Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 104

Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?

Options:

A.

Product

B.

Cost-benefit

C.

Stakeholder

D.

Research

Buy Now
Question # 105

Which type of analysis is used as a general management technique within the Plan Procurements process?

Options:

A.

Risk assessment analysis

B.

Make or buy analysis

C.

Contract value analysis

D.

Cost impact analysis

Buy Now
Question # 106

In the last two iterations, a project team failed to deliver all of the stories on time. What should the project manager do first in order to prevent this from recurring?

Options:

A.

Extend the delivery time for the product since the management reserve allows it.

B.

Temporarily use another team for the next iteration and evaluate their performance.

C.

Observe the project team ' s performance for the next two iterations before taking any action.

D.

Identify possible reasons for the delay and consult the risk register for corrective actions.

Buy Now
Question # 107

Whose approval may be required for change requests after change control board (CCB) approval?

Options:

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Buy Now
Question # 108

Which set of tools and techniques is useful for estimating activity durations for the project schedule?

Options:

A.

Brainstorming, Monte Carlo simulation, analogous estimation

B.

Three-point estimation, resources leveling, iteration burndown chart

C.

Milestone charts, parametric estimation, schedule baseline

D.

Parametric estimation, three-point estimation, meetings

Buy Now
Question # 109

What is an output of the plan resource management process

Options:

A.

Project charter

B.

Risk register

C.

Scope baseline

D.

Stakeholder register

Buy Now
Question # 110

What is the common factor among portfolios, programs, and projects, regardless of the hierarchy within an organization?

Options:

A.

Resources and stakeholders

B.

Operations and performance

C.

Subsidiary projects

D.

Project manager

Buy Now
Question # 111

Which tool and technique is used in Conduct Procurements?

Options:

A.

Teaming agreements

B.

Expert judgment

C.

Bidder conferences

D.

Contract types

Buy Now
Question # 112

An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float.

What is the likelihood the team will complete all 20 story points in the upcoming sprint?

Options:

A.

50-75%

B.

25-50%

C.

75-100%

D.

0-25%

Buy Now
Question # 113

The following is a network diagram for a project.

The critical path for the project is how many days in duration?

Options:

A.

10

B.

12

C.

14

D.

17

Buy Now
Question # 114

A business analyst has encountered a conflict related to competing requirements on an existing project. What tool should the business analyst use to resolve this issue?

Options:

A.

Peer review

B.

Procurement management

C.

Weighted ranking

D.

Risk assessment

Buy Now
Question # 115

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

Options:

A.

Activity cost estimates

B.

Earned value management

C.

Cost management plan

D.

Cost baseline

Buy Now
Question # 116

The correct equation for schedule variance (SV) is earned value:

Options:

A.

minus planned value [EV - PV].

B.

minus actual cost [EV - AC].

C.

divided by planned value [EV/PV],

D.

divided by actual cost [EV/AC].

Buy Now
Question # 117

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Options:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

Buy Now
Question # 118

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

Options:

A.

Monitor and Control Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Buy Now
Question # 119

A new project manager is assigned to a high-visibility project. The project manager starts with the requirements analysis process. Who should the project manager onboard to assist with the requirements traceability matrix or analysis?

Options:

A.

Systems analyst

B.

Business analyst

C.

Project sponsor

D.

Technical consultant

Buy Now
Question # 120

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

Options:

A.

Limited

B.

Low to moderate

C.

Moderate to high

D.

High to almost total

Buy Now
Question # 121

A business case is being assembled. Which two elements are necessary to complete this process? (Choose two)

Options:

A.

Project management plan

B.

Product roadmap

C.

Requirements traceability matrix

D.

Business goals and objectives

E.

Risk register

Buy Now
Question # 122

How should a project manager plan communication for a project which has uncertain requirements?

Options:

A.

Include stakeholders in project meetings and reviews, use frequent checkpoints, and co-locate team members only.

B.

Invite customers to sprint planning and retrospective meetings, update the team quickly and on a daily basis, and use official communication channels.

C.

Adopt social networking to engage stakeholders, issue frequent and short messages, and use informal communication channels.

D.

Adopt a strong change control board process, establish focal points for main subjects, and promote formal and transparent communication.

Buy Now
Question # 123

Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?

Options:

A.

Post project artifacts in a transparent fashion and engage stakeholders on a regular basis.

B.

Make surveys among the stakeholders and meet with the team once a month.

C.

Create a social network and post news there.

D.

Create personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.

Buy Now
Question # 124

A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager. What should the project manager do to address this issue?

Options:

A.

Encourage the team to follow the project plan that was developed with team input.

B.

Apply emotional intelligence (EI) skills, such as active listening, to understand the team ' s issues.

C.

Instruct the team members to self-organize and resolve any outstanding issues.

D.

Ask the team members to record their concerns in the lessons learned log for future action.

Buy Now
Question # 125

A Project manager is failing to secure critical equipment on time, and this resulting in delays in the manufacturing of the final product. Which knowledge area is the project manager handling?

Options:

A.

Project Resource Management

B.

Project Quality Management

C.

Project Schedule Management

D.

Project integration Management

Buy Now
Question # 126

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

Options:

A.

Two

B.

Four

C.

Five

D.

Twelve

Buy Now
Question # 127

An input to the Plan Cost Management process is:

Options:

A.

Cost estimates.

B.

Resource calendars,

C.

The project charter,

D.

The risk register.

Buy Now
Question # 128

The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?

Options:

A.

Co-location

B.

Lite-cycle

C.

Diversity

D.

Management

Buy Now
Question # 129

What is the total float of the critical path?

Options:

A.

Can be any number

B.

