Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 104

Which tasks should a project manager perform in order to manage the project schedule effectively?

Options:

A.

Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities. Develop Schedule

B.

Plan Schedule Management. Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule. Control Schedule

C.

Plan Schedule Management. Define Activities, Sequence Activities, Estimate Activity Durations, Estimate Cost of Activities. Develop Schedule

D.

Define Activities. Sequence Activities, Estimate Activity Durations. Define Quality of Activities. Estimate Cost of Activities, Develop Schedule

Buy Now
Question # 105

Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?

Options:

A.

Project

B.

Functional

C.

Program

D.

Portfolio

Buy Now
Question # 106

An output of the Create WBS process is:

Options:

A.

Scope baseline.

B.

Project scope statement.

C.

Organizational process assets.

D.

Requirements traceability matrix.

Buy Now
Question # 107

How should the project manager obtain the maximum engagement from stakeholders that have recently changed to become more connected to social media?

Options:

A.

Adopt co-creation, sharing responsibilities with stakeholders

B.

Adopt participation of stakeholders in main meetings, listening to their opinion.

C.

Adopt social media tools, improving communication with stakeholders

D.

Adopt involvement of stakeholders in lessons learned sessions, sharing experiences with them

Buy Now
Question # 108

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

Options:

A.

Benchmarking.

B.

Context diagrams.

C.

Brainstorming.

D.

Prototyping.

Buy Now
Question # 109

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Options:

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Buy Now
Question # 110

During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three)

Options:

A.

End user

B.

Product owner

C.

Subject matter experts (SMEs)

D.

Project sponsor

E.

Project team

Buy Now
Question # 111

Who identifies project requirements in the early phase of the project?

Options:

A.

Business analyst, product team, and key stakeholders

B.

Project manager, business analyst, and key stakeholders

C.

Project manager, business analyst, and project sponsor

D.

Project sponsor, business analyst, and key stakeholders

Buy Now
Question # 112

A company is moving from a predictive to an adaptive approach. How should the company now translate the already planned work breakdown structure (WBS) to adaptive iterations?

Options:

A.

Create a product backlog with the information depicted in the WBS and prioritize the newly developed user stories into iterations.

B.

Accept this limitation and perform accordingly since the WBS can only be used in Scrum iterations.

C.

Consider reforming the structure of the company first as it is difficult for a company to transition from predictive to adaptive methods.

D.

Save the WBS in the historical data as the information can only be used for educational purposes and not as inputs for creating user stories.

Buy Now
Question # 113

Which technique is used in Perform Quantitative Risk Analysis?

Options:

A.

Sensitivity analysis

B.

Probability and impact matrix

C.

Risk data quality assessment

D.

Risk categorization

Buy Now
Question # 114

Which of the following is an output of the Conduct Procurements process?

Options:

A.

Project statement of work

B.

Selected sellers

C.

Risk register updates

D.

Teaming agreements

Buy Now
Question # 115

A project management office manages a number of aspects including the:

Options:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Buy Now
Question # 116

Project management processes ensure the:

Options:

A.

alignment with organizational strategy

B.

efficient means to achieve the project objectives

C.

performance of the project team

D.

effective flow of the project throughout its life cycle

Buy Now
Question # 117

A tool and technique used during the Collect Requirements process is:

Options:

A.

prototypes.

B.

expert judgment.

C.

alternatives identification.

D.

product analysis.

Buy Now
Question # 118

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

Options:

A.

Compromising

B.

Collaborating

C.

Smoothing

D.

Problem Solving

Buy Now
Question # 119

Project contracts generally fall into which of the following three broad categories?

Options:

A.

Fixed-price, cost reimbursable, time and materials

B.

Make-or-buy, margin analysis, fixed-price

C.

Time and materials, fixed-price, margin analysis

D.

Make-or-buy, lump-sum, cost-plus-incentive

Buy Now
Question # 120

Which kind of communication should the project manager use when creating reports for government bodies?

Options:

A.

Hierarchical

B.

External

C.

Formal

D.

Official

Buy Now
Question # 121

A weighting system is a tool for which area of Conduct Procurements?

Options:

A.

Plan contracting

B.

Requesting seller responses

C.

Selecting seller ' s

D.

Planning purchase and acquisition

Buy Now
Question # 122

Given the following information.

Activity A takes one week.

Activity B takes three weeks.

Activity C takes two weeks.

Activity D takes five weeks.

Activity A starts at the same time as Activity B.

Activity C follows Activity B and Activity A.

Activity D follows Activity C.

How long will it take to complete the project?

Options:

A.

Eleven weeks

B.

Nine weeks

C.

Eight weeks

D.

Ten weeks

Buy Now
Question # 123

What are the two most common contract types used in a project?

Options:

A.

Cost plus award fee (CPAF) contract and fixed price contract

B.

Fixed price contract and cost-reimbursable contract

C.

Cost-reimbursable contract and time and material (TandM) contract

D.

Time and material (TandM) contract and cost plus award fee (CPAF) contract

Buy Now
Question # 124

Under which circumstances should multiple projects be grouped in a program?

Options:

A.

When they are needed to accomplish a set of goals and objectives for an organization

B.

When they have the same project manager and the same organizational unit

C.

When they have the same scope, budget, and schedule

D.

