A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?
After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?
A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the
following has the project manager identified?
A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:
Which of the following issues should be addressed FIRST?