Once a change has been requested what is the next step in the change control process?
Evaluate the change.
Advise the sponsor.
Update the change log.
Update the project plan.
Which type of projects needs to consider environmental constraints?
Construction projects only.
Construction and petrochemical projects only.
All but IT projects.
All projects.