Which are purposes of the 'directing a project' process?
1. To enable the project board to be accountable for a project's success by making key decisions
2. To enable the project board to authorize work packages
3. To enable the project board to prepare the communication management approach
4. To enable the project board to exercise overall control of a project
What 15the purpose of the ‘progress! practice?
Why is it necessary to apply the 'defined roles and responsibilities' principle?
How can the risk culture of 3n organization make decision-making less effective?