

Buy Now
Question # 267

During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?

Options:

A.

Communicate the concerns to the project management office (PMO) during the weekly project reports

B.

Call for a team meeting to decide if the changes should be included

C.

Initiate the change request to modify the scope and adjust the timelines

D.

Conduct an impact analysis and present the results to the steering committee for approval

Buy Now
Question # 268

A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.

What should the project manager do first?

Options:

A.

Start executing the project since leadership is responsible for the business strategy.

B.

Meet with the project sponsor to better understand the strategic benefits of the project.

C.

Propose an updated business case and project charter that are more aligned with the business strategy.

D.

Conduct qualitative and quantitative risk analysis and record the results in the risk register.

Buy Now
Question # 269

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?

Options:

A.

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve

B.

Develop the quality management plan, as quality is as equally important as cost and schedule management.

C.

Get confirmation from management that the team member has enough experienceto build software without quality control

D.

Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project

Buy Now
Question # 270

A project team is currently dispersed across multiple countries and time zones. Recent team feedback shows engagement levels are sub-optimal, and information flows are irregular and one-sided. There are also company travel restrictions in place, preventing physical colocation.

What improvements should the project manager implement to improve engagement?

Options:

A.

Upgrade each project team member's internet connection to allow virtual video conferencing.

B.

Confirm with the team which approach works best for exchanging information.

C.

Schedule a regular cadence and duration for agile ceremonies and sprint planning.

D.

Submit a change request to the project sponsor for a travel exemption for the team to meet on-site.

Buy Now
Question # 271

A company in the manufacturing industry has started a new initiative to integrate project management and improve product innovation. What first step should the project manager take to increase transparency among the stakeholders?

Options:

A.

Define a plan on how communication throughout the project will be handled among the stakeholders.

B.

Set up a project dashboard to show day-to-day project status across the company.

C.

Invite key stakeholders to retrospective and review sessions to receive feedback as often as possible.

D.

Invite upper management to process workshops where current project statuses will be discussed.

Buy Now
Question # 272

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting The ongoing conflict is preventing tasks and deliverables from being completed The project manager contemplates changing their leadership style

What should the project manager do?

Options:

A.

Review the set of responsibilities with the team member

B.

Avoid the team member to prevent further conflicts

C.

Escalate the situation to the project sponsor

D.

Review the personnel skill documents

Buy Now
Question # 273

Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.

How should the project manager address this situation?

Options:

A.

Send evidence to the new stakeholder that the project's status was sent according to the schedule

B.

Suggest that the new stakeholder review the project status before the next board meeting

C.

Share the communications management plan with the new stakeholder

D.

Discuss project requirements with the new stakeholder, and update the communications management plan.

Buy Now
Question # 274

A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?

Options:

A.

Review the milestone list to determine which tasks can be fast-tracked

B.

Review the risk management plan to identify the response strategy

C.

Escalate the issue to the sponsor and debrief them about the situation

D.

Organize a team meeting to discuss the next course of action

Buy Now
Question # 275

An agile project team is looking to develop quality standards for a project How should the project manager coach the team?

Options:

A.

Determine the tools and techniques suitable for the project and ensure that testing is done early and continuously.

B.

Inform the team that user acceptance testing is required to ensure that the product owner accepts the solution

C.

Insist that test-driven development is implemented along with the automated testing

D.

Ensure that the definition of done (DoD) is provided when the product owner agrees that all acceptance criteria have been met for the user story

Buy Now
Question # 276

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

Options:

A.

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

B.

Encourage and assign the team to perform demos of their products or software with the customers

C.

Give the team autonomy to make their own decisions on how to perform the tasks.

D.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

Buy Now
Question # 277

Throughout an entire project, the project manager took notes at every meeting with

team members. These notes provided useful insights from key stakeholders, which later

resulted in increased value to the project. The project manager thought it would be helpful to

keep these notes as a future reference for other project managers within the organization.

Where should the notes be located?

Options:

A.

Lessons learned

B.

Organizational process assets (OPAs)

C.

Enterprise environmental factors (EEFs)

D.

Project management plan

Buy Now
Question # 278

A project manager is assigned to a project in a company that is transitioning to agile Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project However the project sponsor needs a quick win to ensure the continuation of the project.

What approach should the project manager use?

Options:

A.

An agile approach as this would provide working functionality earlier

B.

A predictive approach as this would please the senior stakeholders

C.

