Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 54

The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager ' s disposal?

Options:

A.

Resource leveling and fast tracking

B.

Fast tracking and crashing

C.

Crashing and applying leads and lags

D.

Scheduling tools and applying leads and lags

Buy Now
Question # 55

After defining activities in project schedule management, which processes should a project manager follow?

Options:

A.

Sequence Activities and Estimate Activity Durations

B.

Estimate Activity Durations and Control Schedule

C.

Develop Schedule and Control schedule

D.

Review Activities and Develop Schedule

Buy Now
Question # 56

Which activity is an input to the Conduct Procurements process?

Options:

A.

Organizational process assets

B.

Resource availability

C.

Perform Integrated Change Control

D.

Team performance assessment

Buy Now
Question # 57

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

Options:

A.

Issue log

B.

Change log

C.

Expert judgment

D.

Change requests

Buy Now
Question # 58

In which process might a project manager use risk reassessment as a tool and technique?

Options:

A.

Perform Qualitative Risk Analysis

B.

Monitor and Control Risk

C.

Monitor and Control Project Work

D.

Plan Risk Responses

Buy Now
Question # 59

Which of the following lists of tools and techniques is used when conducting procurements?

Options:

A.

Expert judgement, procurement negotiations, bidder conferences, proposal evaluation advertising and independent estimates

B.

Budgeting procurement negotiations, bidder conferences, proposal evaluation and advertising, and seller ' s proposal C. Expert judgement, procurement negotiations bidder conferences, proposal evaluation and advertising, and make-or-buy decisions

C.

Agreements procurement negotiations, bidder conferences, proposal evaluation and advertising selected seller

Buy Now
Question # 60

Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

Options:

A.

Influencing

B.

Motivation

C.

Negotiation

D.

Trust building

Buy Now
Question # 61

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Change requests.

C.

Accepted deliverables.

D.

Variance analysis.

Buy Now
Question # 62

What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

Options:

A.

Pareto

B.

Ishikawa

C.

Shewhart-Deming

D.

Delphi

Buy Now
Question # 63

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

Options:

A.

Performance organizations

B.

Schedule baselines

C.

Work performance measurements

D.

Change requests

Buy Now
Question # 64

What does leadership involve?

Options:

A.

Working with others through discussion or debate to guide them from one point to another

B.

Directing another person from one point to another using a known set of expected behaviors

C.

Working with a person using expert judgment to develop the technical deliverables

D.

Directing another person to develop the necessary expertise to establish technical deliverables

Buy Now
Question # 65

Which Manage Communications tool or technique focuses on identifying and managing barriers?

Options:

A.

Communication methods

B.

Information technology

C.

Communication models

D.

Information management systems

Buy Now
Question # 66

Which of the following is an example of tacit knowledge

Options:

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Buy Now
Question # 67

Perform Quantitative Analysis focuses on:

Options:

A.

compiling a lsit of known risks and preparing responses to them

B.

assessing the probability of occurrence and impact for every risk in the risk register

C.

evaluating the contingency and management reserves required for the project

D.

analyzing numerically the impact of individual risks on the overall project ' s time and cost objectives

Buy Now
Question # 68

Which defines the portion of work included in a contract for items being purchased or acquired?

Options:

A.

Procurement management plan

B.

Evaluation criteria

C.

Work breakdown structure

D.

Procurement statement of work

Buy Now
Question # 69

When managing costs in an agile environment, what should a project manager consider?

Options:

A.

Lightweight estimation methods can be used as changes arise.

B.

Agile environments make cost aggregation more difficult.

C.

Agile environments make projects more costly and uncertain.

D.

Detailed cost calculations benefit from frequent changes.

Buy Now
Question # 70

How can a project manager represent a contingency reserve in the schedule?

Options:

A.

Additional weeks of work to account for unknown-unknowns risks

B.

Task duration estimates of the best case scenarios

C.

Addition Duration estimates in response to identified risks that have been accepted

D.

Milestones representing the completion of deliverables

Buy Now
Question # 71

Stakeholder identification and engagement should begin during what phase of the project?

Options:

A.

After the project management plan is completed

B.

After the stakeholder engagement plan is completed

C.

As soon as the project charter has been approved

D.

After the communications management plan is completed

Buy Now
Question # 72

What are the formal and informal policies, procedures, and guidelines that could impact how the project ' s scope is managed?

Options:

A.

Organizational process assets

B.

Enterprise environmental factors

C.

Project management processes

D.

Project scope management plan

Buy Now
Question # 73

Which of the following set of items belongs to the communications management plan?

Options:

A.

Escalation processes and meeting management

B.

Project schedule and glossary of common terminology

C.

Escalation processes and stakeholder communication requirements

D.

Interactive communication model and information to be communicated

Buy Now
Question # 74

Enterprise environmental factors are an input to which process?

Options:

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Buy Now
Question # 75

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

Options:

A.

Urgent information need

B.

Sensitivity of information

C.

Project environment

D.

Ease of use

Buy Now
Question # 76

What is one of the objectives of Project Risk Management?

Options:

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Buy Now
Question # 77

An input to the Plan Procurement Management process is:

Options:

A.

Source selection criteria.

B.

Market research.

C.

A stakeholder register.

D.

A records management system.

