Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMP Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 254

A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in

one of the project teams.

What should the project manager do?

Options:

A.

Apply a root-cause analysis on the data breaches.

B.

Ensure that all team members complete the training.

C.

Redesign the training courseware to make it interesting.

D.

Retrain the team members responsible for the breaches.

Buy Now
Question # 255

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?

Options:

A.

Appoint a dedicated product manager for the duration of the release

B.

Have the customer approve the product increment features.

C.

Ensure every user story has acceptance criteria.

D.

Track business outcomes for planned user stories.

Buy Now
Question # 256

A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?

Options:

A.

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline

B.

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change

C.

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline

D.

Absorb the additional cost for the additional resources internally so that the project completes within the timeline

Buy Now
Question # 257

A project manager Is working on a project using a hybrid approach. The project Is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company which was approved by their functional manager

What should the project manager do first in this situation'?

Options:

A.

Ask the functional manager why a decision was made without consulting them

B.

Use soft skills to influence the team member to slay until the project is completed

C.

Ask the functional manager for an immediate replacement for the team member.

D.

Review the risk management plan and mitigation plan to understand the impact of this issue

Buy Now
Question # 258

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

Options:

A.

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken,

B.

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

D.

Encourage the whole team to be empowered and accountable for the decisions made according to their roles,

Buy Now
Question # 259

The project team is planning a schedule with limited information. The team |s having

issues identifying the detailed tasks and estimating task durations.

Which three techniques should the project manager use? (Choose three)

Options:

A.

Rolling wave planning and an adaptive approach

B.

Relative estimation to determine the task or deliverable sizes

C.

Iterations and reviews to continuously keep adapting the plan

D.

Bottom-up estimating based on a work breakdown structure (WBS)

E.

Gantt chart that includes milestones and deadlines https://www.projectmanager.com/blog/project-management/planning-techniques-for-projects

Buy Now
Question # 260

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add n as an issue m the issue log

C.

Escalate the issue to the functional manager

D.

Direct the sales team to speak with accounting to resolve the issue

Buy Now
Question # 261

A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.

What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?

Options:

A.

Schedule a training course for the new team member to fill in their gaps in experience.

B.

Log this as an issue in the project issue log and speak with the resource manager.

C.

Provide weekly feedback to all project team members, including the new member.

D.

Ensure that coaching meetings are in place for this team member within the project timeline.

Buy Now
Question # 262

Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.

What is the protect manager's first step in addressing the problem?

Options:

A.

Communicate the issue to the change control board (CCB) and relevant stakeholders identified in the stakeholder engagement plan

B.

Create a problem-solving team from quality assurance subject matter experts (SMEs) experienced in this type of analysis

C.

Form a brainstorming team from project team members selected for their relevant technical analytical and management knowledge

D.

Form a brainstorming team with stakeholders from all of the functional departments involved in the project

Buy Now
Question # 263

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

Options:

Buy Now
Question # 264

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

Options:

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

Buy Now
Question # 265

A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is

on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.

What should the project manager do?

Options:

A.

Contact the design team manager and ask to reconsider the priority list based on the latest situation,

B.

Meet with the designer to share the current status and develop a solution to complete the task.

C.

Meet with the design team manager to inform them of the current status and request an additional designer.

D.

Ask the software engineer to move forward without completing the important feature.

Buy Now
Question # 266

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

Options:

A.

Review the deliverable carefully and determine the right status

B.

Assign one person to be responsible for the task

C.

Establish a clear definition of done (DoD) for each task

D.

Encourage team members to work together

Buy Now
Question # 267

A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.

What should the project manager do?

Options:

A.

Process a bank loan to pay the payroll of the third-party supplier.

B.

Reassign resources from other projects to pay the third-party supplier.

C.

Explain the third-party supplier situation to the client and request payment.

D.

Inform the client that the project must be delayed until payment is received.

Buy Now
Question # 268

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?

Options:

A.

Coercion

B.

Conflict resolution

C.

Emotional intelligence

D.

Negotiating

Buy Now
Question # 269

we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.

What should the project manager do?

Options:

A.

Discuss the issue with the team to resolve the disagreement.

B.

Ensure that there is consensus among the project stakeholders.

C.

Discuss the issue during the next sprint planning meeting.

D.

Support the outcome of the architects’ agreement.

Buy Now
Question # 270

In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.

What should the project manager do?

Options:

A.

Submit a change request to leverage previous experience and manage the project using a predictive approach,

B.

Schedule a daily project definition meeting with the team to define the project scope before starting the execution.

C.

Start executing the project as the scope will be defined and redefined throughout the project.

D.

Obtain partial approval from the product owner to baseline the project scope plan before starting the execution.

Buy Now
Question # 271

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do'?

Options:

A.

Escalate the issue to the sponsor and ask for stakeholder engagement

B.

Review the project business case and update it periodically

C.

Plan for strategic program management

D.

Implement a communications management plan

Buy Now
Question # 272

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

Options:

A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget

B.

Engaged with the project sponsor to ensure support for the project manager's decision

C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped

D.