A hybrid project as this will mitigate stakeholders' concerns.

D.

A predictive approach as this will show benefits for all stakeholders

Buy Now
Question # 279

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)

Options:

A.

Require the team to have daily mandatory meetings with the project management office (PMO).

B.

Recommend the use of formal written documentation in all project communications.

C.

Review the communications strategy with the team regularly with a view for continuous improvement.

D.

Send out a survey to review the preferred method, time frequency for communications.

E.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

Buy Now
Question # 280

A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)

needs visibility of the regulatory constraints while maintaining a degree of flexibility.

Which tool can the project manager use?

Options:

A.

Use a burndown chart to provide transparency.

B.

Use a kanban board to increase accountability.

C.

Use a product backlog to manage changes.

D.

Use a burnup chart to provide transparency.

Buy Now
Question # 281

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

Options:

A.

Suggest that the team member ignore the disruptive team member and focus only on the work.

B.

Encourage both team members to meet as soon as possible and resolve the problem

C.

Monitor the situation for a few weeks to determine if the disruptive team member's attitude changes.

D.

Report the disruptive team member to the human resource (HR) department.

Buy Now
Question # 282

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Options:

A.

Review the requirements of the report with the team member to redefine its purpose.

B.

Escalate to the team member's functional manager that the report was not submitted as requested.

C.

Instruct the team member to provide the report and document this in the performance review.

D.

Reassign the report to another team member to prepare and submit it as requested.

Buy Now
Question # 283

A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.

How should the project manager ensure the acceptance criteria are ret?

Options:

A.

Perform tests and routinely track results as per the quality management plan.

B.

Make sure the stakeholders are aware of the acceptance criteria.

C.

Negotiate to obtain approval if most of the tests have passed.

D.

Modify the acceptance criteria before the official delivery.

Buy Now
Question # 284

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

Options:

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

Buy Now
Question # 285

A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.

What should the project manager do first?

Options:

A.

Work with the stakeholders to determine which measurable benefits can be tracked and assign an accountable person to monitor and report them

B.

Create a report based on the work breakdown structure (WBS) and update it on a regular basis.

C.

Use the same benefits tracking process from the last predictive project and add this to the monthly status report

D.

Research which templates of reports were used the most for this framework and incorporate them into the project

Buy Now
Question # 286

A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease. What should the project manager do to address this issue?

Options:

A.

Force the team members to work from one location.

B.

Develop protocols for resolving conflicts between team members

C.

Obtain special expertise to advise the team members

D.

Set up face-to-face meetings with project team members

Buy Now
Question # 287

The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements

How should the project manager address this situation?

Options:

A.

Ask the team to include the compliance requirement in the current sprint and deliver it.

B.

Add the new compliance requirement to the backlog as the technical team does not have any capacity.

C.

Include the compliance lead in the stakeholders list and wait for the next status meeting

D.

Collaborate with the compliance team member to review and prioritize the requirement’s delivery

Buy Now
Question # 288

A project has recently Kicked off. The project manager observes that thete are different expectations among the project team members. These growing misunderstandings are affecting team productivity.

Which document should the project managefve?

Options:

A.

Project charter

B.

Stakeholder register

C.

Team charter

D.

Project organization charts

Buy Now
Question # 289

The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.

What should the project manager do?

Options:

A.

Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future

B.

Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing

C.

Assume the responsibility for product releases making the final call on when something is ready for customer launch

D.

Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision

Buy Now
Question # 290

A project manager is leading the first agile project for the organization. During the

kick-off meeting, the project manager notices that the team does not have the same

understanding about agile approaches. The project manager is concerned about the impact of that confusion.

What should the project manager do to address this situation?

Options:

A.

Evaluate the possibility of managing this project using a predictive approach.

B.

Submit a change request for a new team that has agile experience.

C.

Mentor the team to explain agile principles and create a shared understanding.

D.

Hire a functional manager who is familiar with agile methodologies.

Buy Now
Question # 291

for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications.

What should the project manager do next?

Options:

A.

Accept the proposed replacement in order to keep procurement activities on track

B.

Insist on using the component per the project specifications and air freight the equipment to mitigate the delay

C.

Instruct the vendor to use the part that is compliant with the project specifications and update the schedule

D.

Consult with a subject matter expert (SME) to see if the proposed change isacceptable

Buy Now
Question # 292

A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.

