Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 254

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

Options:

A.

Business case

B.

Work breakdown structure

C.

Requirements documentation

D.

Risk register

Buy Now
Question # 255

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Project scope statement.

C.

Organizational process assets.

D.

Requirements traceability matrix.

Buy Now
Question # 256

If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?

Options:

A.

Plan Quality Management

B.

Control Quality

C.

Risk Management

D.

Plan Scope Management

Buy Now
Question # 257

The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:

Options:

A.

Analysis

B.

Appetite

C.

Tolerance

D.

Response

Buy Now
Question # 258

In which organizational structure would the project manager have most authority?

Options:

A.

Matrix-weak

B.

Matrix-balanced

C.

Matrix-strong

D.

Organic or simple

Buy Now
Question # 259

Which enterprise environmental factors should be considered when creating a new procurement contract?

Options:

A.

Supply chains

B.

Trial engagements

C.

Lessons learned register

D.

Local laws and regulalk

Buy Now
Question # 260

An organization that is being interviewed online has recently experienced a severe network outage. Consequently, the organization has stated that it is required to have a working data network.

Which classification should be assigned to data network requirements?

Options:

A.

Customer requirement

B.

Transition requirement

C.

Solution requirement

D.

Business requirement

Buy Now
Question # 261

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

Options:

A.

Critical path method

B.

Critical chain method

C.

Resource leveling

D.

Schedule network analysis

Buy Now
Question # 262

Which is an output from Distribute Information?

Options:

A.

Earned value analysis

B.

Trend analysis

C.

Project records

D.

Performance reviews

Buy Now
Question # 263

The Perform Quality Assurance process occurs in which Process Group?

Options:

A.

Executing

B.

Monitoring and Controlling

C.

Initiating

D.

Planning

Buy Now
Question # 264

What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives ' ?

Options:

A.

Executing

B.

Planning

C.

Initiating

D.

Monitoring and Controlling

Buy Now
Question # 265

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Options:

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Buy Now
Question # 266

A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members knows their roles and responsibilities.

What are the four elements of a RACI chart?

Options:

A.

Recommend, approve, coordinate, and inform

B.

Responsible, accountable, consult, and inform

C.

Recommend, accountable, consult, and inform

D.

Responsible, accountable, coordinate, and inform

Buy Now
Question # 267

Which format can a network diagram take?

Options:

A.

Flow chart

B.

Control chart

C.

Affinity diagram

D.

Cause-and-effect diagram

Buy Now
Question # 268

Make-or-buy analysis is a tool and technique of which process?

Options:

A.

Conduct Procurements

B.

Plan Procurement Management

C.

Analyze Procurements

D.

Control Procurements

Buy Now
Question # 269

What is an example of a technical project management skill?

Options:

A.

Managing a project schedule

B.

Developing a project delivery strategy

C.

Establishing a project team

D.

Understanding organizational objectives

Buy Now
Question # 270

Which document describes the necessary information to determine if a project is worth the required investment?

Options:

A.

Cost baseline

B.

Service level agreement

C.

Memorandum of understanding

D.

Business case

Buy Now
Question # 271

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

Options:

A.

Plan Schedule Management.

B.

Develop Project Charter.

C.

Develop Schedule.

D.

Plan Scope Management.

Buy Now
Question # 272

The activity tailoring is necessary because:

Options:

A.

the members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide, this is required for all projects

B.

each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide

C.

the members of the project team need to understand the PMBOK Guide processes, which are applied to all projects

D.

each project is unique, and the project team must plain how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide

Buy Now
Question # 273

A project manager needs to develop a product roadmap. Which artifact category is a product roadmap?

Options:

A.

Report artifact

B.

Strategic artifact

C.

Baseline artifact

D.

Plan artifact

Buy Now
Question # 274

During which process would stakeholders provide formal acceptance of the completed project scope?

Options:

A.

Perform Quality Control

B.

Verify Scope

C.

Control Scope

D.

Develop Schedule

Buy Now
Question # 275

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

Options:

A.

Urgent information need

B.

Sensitivity of information

C.

Project environment

D.

Ease of use

Buy Now
Question # 276

Which of the following is an output of the Monitor and Control Project Work process?

Options:

A.

Change requests

B.

Performance reports

C.

Organizational process assets

D.

Project management plan

Buy Now
Question # 277

Which of the following does a portfolio combine?

Options:

A.

Projects, programs, and operations

B.

Operations, strategies, and business continuity

C.

Projects, programs, and risks

D.

Projects, change management, and operations

Buy Now
Question # 278

A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?

Options:

A.

Organizational process assets

B.

Change management plan

C.

Communications management plan

D.