Convinced the functional manager to stop the activities that will run beyond the budget

Buy Now
Question # 273

A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?

Options:

A.

Ask the provider to seek options to solve the issue

B.

Add the issue to the issue log and report it at the next review meeting

C.

Review the current plan and consolidate if necessary

D.

Schedule a meeting with the provider to collaborate on the options

Buy Now
Question # 274

A project manager and project team have brought a project back on track after mapping and removing impediments During the current sprint the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously However, the tasks are not having the same result with the impediment

What should the project manager do?

Options:

A.

Escalate the issue with an impediment to the project sponsor

B.

Use the contingency budget to implement schedule compression

C.

Implement the mitigation plans listed in the organizational process assets (OPAs)

D.

Reassess the issue as part of monitoring and controlling

Buy Now
Question # 275

A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager's performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.

What should the project manager do first?

Options:

A.

Accept the feature.

B.

Determine if the feature is within the scope.

C.

Submit a change request! for the feature.

D.

Reject the feature.

Buy Now
Question # 276

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

Options:

A.

Provide a project management template for the project manager to follow as a guide.

B.

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.

Work with the project manager to develop a new approach that will bring benefits to the project.

D.

Establish a project management methodology that requires the customer to provide daily updates to the team.

Buy Now
Question # 277

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

Options:

A.

Reconcile the key stakeholder to the team member's recommendation.

B.

Reconcile the team member to the key stakeholder's recommendation.

C.

Escalate the communication concerns to the project management office (PMO) and

request that they take action

D.

Work with both the team member and the key stakeholder to reach a consensus.

Buy Now
Question # 278

A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution

phase and will affect a few key workers’ licenses, which will become noncompliant.

What should the project manager do?

Options:

A.

Start scheduling the training for key workers now to ensure compliance.

B.

Maintain the current key workers since the project has already started.

C.

Update the project charter to ensure the new legislation is addressed,

D.

Start a recruitment drive for new workers with the licenses required.

Buy Now
Question # 279

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

Options:

A.

The software development has a high uncertainty level, so an agile approach is recommended for the project.

B.

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

C.

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

Buy Now
Question # 280

A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.

The project team will be virtual and will include members from different countries around the world.

What should the project manager do to ensure effective team building occurs?

Options:

A.

Coordinate with team members to define and communicate ways of working, roles and responsibilities, scheduling, time zone, and cultural

observance information.

B.

Explain to the team that since they are all SMEs and know one another, they are expected to immediately collaborate and deliver effectively.

C.

Update the communications management plan and determine an issue resolution process for when furture conflicts arise.

D.

Colocate the team members at the beginning of the project to explain the expectations for team interaction, meeting schedules, and overall

project governance.

Buy Now
Question # 281

A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments.

What should the project manager do?

Options:

A.

Allow the most senior team members to decide the time that works for the team.

B.

Reassess the team's hours collaboratively so that the team is not impeded by the issue.

C.

Discuss the lack of dedication with the team member and their functional manager.

D.

Remove the team member from the project team to be fair to the other members.

Buy Now
Question # 282

A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications

What should the project manager do?

Options:

A.

Schedule a meeting with all stakeholders to understand what went wrong and who should be held responsible

B.

Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue

C.

Meet with the client and discuss the project deadlines

D.

Seek approval for more time for rework and resolve the issue

Buy Now
Question # 283

A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.

What should the project manager have done*?

Options:

A.

Confirmed that the communication was understood and solicited feedback from the team

B.

Sent the roles and responsibilities matrix along with the project management plan

C.

Discussed the roles with the managers to help explain them to their team members

D.

Briefed each team member on their roles before sending the project management plan

Buy Now
Question # 284

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

Options:

A.

Meet with all project stakeholders to identify how to implement the technology.

B.

Identify the disagreement in the risk register and develop a contingency plan.

C.

Update the project charter to align with the desires of the project sponsor.

D.

Negotiate with the project sponsor to develop a mutually beneficial solution.

Buy Now
Question # 285

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?

Options:

A.

Align with the organization's project management office (PMO) to inform and make them aware of the new approach

B.

Explain and communicate the new approach to the project sponsor and key stakeholders

C.

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders

D.

Communicate with other project managers to see how they manage hybrid projects

Buy Now
Question # 286

A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time

What should the project manager do next?

Options:

A.

Record the issue then refocus the team's efforts on delivering the next set of deliverables

B.

Give the team member a formal warning for the negative impact due to failure to delrver and not meet deadlines

C.

Hold a team meeting to discuss team member commitments and communications

D.

Meet with the team member and work on a development plan for them to avoid missed deliverables in the future

Buy Now
Question # 287

One of the project manager's important assignments is to formally revise project compliance as it pertains to user data protection regulations. What should the project manager

do to monitor compliance?

Options:

A.

Assess the risk register.

B.

Conduct project reviews.

C.

Perform retrospectives.

D.

Complete sprint reviews

Buy Now
Question # 288

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

Options:

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Buy Now
Question # 289

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit

Which two rules are appropriate tor the project manager to instill in the team? (Choose two)

Options:

A.

