Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 54

Which tool should a project manager use to calculate cost variance for a project?

Options:

A.

Contingency analysis

B.

Review lessons learned from similar projects

C.

Expert judgment

D.

Actual cost

Buy Now
Question # 55

A project manager is performing a specific process and has..........is being referred to?

A project manager is performing a specific process and has a list of accepted deliverables One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables Which process is being referred to?

Options:

A.

Control Quality

B.

Validate Scope

C.

Validate Quality

D.

Control Scope

Buy Now
Question # 56

Which process should be conducted from the project inception through completion?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Buy Now
Question # 57

A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?

Options:

A.

Expand the scope of the project.

B.

Schedule the tasks in sequence.

C.

Increase quality review cycles.

D.

Schedule the tasks in parallel.

Buy Now
Question # 58

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

Options:

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

Buy Now
Question # 59

Match each tool or technique with its corresponding Project Cost Management process.

Options:

Buy Now
Question # 60

Which are examples of processes that may be used once or at predefined points in the project life cycle?

Options:

A.

Develop Project Charter and Close Project or Phase

B.

Define Activities and Acquire Resources

C.

Control Schedule and Conduct Procurements

D.

Monitor Communications and Control Costs

Buy Now
Question # 61

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Buy Now
Question # 62

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

Options:

A.

Approved change requests

B.

Verified deliverables

C.

Lessons learned

D.

Work performance data

Buy Now
Question # 63

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:

Options:

A.

training, testing, and warranty work.

B.

equipment, rework, and scrap.

C.

training, document processes, and inspections.

D.

inspections, rework, and warranty work.

Buy Now
Question # 64

The following is a network diagram for a project.

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Buy Now
Question # 65

A project manager is reviewing some techniques that can be used to evaluate solution results. The intent is to evaluate the solution in the larger context to ensure it does not behave in unacceptable ways when deployed to production.

Which evaluation technique should be used here?

Options:

A.

Performance testing

B.

Integration testing

C.

Day-in-the-life testing

D.

Exploratory testing

Buy Now
Question # 66

When would resource leveling be applied to a schedule model?

Options:

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Buy Now
Question # 67

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

Options:

A.

BAC

B.

EAC

C.

ETC

D.

WBS

Buy Now
Question # 68

A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.

Options:

A.

Risks should be considered when selecting the content of each iteration.

B.

Risks should be tailored for each iteration.

C.

Risks should be identified, analyzed, and managed during each iteration.

D.

Risks should be documented prior to each iteration.

E.

Risks should be reviewed only once during each iteration.

Buy Now
Question # 69

A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and product acceptance criteria. Which activity is being performed?

Options:

A.

Inspection

B.

Prototyping

C.

Decision making

D.

Brainstorming

Buy Now
Question # 70

A business manager wants to start a project to launch a new product and submits a business case to the Portfolio Steering Committee for review. The committee asks the manager for details about the expected business value of the project.

How can the manager document the business value for the Portfolio Steering Committee?

Options:

A.

Conduct a feasibility study to determine the business impact of the new product.

B.

Prepare a benefits management plan to capture target benefits and strategic alignment.

C.

Execute a market study for similar products and demonstrate a market need.

D.

Create a presentation outlining the business benefits of the new product.

Buy Now
Question # 71

What organizational asset can influence the Plan Risk Management process?

Options:

A.

Corporate policies and procedures for social media, ethics, and security

B.

Organizational risk policy

C.

Stakeholder register templates and instructions

D.

Organizational communication requirements

Buy Now
Question # 72

For which kind of quantitative risk analysis chart can a tornado diagram represent values?

Options:

A.

Sensitivity analysis

B.

Monte Carlo analysis

C.

Expected monetary value analysis

D.

Decision tree analysis

Buy Now
Question # 73

Which item is a cost of conformance?

Options:

A.

Training

B.

Liabilities

C.

Lost business

D.

Scrap

Buy Now
Question # 74

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

Options:

A.

Acquisition

B.

Negotiation

C.

Virtual team

D.

Pre-assignment

Buy Now
Question # 75

Which of the following is least influenced by a project manager, according to the project manager ' s sphere of influence?

Options:

A.

Sponsors

B.

Project team

C.

Steering committees

D.

Stakeholders

Buy Now
Question # 76

Which of the following can be used as an input for Define Scope?

Options:

A.

Product analysis

B.

Project charter

C.

Scope baseline

D.

Project scope statement

Buy Now
Question # 77

A project team is brainstorming about the best methods and practices to adopt for an upcoming project. What is the project team trying to follow?

Options:

A.

Portfolios

B.

Standards

C.

Concepts

D.

Programs

Buy Now
Question # 78

During the execution phase of a multibillion-dollar project, the project manager encountered performance issues with some of the team members. In a performance review meeting, the project manager noticed that the team members do not follow SMART objectives.

What are SMART objectives?

Options:

A.

Specific, measurable, accurate, relevant, and time-bound.

B.

Specific, measurable, achievable, relevant, and time-bound.

C.

Specific, measurable, accurate, realistic, and time-bound.

D.

Specific, measurable, achievable, realistic, and time-bound.

Buy Now
Question # 79

Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?

Options:

A.

Hybrid methodologies

B.

Risk register updates

C.

Outsourced project resources

D.

