A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?
Which of the following are processes associated with Project Cost Management?
A project manager held a meeting and listed all team members' ideas for improving the product on a white board. What data gathering technique did the project manager apply?
Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
The project manager is creating the communications management plan Which group of inputs Is required to begin?
In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?
A project using the agile/adaptive approach has reached the Project Integration Management phase. What is the project manager's key responsibility during this phase?
Which of the following are components of the technical project management skill?
Which is a list of organizational systems that may have an impact on a project?
Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?
The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?
Once the make-or-buy analysis is completed, which document defines the project delivery method?
How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?
An important project stakeholder has low risk tolerance. Which type ot communication should a project manager use to provide this stakeholder with a difficult update?
What communication methods would a project manager use for overall effective project communication?
Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?
What is a tailoring consideration for the application of Project Risk Management processes?
During which process of Project Cost Management does a project manager produce the cost baseline?
During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?
Which of the following best correspond to the organizational process assets (OPAs) that affect the project?
A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?
A project manager is experiencing a project with a high degree of change. Which type of stakeholder engagement does this project require?
At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?
Which of the following lists represents the outputs of the Monitor Communications process?
A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting. Which two procedures will the project team perform? (Choose two)
While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.
What should the team do to ensure that this situation is managed?
A project team is closing out a phase and updating the organizational knowledge base What organizational process asset (OPA) will the team update?
During the project life cycle for a major product, a stakeholder asked to add a new feature. Which document should they consult for guidance?
What process is used to identify quality requirements and/or standards for a project and its deliverables'?
A business manager wants to start a project to launch a new product and submits a business case to the Portfolio Steering Committee for review. The committee asks the manager for details about the expected business value of the project.
How can the manager document the business value for the Portfolio Steering Committee?
A project team is brainstorming about the best methods and practices to adopt for an upcoming project. What is the project team trying to follow?
A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?
Given the following information, what is the schedule variance (SV) for this project?
Early start date (ES): 16 weeks
Actual time: 12 weeks
Schedule performance index (SPI): 1.3
The project manager has following information about duration for an activity:
* Most likely [tM] - 15 days
* Pessimistic [tP] - 20 days
* Optimistic [tO] - 10 days
What is the estimated duration of this activity, according to the triangular distribution technique?
What quantitative risk analysis technique is used to select the optimum course of action from a number of alternatives?
Following a project planning meeting with the team, a few team members approach the project manager to follow up on actions required. How can the project manager assess the effectiveness of the meeting?
After defining activities in project schedule management, which processes should a project manager follow?
During a project team meeting, one of the team members suggested a product functionality that would immensely benefit the customer. The project manager documents the request for later analysis. What is this an example of?