PMI-001 Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 114

Plan Risk Management is the process of defining how to:

Options:

A.

Communicate identified risks to the project stakeholders.

B.

Conduct risk management activities for a project.

C.

Analyze the impact a specific risk may have on the project.

D.

Address unexpected risks that may occur during a project.

Buy Now
Question # 115

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

Options:

A.

start-to-start (SS)

B.

start-to-finish (SF)

C.

finish-to-start (FS)

D.

finish-to-finish (FF)

Buy Now
Question # 116

The integrative nature of project management requires which Process Group to interact with the other Process Groups?

Options:

A.

Planning

B.

Executing

C.

Monitoring and Controlling

D.

Project Management

Buy Now
Question # 117

The process for performing variance analysis may vary, depending on:

Options:

A.

scenario building, technology forecasting, and forecast by analogy.

B.

working relationships among various stakeholders and team members.

C.

application area, the standard used, and the industry,

D.

work to be completed next.

Buy Now
Question # 118

Which of the following is a complete set of indexed contract documentation, including the closed contract?

Options:

A.

Procurement package

B.

Negotiated settlements

C.

Procurement file

D.

Procurement management plan

Buy Now
Question # 119

The product scope description is used to:

Options:

A.

Gain stakeholders' support for the project.

B.

Progressively elaborate the characteristics of the product, service, or result.

C.

Describe the project in great detail.

D.

Define the process and criteria for accepting a completed product, service, or result.

Buy Now
Question # 120

Which of the following correctly explains the term "progressive elaboration'?

Options:

A.

Changing project specifications continuously

B.

Elaborate tracking of the project progress

C.

Elaborate tracking of the project specifications with a change control system

D.

Project specifications becoming more explicit and detailed as the project progresses

Buy Now
Question # 121

Project Stakeholder Management focuses on:

Options:

A.

project staff assignments

B.

project tea m acquisition

C.

managing conflicting interests

D.

communication methods

Buy Now
Question # 122

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

Options:

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Buy Now
Question # 123

Which organizational process assets update is performed during the Close Procurements process?

Options:

A.

Procurement audit

B.

Lessons learned

C.

Performance reporting

D.

Payment requests

Buy Now
Exam Code: PMI-001
Exam Name: Project Management Professional v5
Last Update: Aug 22, 2025
Questions: 918
PMI-001 pdf

PMI-001 PDF

$25.5  $84.99
PMI-001 Engine

PMI-001 Testing Engine

$28.5  $94.99
PMI-001 PDF + Engine

PMI-001 PDF + Testing Engine

$40.5  $134.99