Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 4

During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.

What could be missing from the business case?

Options:

A.

Work breakdown structure (WBS)

B.

Approval from the stakeholders

C.

Feasibility study of the solution

D.

Root cause analysis of the problem

Buy Now
Question # 5

Which of the following documents allows the project manager to assess risks that may require near term action?

Options:

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Buy Now
Question # 6

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Performance reports

B.

Project charter

C.

Outputs from planning processes

D.

Enterprise environmental factors

Buy Now
Question # 7

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?

Options:

A.

Analogous

B.

Parametric

C.

Bottom-up

D.

Top-down

Buy Now
Question # 8

What document gathers all of the lessons learned at the end of a phase or project

Options:

A.

Lessons learned register

B.

Lessons learned list

C.

Lessons learned project asset

D.

Lessons learned repository

Buy Now
Question # 9

An organization that is being interviewed online has recently experienced a severe network outage. Consequently, the organization has stated that it is required to have a working data network.

Which classification should be assigned to data network requirements?

Options:

A.

Customer requirement

B.

Transition requirement

C.

Solution requirement

D.

Business requirement

Buy Now
Question # 10

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

Options:

A.

Monitor and Control Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Buy Now
Question # 11

A project manager is leading a project in a volatile industry. Industry standards are updated often, which requires the project team to make frequent adjustments to their work.

What should the project manager create to manage the possible changes?

Options:

A.

Communications management plan

B.

Cost management plan

C.

Risk management plan

D.

Quality management plan

Buy Now
Question # 12

A Project manager is failing to secure critical equipment on time, and this resulting in delays in the manufacturing of the final product. Which knowledge area is the project manager handling?

Options:

A.

Project Resource Management

B.

Project Quality Management

C.

Project Schedule Management

D.

Project integration Management

Buy Now
Question # 13

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

Options:

A.

Requirements traceability matrix

B.

Work breakdown structure (WBS) dictionary

C.

Requirements management plan

D.

Requirements documentation

Buy Now
Question # 14

What method for categorizing stakeholders is suitable for small projects with simple relationships among stakeholders ' ?

Options:

A.

Prioritization

B.

Directions of influence

C.

Salience model

D.

Power/influence grid

Buy Now
Question # 15

A sponsor asks a project manager to provide a project ' s expected total costs based on its progress. What formula should the project manager use to determine this?

Options:

A.

Earned value (EV) / actual cost (AC)

B.

Estimate at completion (EAC) - AC

C.

Budget at completion (BAC) / cost performance index (CPI)

D.

EV - planned value (PV)

Buy Now
Question # 16

What is the first step in the Stakeholder Management process?

Options:

A.

Plan Stakeholder Engagement

B.

Identify Stakeholders

C.

Manage Stakeholder Responsibility

D.

Monitor Stakeholder Activity

Buy Now
Question # 17

The Monitoring and Controlling Process Group includes processes that:

Options:

A.

Establish the scope, objectives, and course of action of a project,

B.

Define a new project or a new phase of an existing project.

C.

Track, review, and regulate the progress and performance of a project.

D.

Complete the work defined in the project management plan.

Buy Now
Question # 18

The project scope statement and resource calendars are inputs to which Project Time Management process?

Options:

A.

Sequence Activities

B.

Estimate Activity Resources

C.

Develop Schedule

D.

Control Schedule

Buy Now
Question # 19

During a sprint demo, the customer says that one of the user stories is not ready for customer use. Which checklist should the team look at to find out what has been missed for the user story?

Options:

A.

Burndown chart

B.

Velocity chart

C.

Definition of ready (DoR)

D.

Definition of done (DoD)

Buy Now
Question # 20

During a virtual kick-off session, the project sponsor highlights the significance of the project to the company. What message should be conveyed to the team in this meeting?

Options:

A.

Bonuses based on accomplishment criteria

B.

New working contract with more benefits

C.

Promotion opportunities with this project

D.

Assignment of key roles and responsibilities

Buy Now
Question # 21

What is a tailoring consideration for the application of Project Risk Management processes?

Options:

A.

Project complexity

B.

Procurement criteria

C.

Communication technology

D.

Knowledge management

Buy Now
Question # 22

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

Options:

A.

Text-oriented formal

B.

Resource management plan

C.

Organization chart

D.

Responsibility assignment matrix (RAM)

Buy Now
Question # 23

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

Options:

A.

Discuss the processes and deliverables needed to meet the project objectives with the team.

B.

Integrate hybrid approach processes and deliverables to meet the short delivery time line.

C.

Identify the processes and deliverables for only the current phase first.

D.

Follow organizational methodology and produce all required deliverables.

Buy Now
Question # 24

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

Options:

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

Buy Now
Question # 25

What should a project manager use to determine how much money is needed to complete a project?

Options:

A.

Earned value management (EVM)

B.

Estimate at completion (EAC)

C.

Earned value analysis (EVA)

D.

Budget at completion (BAG)

Buy Now
Question # 26

The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.

Which of the 5Cs of written communications does the project manager need to address?

Options:

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

Buy Now
Question # 27

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

Options:

A.

scope creep.

B.

a change request.

C.

work performance information.

D.

deliverables.

Buy Now
Question # 28

Which of the following characteristics are found in a functional organizational structure?

Options:

A.

Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget

B.

Limited project manager authority, limited resource availability, and a part-time project manager ' s role

C.

Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager ' s role

D.

High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Buy Now
Question # 29

What is the recommended approach for handling risk in a high-variability environment?

Options:

A.

Adaptive

B.

Predictive

C.

Iterative

D.

Incremental

Buy Now
Question # 30

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

Options:

A.

Procurement documents

B.

Communications plan

C.

Project charter

D.

Stakeholder register

Buy Now
Question # 31

In which Knowledge Area is the project charter developed?

Options:

A.

Project Cost Management

B.

Project Scope Management

C.

Project Time Management

D.

Project Integration Management

Buy Now
Question # 32

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

Options:

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Buy Now
Question # 33

Given the following information, what is the schedule variance (SV) for this project?

Early start date (ES): 16 weeks

Actual time: 12 weeks

Schedule performance index (SPI): 1.3

Options:

A.

5

B.

2

C.

3

D.

4

Buy Now
Question # 34

The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.

What are these elements called?

Options:

A.

Project activities

B.

Work packages

C.

Planning packages

D.

Project deliverables

Buy Now
Question # 35

What characteristic of servant leadership supports resource management in an agile environment?

Options:

A.

Lecturing

B.

Construing

C.

Measuring

D.

Coaching

Buy Now
Question # 36

The process of identifying and documenting relationships among the project activities is known as:

Options:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

Buy Now
Question # 37

A new project was approved by the project management office (PMO), and the scope of the project is to build a new detachable classroom. What delivery method and artifacts should the project manager use to deliver this project?

Options:

A.

Linear project management; project schedule and project backlog

B.

Adaptive project management; project schedule and work breakdown structure

C.

Linear project management; project schedule and work breakdown structure (WBS)

D.

Adaptive project management; project schedule and project backlog

Buy Now
Question # 38

A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client ' s project manager. The technical lead is requesting two new developers.

Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?

Options:

A.

Cost management plan

B.

Business management plan

C.

Stakeholder engagement plan

D.

Resource management plan

Buy Now
Question # 39

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

Options:

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Buy Now
Question # 40

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

Options:

A.

Interactive

B.

Push

C.

Verbal

D.

Oral

Buy Now
Question # 41

Stakeholder communication requirements should be included as a component of:

Options:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Buy Now
Question # 42

After missing a weekly communication meeting hosted by the project manager, a stakeholder looks at the latest report in the common repository.

What is the communication type used in this scenario?

Options:

A.

Pull

B.

Verbal

C.

Written

D.

Push

Buy Now
Question # 43

The Verify Scope process is primarily concerned with:

Options:

A.

formalizing acceptance of the completed project deliverables.

B.

accuracy of the work deliverables.

C.

formalizing approval of the scope statement.

D.

accuracy of the work breakdown structure (WBS).

Buy Now
Question # 44

A project lifecycle is defined as:

Options:

A.

a collection of generally sequential and sometimes overlapping project phases.

B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

C.

a recognized standard for the project management profession.

D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Buy Now
Question # 45

Which tools or techniques are used in the Plan Schedule Management process?

Options:

A.

Benchmarking, expert judgment, and analytical techniques

B.

Statistical sampling, benchmarking, and meetings

C.

Negotiations, pre-assignment, and multi-criteria decision analysis

D.

Expert judgment, analytical techniques, and meetings

Buy Now
Question # 46

A product owner wants to ensure that the project ' s requirements, including product requirements, are met and validated. To do this project manager wants.

Match each process to its definition.

Options:

Buy Now
Question # 47

A project manager read the initial contract when a project was started. The contract states a house has to be built in one year, and the foundation has to be completed in 30 days. What should the project manager do?

Options:

A.

Add the milestones to the risk register, as time is short.

B.

Add the two milestones to the project plan, as they are mandatory.

C.

Calculate the duration of the two milestones stated in the contract.

D.

Start the project as soon as possible, as time is short.

Buy Now
Question # 48

A project is composed of three phases that are implemented in parallel without affecting one another. The baselines for each individual phase have been approved by the major stakeholders, and there is a minimal ability to vary the baselines during the execution of the project.

Which methodology did the project manager adopt?

Options:

A.

Incremental approach

B.

Predictive approach

C.

Hybrid approach

D.

Iterative approach

Buy Now
Question # 49

Which enterprise environmental factors should be considered when creating a new procurement contract?

Options:

A.

Supply chains

B.

Trial engagements

C.

Lessons learned register

D.

Local laws and regulalk

Buy Now
Question # 50

In one of the project meetings during project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?

Options:

A.

Ignore the risk from this stakeholder as this stakeholder never showed up at the start of the project.

B.

Make sure proper testing gets completed to minimize the risk highlighted.

C.

Add this risk to the lessons learned register on project completion.

D.

Add the stakeholder to the stakeholder register and add the risk to the risk register.

Buy Now
Question # 51

Match the method for categorizing stakeholders with its corresponding description

Options:

Buy Now
Question # 52

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Options:

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Buy Now
Question # 53

A technique used to determine the cause and degree of difference between baseline and actual performance is:

Options:

A.

Product analysis.

B.

Variance analysis.

C.

Document analysis,

D.

Decomposition.

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: May 21, 2026
Questions: 1320
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99