Resource management plan

Buy Now
Question # 279

A project manager has been assigned to a project with a short duration and given funding to form a small team. The project manager needs to choose team members based on their availability and other aspects.

What other features should the project manager consider?

Options:

A.

Skill set, expertise, and training readiness

B.

Past project performance, wage rate, and network base

C.

Collaborative skills, quality focus, and political connections

D.

Priorities, resource demand, and expertise

Buy Now
Question # 280

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take into account for risk management in this environment?

Options:

A.

Occasionally identify, evaluate, and classify risks.

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Buy Now
Question # 281

Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?

Options:

A.

Cause and effect diagram

B.

Control charts

C.

Pareto chart

D.

Histogram

Buy Now
Question # 282

Which is the tool or technique that is used to obtain the list of activities from the work packages?

Options:

A.

Data analysis

B.

Leads and lags

C.

Precedence diagramming method

D.

Decomposition

Buy Now
Question # 283

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

Options:

A.

Change request

B.

Risk response

C.

Risk management plan

D.

Lessons learned

Buy Now
Question # 284

Which stakeholder approves a project ' s result?

Options:

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Buy Now
Question # 285

Which Control Quality tool is also known as an arrow diagram?

Options:

A.

Matrix diagram

B.

Affinity diagram

C.

Tree diagram

D.

Activity network diagram

Buy Now
Question # 286

Which process determines the correctness of deliverables?

Options:

A.

Verify Deliverables

B.

Validate Deliverables

C.

Review Deliverables

D.

Analyze Deliverables

Buy Now
Question # 287

What tool or technique is used in the Collect Requirements process?

Options:

A.

Inspection

B.

Decomposition

C.

Product analysis

D.

Prototypes

Buy Now
Question # 288

What is the process of ensuring that project resources are assigned and available?

Options:

A.

Control Procurements

B.

Acquire Resources

C.

Control Resources

D.

Plan Procurement Management

Buy Now
Question # 289

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

Options:

A.

Checksheets

B.

Histograms

C.

Flowcharts

D.

Control charts

Buy Now
Question # 290

Which of the following is a tool and technique used in the Develop Schedule process?

Options:

A.

Three-point estimates

B.

Resource leveling

C.

Precedence diagramming method

D.

Bottom-up estimating

Buy Now
Question # 291

Most experienced project managers know that:

Options:

A.

every project requires the use of all processes in the PMBOK® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

Buy Now
Question # 292

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

Options:

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Buy Now
Question # 293

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

Options:

A.

0.50

B.

0.67

C.

1.50

D.

2.00

Buy Now
Question # 294

A project manager should communicate to stakeholders about resolved project issues by updating the:

Options:

A.

project records

B.

project reports

C.

stakeholder notifications

D.

stakeholder register

Buy Now
Question # 295

Lessons learned are created and project resources are released in which Process Group?

Options:

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Buy Now
Question # 296

Funding limit reconciliation is a tool and technique of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Question # 297

The definition of operations is a/an:

Options:

A.

organizational function performing the temporary execution of activities that produce the same product or provide repetitive service.

B.

temporary endeavor undertaken to create a unique product, service, or result.

C.

organization that provides oversight for an administrative area.

D.

organizational function performing the ongoing execution of activities that produce the same product or provide repetitive service.

Buy Now
Question # 298

An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.

Which two of the following items should be included in the planning? (Choose two)

Options:

A.

Daily scrum

B.

Sprint backlog

C.

Sprint review

D.

Increments

E.

Sprint retrospective

Buy Now
Question # 299

What tool or technique will establish expected behaviors for project team members?

Options:

A.

Ground rules

B.

Decision mating

C.

Power/influence grid

D.

Stakeholder engagement assessment matrix

Buy Now
Question # 300

An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the product was to be launched in the beta phase. One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.

Why was the product still determined to be ready for delivery?

Options:

A.

The development team ran out of time and did not pull the social media story from the backlog.

B.

The development team completed all of the stories identified by the product owner as having the highest customer value.

C.

The sprint demo went smoothly and the team did not find any open issues.

D.

The social media story is a marketing priority and less important than other priorities.

Buy Now
Question # 301

Exhibit A is an example of which of the following types of Sequence Activities?

Options:

A.

Activity-on-arrow diagramming

B.

Precedence diagramming

C.

Project schedule network diagramming

D.

Mathematical analysis diagramming

Buy Now
Question # 302

What estimating technique is used when there is limited information?

Options:

A.

Analogous estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Three-point estimating

Buy Now
Question # 303

Which behavior is a management trait?

Options:

A.

Asking what and why

B.

Challenging the status quo

C.

Innovating

D.

Relying on control

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Jul 5, 2026
Questions: 1326
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99