During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?
Which of the following is least influenced by a project manager, according to the project manager's sphere of influence?
Which of the following are outputs of define scope process in project scope management
Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?
Which is the appropriate tool to identify the possible correlation two elements in aprocess?
The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?
What is purpose of using the building information model (BIM) in software tools in the construction field?
A product owner reviews the list of stakeholders to confirm their continued involvement with the product team. A new stakeholder is identified as actively involved in the next product release.
What should the project manager do next to engage the new stakeholder?
During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.
What should the project manager do?
All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?
A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?
The executive committee of a company is reviewing its portfolios. Which of the following would be helpful to evaluate success?
A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity's prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.
How should the project manager proceed?
Construction of a building has stopped due to a supplier's failure to deliver concrete. The project schedule is behind by three months.
What should the project manager do to overcome this problem and put the project back on track?
A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?
At what stages of project should the identify Stakeholder process be performed?
A business case is being assembled. Which two elements are necessary to complete this process? (Choose two)
Why is working in iterations usually more time consuming than using a predictive life cycle?
A Scrum team has a product backlog and a sprint backlog. Which of the following is a correct statement related to these artifacts?
An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.
Which two of the following items should be included in the planning? (Choose two)
A key project team member complains about being left out of the communication loop. In order to ensure that each key member is involved, who should review the business analysis communications management plan?
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
During what project management process does the project team begin identifying risks?
The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.
Which of the 5Cs of written communications does the project manager need to address?
During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three)
In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?
A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?
Which process is engaged when a project team member makes a change to project budget with project manager's approval
A project sponsor has asked the project manager to determine how soon the project can be completed. Which of the following methods can a project manager use to find this information?
The project manager is working in the Resource Management process. Which items may the project manager need to include in the team charter?
A Project manager is failing to secure critical equipment on time, and this resulting in delays in the manufacturing of the final product. Which knowledge area is the project manager handling?
An executive sponsor wants to be briefed on how the product will change over time. Which document should the business analyst use to prepare their presentation?
Which is the main benefit of managing and tailoring strategies in the Stakeholder Engagement process?
In one of the project meetings during project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?
What characteristic of servant leadership supports resource management in an agile environment?
A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?