Question # 4

A tool and technique used during the Collect Requirements process is:

Options:

A.

prototypes.

B.

expert judgment.

C.

alternatives identification.

D.

product analysis.

Buy Now
Question # 5

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Options:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

Buy Now
Question # 6

The precedence diagramming method (PDM) is also known as:

Options:

A.

Arrow Diagram.

B.

Critical Path Methodology (CPM).

C.

Activity-On-Node (AON).

D.

schedule network diagram.

Buy Now
Question # 7

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

Options:

A.

Identify Risks

B.

Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

Buy Now
Question # 8

Which characteristics do effective project managers possess?

Options:

A.

Project management knowledge, performance skills, and personal effectiveness

B.

Preparedness, project management knowledge, and personality characteristics

C.

General management, preparedness, and project management knowledge

D.

Assertiveness, collaboration, and performance skills

Buy Now
Question # 9

Which of the following is the correct network diagram for the table?

Options:

A.

Begin-A-C-D-E-End-B-D

B.

Begin-A-B-C-D-E-End

C.

Begin-A-B-D-E-End A-C-D

D.

Begin-A-C-D-E-End-B-C

Buy Now
Question # 10

Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work days. What should be your concern?

Options:

A.

There is a cost under run.

B.

There is a cost overrun.

C.

May not meet deadline.

D.

The project is 20 days behind schedule.

Buy Now
Question # 11

A project manager who communicates to the project team though email is using which type of communication?

Options:

A.

Formal

B.

Informal r

C.

Horizontal

D.

Unofficial

Buy Now
Question # 12

When should quality planning be performed?

Options:

A.

While developing the project charter

B.

In parallel with the other planning processes

C.

As part of a detailed risk analysis

D.

As a separate step from the other planning processes

Buy Now
Question # 13

During which process would stakeholders provide formal acceptance of the completed project scope?

Options:

A.

Perform Quality Control

B.

Verify Scope

C.

Control Scope

D.

Develop Schedule

Buy Now
Exam Code: PMI-001
Exam Name: Project Management Professional v5
Last Update: Aug 22, 2025
Questions: 918
PMI-001 pdf

PMI-001 PDF

$29.75  $84.99
PMI-001 Engine

PMI-001 Testing Engine

$33.25  $94.99
PMI-001 PDF + Engine

PMI-001 PDF + Testing Engine

$47.25  $134.99