What is a description of a leadership activity within a project?
The project management team heeds t document quality antral events, such as testing
According to the guidance for effective quality management, haw should the events be documented?
Thea project manager needs to report to the project board on the status of the project's issues.
Which management product should the project manager review?
Which TWO are objectives of the 'managing a stage boundary" process?
1. To confirm to the project board that there are no products outstanding for the stage
2. To ensure that expectations are managed via accurate reporting to the project manager during a stage
3. To ensure that the project management team is not distracted by delivering additional products during the stage
4. To request the project board to approve work to start on the next stage