Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMI-001 Exam Dumps - PMI Project-Management-Professional Questions and Answers

Question # 34

How is the schedule variance calculated using the earned value technique?

Options:

A.

EV less AC

B.

AC less PV

C.

EV less PV

D.

AC less EV

Buy Now
Question # 35

Which items are an output of the Perform Integrated Change Control process?

Options:

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Buy Now
Question # 36

Outputs of the Control Communications process include:

Options:

A.

expert judgment and change requests.

B.

work performance information and change requests.

C.

organizational process asset updates and an issue log.

D.

project management plan updates and an issue log.

Buy Now
Question # 37

Which piece of information is part of the WBS Dictionary?

Options:

A.

Responsible organization

B.

Change requests

C.

Validated deliverables

D.

Organizational process assets

Buy Now
Question # 38

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

Options:

A.

Limited

B.

Low to moderate

C.

Moderate to high

D.

High to almost total

Buy Now
Question # 39

What are the five Project Management Process Groups?

Options:

A.

Initiating, Planning, Executing, Monitoring and Controlling, and Closing

B.

Introduction, Planning, Executing, Monitoring and Controlling, and Closing

C.

Initiating, Planning, Executing, Monitoring and Controlling, and Ending

D.

Introduction, Planning, Implementation, Monitoring and Controlling, and Closure

Buy Now
Question # 40

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

Options:

A.

Human resource management plan.

B.

Activity resource requirements.

C.

Personnel assessment tools,

D.

Multi-criteria decision analysis.

Buy Now
Question # 41

Which technique is utilized in the Control Schedule process?

Options:

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Buy Now
Question # 42

Cost variance (CV) is equal to earned value:

Options:

A.

Minus actual cost [EV - AC].

B.

Minus planned value [EV - PV].

C.

Divided by actual cost [EV/AC].

D.

Divided by planned value [EV/PV].

Buy Now
Question # 43

Analogous cost estimating relies on which of the following techniques?

Options:

A.

Expert judgment

B.

Project management software

C.

Vendor bid analysis

D.

Reserve analysis

Buy Now
Exam Code: PMI-001
Exam Name: Project Management Professional v5
Last Update: Aug 22, 2025
Questions: 918
PMI-001 pdf

PMI-001 PDF

$25.5  $84.99
PMI-001 Engine

PMI-001 Testing Engine

$28.5  $94.99
PMI-001 PDF + Engine

PMI-001 PDF + Testing Engine

$40.5  $134.99