Strive toward continuous improvement

B.

Work together daily as a team

C.

Only share suggestions at the end of the sprint

D.

Follow the sprint planning

E.

Send communications to the entire team

Buy Now
Question # 290

A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules

Which two actions should the project manager take with regard to schedule analysis? (Choose two)

Options:

A.

Review with subject matter experts (SMEs) to ensure they have contributed to the schedule development

B.

Evaluate the master schedule and perform fast tracking and task crashing

C.

Look (or gaps in the different schedules to determine which major risks might evolve over time

D.

Review the project schedules to ensure that all tasks end with milestones

E.

Evaluate the schedules for interdependencies to establish the critical path

Buy Now
Question # 291

A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.

What should the project manager do?

Options:

A.

Meet with the project sponsor to explain that the project cannot be completed as planned

B.

Meet with the technical lead to review the sprint plan

C.

Meet with the product owner to confirm the minimum viable product (MVP) option

D.

Meet with the project team and reprioritize the backlog

Buy Now
Question # 292

An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but

the agile coach and technical writer feel that is an inconvenient time for them.

How does the project lead ensure adherence to agile practices?

Options:

A.

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach,

B.

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team.

C.

Have a discussion with the team on the approach and come to a decision on when the daily standups should be.

D.

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.

Buy Now
Question # 293

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

Options:

Buy Now
Question # 294

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

Options:

A.

Expedite the next phase to reduce slippage

B.

Add more float to the overall project schedule

C.

Request additional contingency from the sponsor.

D.

Organize a root cause analysis (RCA) workshop.

Buy Now
Question # 295

A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented

What should the project manager do?

Options:

A.

Ask the team member to learn the new system as on-the-job training

B.

Issue a change request to extend the project schedule

C.

Escalate the team members performance to the project sponsor

D.

Assign an experienced resource to support the team member

Buy Now
Question # 296

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

Options:

A.

Use compression techniques to break down the scope and assign the scope pieces to

different vendors with a fixed-price contract.

B.

Use the contingency budget for hiring additional vendor resources to mitigate any project

risk.

C.

Engage in a time and materials (T&M) contract and hire a local vendor to support

development.

D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Buy Now
Question # 297

One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority

What should the project manager do to mitigate the risk of not having the materials printed on time?

Options:

A.

Meet with the manager to set a high priority for printing the materials

B.

Create a change request to modify the print requirements

C.

Include a risk response in the resource management plan

D.

Purchase a high-volume printer specifically for this project.

Buy Now
Question # 298

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

Options:

A.

Plan the project based on the available resources and submit a change request upon completion.

B.

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.

Identify the technical requirements and request that management hire external resources,

D.

Document the problem in the issue log and suggest a change request to decrease the scope.

Buy Now
Question # 299

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?

Options:

A.

Shared

B.

Accepted

C.

Enhanced

D.

Exploited

Buy Now
Question # 300

A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board (CCB).

What should the project manager do now?

Options:

A.

Notify the project team about the change request's approval.

B.

Include the new branch of the bridge in the design.

C.

Communicate the decision to the stakeholder who requested the change.

D.

Evaluate the adjustments to the project management plan.

Buy Now
Question # 301

A credit collection company is implementing new software to assist customer service agents when calling clients for payments. The software will benefit the company by freeing up staff to work on other projects. Several business areas want to take advantage of this benefit.

What should the project manager do?

Options:

A.

Request all of the business areas to plan for a portion of the benefit equally and include it in their staffing plans.

B.

Set up a stakeholder session with all teams to agree and document the benefits and establish ownership.

C.

Ask the project sponsor for approval to distribute the project benefits equally to the business areas.

D.

Ask the project sponsor to make a decision on who will own the benefit and document the decision.

Buy Now
Question # 302

A project is continuously overlapping phases. Due to a recent human error, the team, which is made up of senior members, is experiencing distrust issues from other departments and lacking initiative. This is impacting overall performance and putting the project objectives at risk.

What should the project manager do when executing the next sprint?

Options:

A.

Coach those responsible for the error so that the whole team understands they are not responsible for it.

B.

Explain high-level objectives and ask team members to self-organize around their tasks to meet the objectives.

C.

Request offsite team-building activities and deploy incentive plans around their tasks.

D.

Identify the poor performers and ask their functional managers to assign them a mentor.

Buy Now
Question # 303

During a design workshop, the engineers ask the project manager about the safety prerequisites for the new product's operating procedures.

What should the project manager do?

Options:

A.

Provide the team with the enterprise environmental factors (EEFs).

B.

Run a benchmark with similar sites to compare compliance constraints.

C.

Look into lessons learned documentation for similar projects.

D.

Hire a specialized engineer to support the design team.

Buy Now
Exam Code: PMP
Exam Name: Project Management Professional (2025 Version)
Last Update: Aug 22, 2025
Questions: 1988
PMP pdf

PMP PDF

$119.7  $399
PMP Engine

PMP Testing Engine

$134.7  $449
PMP PDF + Engine

PMP PDF + Testing Engine

$179.7  $599