Zero or positive

C.

Zero or negative

D.

Depends on the calendar

Buy Now
Question # 130

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

Options:

A.

Interactive

B.

Push

C.

Verbal

D.

Oral

Buy Now
Question # 131

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Buy Now
Question # 132

Which tool or technique is used to develop the human resource management plan?

Options:

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Buy Now
Question # 133

Which three of the following are the most widely used techniques that a business analyst should implement to gather requirements? (Choose three)

Options:

A.

Current state analysis

B.

Facilitated workshops

C.

Scheduled interviews

D.

Shop floor observation

E.

Brainstorming sessions

Buy Now
Question # 134

Which technique is utilized in the Control Schedule process?

Options:

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Buy Now
Question # 135

Technical capability, past performance, and intellectual property rights are examples of:

Options:

A.

performance measurement criteria

B.

source selection criteria

C.

product acceptance criteria

D.

phase exit criteria

Buy Now
Question # 136

The risk shared between the buyer and seller is determined by the:

Options:

A.

assumption log.

B.

quality checklist.

C.

risk register.

D.

contract type.

Buy Now
Question # 137

What benefit does the Manage Stakeholder Engagement process offer?

Options:

A.

Allows the project manager to increase support and minimize resistance from stakeholders

B.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes

C.

Provides an actionable plan to interact effectively with stakeholders

D.

Enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders

Buy Now
Question # 138

The purpose of inspection in Perform Quality Control is to keep errors:

Options:

A.

in line with a measured degree of conformity.

B.

out of the hands of the customer.

C.

in a specified range of acceptable results.

D.

out of the process.

Buy Now
Question # 139

When presenting a product roadmap to an adaptive team, which form of communication is the most appropriate?

Options:

A.

Requirements matrix

B.

Presentation slides

C.

Story map

D.

Project management plan

Buy Now
Question # 140

In agile projects while performing scope management. What is the definition of requirements

Options:

A.

Metrics

B.

Sprint

C.

Charter

D.

Backlog i

Buy Now
Question # 141

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (TandM).

Buy Now
Question # 142

Which of the following lists of tools and techniques is used when conducting procurements?

Options:

A.

Expert judgement, procurement negotiations, bidder conferences, proposal evaluation advertising and independent estimates

B.

Budgeting procurement negotiations, bidder conferences, proposal evaluation and advertising, and seller ' s proposal C. Expert judgement, procurement negotiations bidder conferences, proposal evaluation and advertising, and make-or-buy decisions

C.

Agreements procurement negotiations, bidder conferences, proposal evaluation and advertising selected seller

Buy Now
Question # 143

A project manager is preparing a monthly status report for the project, which includes project performance compared to the baseline schedule. How can the project manager calculate the schedule variance (SV) for tasks on the critical path?

Options:

A.

Earned Schedule + Actual Time

B.

Actual Time - Earned Schedule

C.

Planned Value - Earned Value

D.

Earned Value - Planned Value

Buy Now
Question # 144

A project manager was assigned to a project to implement a manufacturing system in a food factory. The main project objective is to deliver machines that are ready to process food. The project manager decides that this particular project does not require the use of timeboxed iterations.

Which method should the project manager adopt?

Options:

A.

SAFe®

B.

Kanban

C.

Feature-driven development (FDD)

D.

Scrum

Buy Now
Question # 145

How is program success measured?

Options:

A.

By delivering the benefit of managing the program ' s projects in a coordinated manner

B.

By the quality, timeliness, cost-effectiveness, and customer satisfaction of the product or service

C.

By completing the right projects to achieve objectives rather than completing projects the right way

D.

By aggregating the successes of the individual projects in the program

Buy Now
Question # 146

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

Options:

A.

adaptive

B.

reflexive

C.

predictive

D.

iterative

Buy Now
Question # 147

A new game development process must have three versions. Each version is to be developed in approximately five iteration cycles with a duration of one month each. This will help this small enterprise to have a return on investment (ROI) as the project runs from the first cycle. Which methodology should the project manager adopt and implement in the project?

Options:

A.

Feature-driven development (FDD) as it will deliver product segments and the milestones are controlled by the development manager.

B.

Kanban as it will provide flexibility to the team for working at their own pace in the time frame requested.

C.

Scrum as it uses sprints and retrospectives, maximizing time delivery and the value of the product.

D.

Extreme Programming (XP) as it will help deliver more quickly since developers will work in pairs.

Buy Now
Question # 148

As the project progresses, which of the following is routinely collected from the project activities?

Options:

A.

Communication management activities

B.

Change requests

C.

Configuration verification and audit

D.

Work performance information

Buy Now
Question # 149

What can a requirements traceability matrix enable regardless of the project methodology being used?

Options:

A.

Creation of a solid business case

B.

Investigation of the viability of a new product

C.

Identification of missing and superfluous requirements

D.

Evaluation of solution and system performance

Buy Now
Question # 150

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

Options:

A.

influencing

B.

leadership

C.

motivation

D.

coaching

Buy Now
Question # 151

What can increase the complexity of the Manage Stakeholder Engagement process?

Options:

A.

The project must be of high quality.

B.

The stakeholders are from different countries.

C.

The project must comply with strict local government regulations.

D.

The project has a tight budget and timeline.

Buy Now
Question # 152

What does earned value (EV) measure?

Options:

A.

Budgeted work that has been completed

B.

Total costs incurred while accomplishing work

C.

Budget associated with planned work

D.

Cost efficiency of budgeted resources

Buy Now
Question # 153

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

Options:

A.

Slack

B.

Float

C.

Lag

D.

Lead

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Jul 5, 2026
Questions: 1326
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99