Reliance on lessons learned documents

Buy Now
Question # 80

A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

Options:

A.

-700

B.

-200

C.

200

D.

500

Buy Now
Question # 81

What is a tailoring consideration in Project Integration Management?

Options:

A.

Validation and control

B.

Benefits

C.

Technology support

D.

Physical location

Buy Now
Question # 82

What does an S-curve from a Monte Carlo analysis show?

Options:

A.

Cumulative probability distribution representing probability of achieving a particular outcome

B.

Individual project risks or uncertainties that have the most potential impact on outcome

C.

Best alternative out of the possible solutions, incorporating associated risks and opportunities

D.

Diagram for all project uncertainties and their influence over a period of time

Buy Now
Question # 83

What internal enterprise environmental factor (EEF) can impact a project?

Options:

A.

Cultural influences

B.

Physical environmental elements

C.

Commercial databases

D.

Infrastructure

Buy Now
Question # 84

What process is included in Project Schedule Management?

Options:

A.

Estimate Activity Durations

B.

Create Work Breakdown Structure (WBS)

C.

Direct and Manage Project Work

D.

Estimate Activity Resources

Buy Now
Question # 85

Who provides the inputs for the original estimates of activity durations for tasks on the project plan?

Options:

A.

Project sponsor

B.

Project manager

C.

Person responsible for project scheduling

D.

Person who is most familiar with the task

Buy Now
Question # 86

The following is a network diagram for a project.

The free float for Activity E is how many days?

Options:

A.

2

B.

3

C.

5

D.

8

Buy Now
Question # 87

While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.

What should the team do to ensure that this situation is managed?

Options:

A.

Implement Appropriate Response

B.

Plan Project Risk Management

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Buy Now
Question # 88

Which subsidiary management plan.... during the project ilfe cycle?

Which Subsidiary management plan would a project manager create to manage Information dissemination during the project life cycle?

Options:

A.

Stakeholder Engagement Plan

B.

Quality Management Plan

C.

Communications Management Plan

D.

Scope Management Plan

Buy Now
Question # 89

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

Options:

A.

Organizational breakdown structure (OBS)

B.

Work performance information

C.

Work package

D.

Work breakdown structure (WBS)

Buy Now
Question # 90

During a sprint demo, the customer says that one of the user stories is not ready for customer use. Which checklist should the team look at to find out what has been missed for the user story?

Options:

A.

Burndown chart

B.

Velocity chart

C.

Definition of ready (DoR)

D.

Definition of done (DoD)

Buy Now
Question # 91

How does a requirements traceability matrix help to determine whether a product is ready for delivery?

Options:

A.

It captures assigned tasks and their estimated durations.

B.

It confirms the completion of all stories in the backlog.

C.

It assesses the quality of test cases and expected results.

D.

It tracks links between the approved requirements and each work product.

Buy Now
Question # 92

Which items are an output of the Perform Integrated Change Control process?

Options:

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Buy Now
Question # 93

Company A’s accountant sends notification about a change in the company’s tax classification.

What would a project have to be initiated?

Options:

A.

To change business and technological strategies

B.

To improve processes and services

C.

To meet regulatory and legal requirements

D.

To satisfy stakeholder requests

Buy Now
Question # 94

A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence.

What should the project manager do first?

Options:

A.

Extend an iteration review invite to the new stakeholder.

B.

Perform qualitative risk analysis.

C.

Engage with the new stakeholder.

D.

Allow team members to share project status reports.

Buy Now
Question # 95

Which tool uses an algorithm based on historical data to calculate cost?

Options:

A.

Three-point estimating

B.

Parametric estimating

C.

Analogous estimating

D.

Relative estimating

Buy Now
Question # 96

Which of the following is an output of the Distribute Information process?

Options:

A.

Project calendar

B.

Communications management plan

C.

Organizational process assets updates

D.

Project document updates

Buy Now
Question # 97

A sponsor asks a project manager to provide a project ' s expected total costs based on its progress. What formula should the project manager use to determine this?

Options:

A.

Earned value (EV) / actual cost (AC)

B.

Estimate at completion (EAC) - AC

C.

Budget at completion (BAC) / cost performance index (CPI)

D.

EV - planned value (PV)

Buy Now
Question # 98

In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

Options:

A.

Predictive

B.

Adaptive

C.

A mix

D.

Agile

Buy Now
Question # 99

Cost baseline is an output of which of the following processes?

Options:

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Estimate Activity Resources

Buy Now
Question # 100

What key component of the project charter defines the conditions for dosing a project phase?

Options:

A.

Purpose

B.

Approval requirements

C.

Exit criteria

D.

High-level requirements

Buy Now
Question # 101

Which of the following set of elements is part of an effective communications management plan?

Options:

A.

Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information

B.

Phone book directory, stakeholder communication requirements, project charter, glossary of common terminology

C.

Organizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology

D.

Glossary of common terminology, constraints denved from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan

Buy Now
Question # 102

During project selection, which factor is most important?

Options:

A.

Types of constraints

B.

Internal business needs

C.

Budget

D.

Schedule

Buy Now
Question # 103

An example of a group decision-making technique is:

Options:

A.

nominal group technique

B.

majority

C.

affinity diagram

D.

multi-criteria decision analysis

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Jul 5, 2026
Questions: 1326
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99