A logistics project is anticipating significant delays in the next few months. The project manager makes a list of the causes of the delays before thinking about how to minimize them.
How should the project manager prioritize which delays to take action on? (Select each box from the Items list and drag and drop it into either the Risk Register or Issue Log box.)

Akey stakeholder has been mostly silent until now. To optimize resources, the stakeholder wants to move one team member to another project but the project
manager does not agree.
What should the project manager do?
A project team had been developing their deliverables on a 2-week sprint. The deliverables were tested and proven to be functional. However, during the sprint
review, they were rejected because they failed to meet the end-user requirements.
What actions should the project manager have done?
A project manager is leading a global project involving third-party contractors, internal stakeholders, and regulators. During a project board meeting, stakeholders are
informed of a regional compliance issue that could delay a critical milestone. One stakeholder demands immediate resolution, while another stakeholder thinks it is
not a priority.
What should the project manager do?
A project creating a new search engine has been ongeing for several years. Some original features are no longer relevant and will be replaced, due to advancements
with artificial intelligence (Al). A team member has raised concern that one backlog item falls in that category.
What should the project manager do?
A project team is working across different time zones and all team members are unable to attend the daily coordination meetings at the same time. The tasks are split
across teams working independently in different regions; however, there are task dependencies between the two teams.
What should the team lead do?