Question # 124

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

Options:

A.

Fixed Price with Economic Price Adjustments Contract (FP-EPA)

B.

Cost-Reimbursable Contract (CR)

C.

Firm-Fixed -Price Contract (FFP)

D.

Fixed-Price-Incentive-Fee Contract (FPIF)

Buy Now
Question # 125

Which action is included in the Control Costs process?

Options:

A.

Identify how the project costs will be planned, structured, and controlled

B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.

Develop an approximation of the monetary resources needed to complete project activities

D.

Monitor cost performance to isolate and understand variances from the approved cost baseline

Buy Now
Question # 126

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

Options:

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

Buy Now
Question # 127

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

Options:

A.

Brainstorming

B.

Strategies for opportunities

C.

Decision tree analysis

D.

Risk data quality assessment

Buy Now
Question # 128

In project management, a temporary project can be:

Options:

A.

Completed without planning

B.

A routine business process

C.

Long in duration

D.

Ongoing to produce goods

Buy Now
Question # 129

Which Process Group and Knowledge Area include the Sequence Activities process?

Options:

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Buy Now
Question # 130

Which type of managers do composite organizations involve?

Options:

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Buy Now
Question # 131

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

Options:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Buy Now
Question # 132

A reward can only be effective if it is:

Options:

A.

Given immediately after the project is completed.

B.

Something that is tangible.

C.

Formally given during project performance appraisals.

D.

Satisfying a need valued by the individual.

Buy Now
Question # 133

Which document includes the project scope, major deliverables, assumptions, and constraints?

Options:

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

Buy Now
Exam Code: PMI-001
Exam Name: Project Management Professional v5
Last Update: Aug 22, 2025
Questions: 918
PMI-001 pdf

PMI-001 PDF

$25.5  $84.99
PMI-001 Engine

PMI-001 Testing Engine

$28.5  $94.99
PMI-001 PDF + Engine

PMI-001 PDF + Testing Engine

$40.5  $134.99