What should the project manager do?

Options:

A.

Explain to the project sponsor that the project manager is only accountable for managing the project scope budget quality and schedule

B.

Document who will be tracking benefits realization what will be tracked and when it will be tracked in the project closure report

C.

Explain to the project sponsor that they are accountable for tracking benefits realization after project completion

D.

Discuss extending the project manager's allocation to the project until all benefits are realized with the project management office (PMO)

Buy Now
Question # 293

There is a problem with a project because some features are not in compliance with

regulations. Some stakeholders do not believe compliance is a priority, while others disagree.

What should the project manager do?

Options:

A.

Review the stakeholder engagement assessment matrix to determine next steps.

B.

Set up some time with the stakeholders to explain the importance of compliance.

C.

Meet with the sponsor to discuss how to handle the stakeholders' differing opinions.

D.

Send out documentation to align stakeholder expectations and project objectives.

Buy Now
Question # 294

A company has decided to investigate the feasibility of a new product. The project manager is in charge of validating the customer requirements. What should the project manager do to gam customer feedback?

Options:

A.

Have the product owner create product documentation

B.

Have the team create a minimum viable product (MVP).

C.

Have the marketing department create a survey

D.

Have the team create a prototype with all features

Buy Now
Question # 295

Due to a recent company merger, a project manager from company B has been

assigned to a team that is comprised of team members from company A. At the start of the

project, conflicts arise due to a lack of clarity on processes and the project manager's

relationship with company B.

What should the project manager do to resolve this conflict?

Options:

A.

Avoid the conflict as the customer feels comfortable with using processes fromcompany A.

B.

Review the historical information and make the decision based on the return oninvestment (ROI).

C.

Ask the team to use company B's processes since they are more familiar with theseprocesses.

D.

Work with the team to analyze which processes are suitable to use and define them inthe ground rules.

Buy Now
Question # 296

A protect manager is managing a project that will handle sensitive data for millions of users The sponsor mentioned that, lo their knowledge, the project does not seem to have any compliance requirements in their country.

What should the project manager do in this situation?

Options:

A.

Request expert advice from the compliance leader to confirm if there are any compliance requirements for the project.

B.

Check with The national compliance agency to determine if the project has any compliance requirements in this country

C.

Trust in the expertise of the sponsor and believe that there are no compliance requirements for this project.

D.

Conduct independent research regarding the data protection policy of the country for legal and regulatory compliance.

Buy Now
Question # 297

A project manager is working on a highly complex project. During the execution of

the project, the local government changed certain environmental regulations, which could

potentially delay the project.

What immediate action should the project manager take?

Options:

A.

Update the issue log.

B.

Update the project baseline.

C.

Update the risk management plan.

D.

Update the change request log.

Buy Now
Question # 298

During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?

Options:

A.

Design a set of metrics including velocity, which is a good measure of value delivered.

B.

Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP)

C.

Promote a productive environment where everybody can work without interruptions from the rest of the team members

D.

Create a reward system recognizing group contributions to get people motivated and improve performance

Buy Now
Question # 299

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?

Options:

A.

Stakeholder analysis

B.

Resource needs analysis

C.

Accommodations assessment

D.

Team member assessment

Buy Now
Question # 300

A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.

What should the project manager do to avoid these challenges?

Options:

A.

Increase the project budget by 10% for team-related activities and awards.

B.

Plan to implement team-building strategies throughout the project.

C.

Ask the functional manager to motivate the team outside of the project.

D.

Colocate the team to encourage more motivational team activities.

Buy Now
Question # 301

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?

Options:

A.

Encourage and motivate the team with project incentives

B.

Subdivide the team to handle different aspects of the project

C.

Support the team to find and execute the minimum viable product (MVP)

D.

Organize project execution to satisfy the project sponsor s request

Buy Now
Question # 302

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

Options:

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics

B.

Stop the project and kick off another project to apply alternative wires for the machine

C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider

D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine

Buy Now
Question # 303

A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.

How should the project manager address this?

Options:

A.

Consult the previous project manager to discuss how they managed these questions.

B.

Ensure all engineers are aware that questions should only be submitted in their weekly reports.

C.

Email the company vision to the engineers and tell them they need to meet deadlines

D.

Reinforce to all engineers the company vision of a safety-first approach to project activities.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (PMBOK 7th Version)
Last Update: Apr 6, 2026
Questions: 2191
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599