Buy Now
Question # 78

The following is a network diagram for a project.

The free float for Activity E is how many days?

Options:

A.

2

B.

3

C.

5

D.

8

Buy Now
Question # 79

Which procurement management process includes obtaining seller response, seller selection, and contract awarding?

Options:

A.

Plan Procurement

B.

Manage Procurement

C.

Conduct Procurements

D.

Perform Procurement

Buy Now
Question # 80

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

Options:

A.

Work performance reports

B.

Assumptions logs

C.

Network diagrams

D.

Academic studies

Buy Now
Question # 81

Which item is a formal proposal to modify any document, deliverable, or baseline?

Options:

A.

Change request

B.

Requirements documentation

C.

Scope baseline

D.

Risk urgency assessment

Buy Now
Question # 82

What process is performed periodically throughout the project as needed?

Options:

A.

Plan Risk Management

B.

Plan Communications Management

C.

Plan Resource Management

D.

Plan Cost Management

Buy Now
Question # 83

Which tool and technique is used in Conduct Procurements?

Options:

A.

Teaming agreements

B.

Expert judgment

C.

Bidder conferences

D.

Contract types

Buy Now
Question # 84

Which tools and techniques should a project manager use when estimating costs?

Options:

A.

Lessons learned register and cost aggregation

B.

Project schedule and resources requirements

C.

Three-point estimating and risk register

D.

Expert judgempnt and decision making

Buy Now
Question # 85

A project is in its final stages when a competitor releases a similar product. This could make the project redundant. What should the project manager do next?

Options:

A.

Initiate change control.

B.

Address risk mitigation.

C.

Escalate this to the project sponsor.

D.

Initiate project closure.

Buy Now
Question # 86

In which type of organizational structure are staff members grouped by specialty?

Options:

A.

Functional

B.

Projectized

C.

Matrix

D.

Balanced

Buy Now
Question # 87

Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?

Options:

A.

Scope plan

B.

Product scope

C.

Scope management plan

D.

Scope baseline

Buy Now
Question # 88

Which of the following is a narrative description of products, services, or results to be delivered by a project?

Options:

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

Buy Now
Question # 89

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

Options:

A.

ends.

B.

begins.

C.

delays.

D.

deviates.

Buy Now
Question # 90

How does planning for prevention costs assist in meeting stakeholder needs and expectations, while still providing required performance and reliability?

Options:

A.

It details product or service failures experienced by the customer

B.

It clarifies the costs associated with assessing the quality of the product or service

C.

It accounts for costs used to avoid poor quality in the product or service

D.

It communicates product or service failures discovered by the project team

Buy Now
Question # 91

The following is a network diagram for a project.

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Buy Now
Question # 92

Which enterprise environmental factors are considered during Estimate Costs?

Options:

A.

Market conditions and published commercial information

B.

Company structure and market conditions

C.

Commercial information and company structure

D.

Existing human resources and market conditions

Buy Now
Question # 93

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

Options:

A.

Cost management plan

B.

Quality management plan

C.

Communications management plan

D.

Risk management plan

Buy Now
Question # 94

Which illustrates the connection between work that needs to be done and its project team members?

Options:

A.

Work breakdown structure (WBS)

B.

Network diagrams

C.

Staffing management plan

D.

Responsibility assignment matrix (RAM)

Buy Now
Question # 95

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:

Options:

A.

training, testing, and warranty work.

B.

equipment, rework, and scrap.

C.

training, document processes, and inspections.

D.

inspections, rework, and warranty work.

Buy Now
Question # 96

The ability to influence cost is greatest during which stages of the project?

Options:

A.

Early

B.

Middle

C.

Late

D.

Completion

Buy Now
Question # 97

Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project ' s:

Options:

A.

Level of control.

B.

Communication channels.

C.

Scope.

D.

Strategic alignment.

Buy Now
Question # 98

The Human Resource Management processes are:

Options:

A.

Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.

B.

Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.

C.

Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.

D.

Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.

Buy Now
Question # 99

Which action is included in the Control Costs process?

Options:

A.

Identify how the project costs will be planned, structured, and controlled

B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.

Develop an approximation of the monetary resources needed to complete project activities

D.

Monitor cost performance to isolate and understand variances from the approved cost baseline

Buy Now
Question # 100

Which tool or technique is an examination of industry and specific vendor capabilities?

Options:

A.

Independent estimates

B.

Market research

C.

Analytical techniques

D.

Bidder conferences

Buy Now
Question # 101

A business analyst sent multiple meeting requests via instant message to a subject matter expert (SME) working in another country but did not receive a response. What should the business analyst do to reduce the likelihood of this occurring in the future with other stakeholders distributed across multiple locations?

Options:

A.

Ask each stakeholder for their preferred communication method.

B.

Confirm the time zone and work days in each location.

C.

Check with the IT department to see if there is a technical issue.

D.

Assume the meeting request is accepted unless declined.

Buy Now
Question # 102

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

Options:

A.

0.45

B.

0.56

C.

0.70

D.

1.36

Buy Now
Question # 103

Which Perform Quality Control tool graphically represents how various elements of a system interrelate?

Options:

A.

Control chart

B.

Flowchart

C.

Run chart

D.

Pareto chart

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: May 21, 2026
Questions: 1320
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99