When they are from the same unit of the organization

Buy Now
Question # 125

Which of the following is a tool and technique used to monitor risk?

Options:

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Buy Now
Question # 126

Which of the following is a tool or technique used in the Acquire Project Team process?

Options:

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

Buy Now
Question # 127

A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?

Options:

A.

Informal

B.

Unofficial

C.

Formal

D.

Hierarchical

Buy Now
Question # 128

In an interactive communication model, how is the sender ensured that the message was understood by the receiver?

Options:

A.

The receiver decodes the message

B.

The receiver responds to the message with feedback.

C.

The receiver transmits the message

D.

The receiver acknowledges their receipt of the message

Buy Now
Question # 129

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

Options:

A.

Collect Requirements.

B.

Conduct Procurements.

C.

Estimate Activity Durations.

D.

Estimate Activity Resources.

Buy Now
Question # 130

An input to the Estimate Activity Resources process is:

Options:

A.

Activity resource requirements.

B.

Published estimating data.

C.

Resource calendars.

D.

Resource breakdown structure (RBS).

Buy Now
Question # 131

Which item is a cost of conformance?

Options:

A.

Training

B.

Liabilities

C.

Lost business

D.

Scrap

Buy Now
Question # 132

Which process determines the risks that might affect the project?

Options:

A.

Perform Qualitative Risk Analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Buy Now
Question # 133

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

Options:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

Buy Now
Question # 134

Which action should the project manager take after the team finishes executing the scope?

Options:

A.

Verify the deliverables to ensure that they are correct and meet the customer ' s satisfaction.

B.

Accept all the deliverables and deliver them to the customer for final acceptance.

C.

Conduct a joint session with the customer, change the deliverables, and then request approval.

D.

Check that all change requests were implemented and release deliverables to the customer.

Buy Now
Question # 135

Which of the following is an information gathering technique in Identify Risks?

Options:

A.

Influence diagrams

B.

Brainstorming

C.

Assumption analysis

D.

SWOT analysis

Buy Now
Question # 136

Which of the following is a group decision-making technique?

Options:

A.

Brainstorming

B.

Focus groups

C.

Affinity diagram

D.

Plurality

Buy Now
Question # 137

What are the Project Procurement Management processes?

Options:

A.

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements

B.

Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements

C.

Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements

D.

Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Buy Now
Question # 138

According to the PMI Talent Triangle. leadership skills relate to the ability to:

Options:

A.

understand the high-level overview of the organization

B.

tailor traditional and agile tools for the project

C.

work with stakeholders to develop an appropriate project delivery

D.

guide, motivate, and direct a team to reach project goals

Buy Now
Question # 139

A project manager is performing the procurement management process with three vendors The project team is reviewing the requests for proposal (RFPs).

What type of procurement document is the RFP?

Options:

A.

Bid document

B.

Statement of work (SOW)

C.

Source selection criteria

D.

Independent cost estimate

Buy Now
Question # 140

The stakeholder register is an output of:

Options:

A.

Identify Stakeholders.

B.

Plan Stakeholder Management.

C.

Control Stakeholder Engagement.

D.

Manage Stakeholder Engagement.

Buy Now
Question # 141

When the business objectives of an organization change, project goals need to be:

Options:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

Buy Now
Question # 142

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

Options:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

Buy Now
Question # 143

A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract Is this?

Options:

A.

Time and material (T8M)

B.

Fixed price incentive fee (FPIF)

C.

Cost plus fixed fee (CPFF)

D.

Cost plus award fee (CPAF)

Buy Now
Question # 144

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

Options:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Buy Now
Question # 145

In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?

Options:

A.

Ensures a thorough unit test case coverage

B.

Ensures an accurate reflection of the stakeholders ' intentions

C.

Ensures that the business problem is solved

D.

Ensures the successful delivery of business value

Buy Now
Question # 146

The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?

Options:

A.

Technical project management skills

B.

Time management skills

C.

Strategic and business management skills

D.

Leadership skills

Buy Now
Question # 147

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (TandM).

Buy Now
Question # 148

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options:

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

Buy Now
Question # 149

In the Plan Stakeholder Management process, expert judgment is used to:

Options:

A.

Provide information needed to plan appropriate ways to engage project stakeholders.

B.

Ensure comprehensive identification and listing of new stakeholders.

C.

Analyze the information needed to develop the project scope statement.

D.

Decide the level of engagement of the stakeholders at each required stage.

Buy Now
Question # 150

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

Options:

A.

Expert judgment.

B.

Analytical techniques.

C.

Earned value management.

D.

Group decision-making techniques.

Buy Now
Question # 151

Inputs to the Plan Schedule Management process include:

Options:

A.

Organizational process assets and the project charter,

B.

Enterprise environmental factors and schedule tools.

C.

Time tables and Pareto diagrams.

D.

Activity attributes and resource calendars.

Buy Now
Question # 152

The activity tailoring is necessary because:

Options:

A.

the members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide, this is required for all projects

B.

each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide

C.

the members of the project team need to understand the PMBOK Guide processes, which are applied to all projects

D.

each project is unique, and the project team must plain how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide

Buy Now
Question # 153

Which organizational process assets update is performed during the Close Procurements process?

Options:

A.

Procurement audit

B.

Lessons learned

C.

Performance reporting

D.

Payment requests

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: May 21, 2026
Questions: 1320
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99