Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 354

Which document describes the necessary information to determine if a project is worth the required investment?

Options:

A.

Cost baseline

B.

Service level agreement

C.

Memorandum of understanding

D.

Business case

Buy Now
Question # 355

An example of a group decision-ma king technique is:

Options:

A.

Nominal group technique.

B.

Majority.

C.

Affinity diagram.

D.

Multi-criteria decision analysis.

Buy Now
Question # 356

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

Options:

A.

Work performance information.

B.

Inspections and audits.

C.

Payment systems.

D.

Procurement performance reviews.

Buy Now
Question # 357

An input to the Plan Stakeholder Management process is:

Options:

A.

The project charter.

B.

The stakeholder analysis.

C.

A communication management plan.

D.

A stakeholder register.

Buy Now
Question # 358

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

Options:

A.

Direct and Manage Project Work

B.

Develop Project Management Plan

C.

Plan Quality Management

D.

Monitor and Control Project Work

Buy Now
Question # 359

Typical outcomes of a project include:

Options:

A.

Products, services, and improvements.

B.

Products, programs, and services.

C.

Improvements, portfolios, and services.

D.

Improvements, processes, and products.

Buy Now
Question # 360

An input to Conduct Procurements is:

Options:

A.

Independent estimates.

B.

Selected sellers.

C.

Seller proposals.

D.

Resource calendars.

Buy Now
Question # 361

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

Options:

A.

Mandatory

B.

Discretionary

C.

Internal

D.

External

Buy Now
Question # 362

An element of the project scope statement is:

Options:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

Buy Now
Question # 363

Reserve analysis is a tool and technique used in which process?

Options:

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Identify Risks

D.

Control Risks

Buy Now
Question # 364

Scope, schedule, and cost parameters are integrated in the:

Options:

A.

Performance measurement baseline.

B.

Analysis of project forecasts,

C.

Summary of changes approved in a period,

D.

Analysis of past performance.

Buy Now
Question # 365

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Buy Now
Question # 366

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

Options:

A.

Develop Project Team.

B.

Manage Project Team.

C.

Acquire Project Team.

D.

Plan Human Resource Management.

Buy Now
Question # 367

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

Options:

A.

Urgent information need

B.

Sensitivity of information

C.

Project environment

D.

Ease of use

Buy Now
Question # 368

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

Options:

A.

Develop Schedule

B.

Create VVBS

C.

Estimate Activity Resources

D.

Define Scope

Buy Now
Question # 369

Organizational theory is a tool used in which Project Human Resource Management process?

Options:

A.

Manage Project Team

B.

Acquire Project Team

C.

Develop Project Team

D.

Plan Human Resource Management

Buy Now
Question # 370

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Options:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Buy Now
Question # 371

An input to the Manage Project Team process is:

Options:

A.

Work performance reports.

B.

Change requests.

C.

Activity resource requirements.

D.

Enterprise environmental factors.

Buy Now
Question # 372

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

Options:

A.

Work breakdown structure

B.

Requirements document

C.

Project charter

D.

Project management plan

Buy Now
Question # 373

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

Options:

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Buy Now
Question # 374

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

Options:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs

Buy Now
Question # 375

Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

Options:

A.

Influence/impact grid

B.

Power/influence grid

C.

Power/interest grid

D.

Salience model

Buy Now
Question # 376

Project Stakeholder Management focuses on:

Options:

A.

project staff assignments

B.

project tea m acquisition

C.

managing conflicting interests

D.

communication methods

Buy Now
Question # 377

Which project document is updated in the Control Stakeholder Engagement process?

Options:

A.

Project reports

B.

Issue log

C.

Lessons learned documentation

D.

Work performance information

Buy Now
Question # 378

Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

Options:

A.

Control chart

B.

Flowchart

C.

Checksheet

D.

Pareto diagram

Buy Now
Question # 379

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

Options:

A.

Earned value management.

B.

Forecasting.

C.

Critical chain methodology.

D.

Critical path methodology.

Buy Now
Question # 380

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

Options:

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

Buy Now
Question # 381

Which output is the approved version of the time-phased project budget?

Options:

A.

Resource calendar

B.

Scope baseline

C.

Trend analysis

D.

Cost baseline

Buy Now
Question # 382

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

Options:

A.

Strong

B.

Weak

C.

Managed

D.

Balanced

Buy Now
Question # 383

A project manager should communicate to stakeholders about resolved project issues by updating the:

Options:

A.

project records

B.

project reports

C.

stakeholder notifications

D.

stakeholder register

Buy Now
Question # 384

Variance and trend analysis is a tool and technique used in which process?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Control Risks

D.

Plan Risk Responses

Buy Now
Question # 385

In the Define Activities process, the schedule management plan is used to:

Options:

A.

Capture the lessons learned from other projects for comparison.

B.

Contain the standard activity list.

C.

Document and support the project change requests.

D.

Prescribe the level of detail needed to manage the work.

Buy Now
Question # 386

A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

Options:

A.

Plan Stakeholder Management

B.

Identify Stakeholders

C.

Manage Stakeholder Engagement

D.

Control Stakeholder Engagement

Buy Now
Question # 387

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

Options:

A.

Continuous

B.

Discrete

C.

Regulated

D.

Arbitrary

Buy Now
Question # 388

The following is a network diagram for a project.

What is the critical path for the project?

Options:

A.

A-B-D-G

B.

A-B-E-G

C.

A-C-F-G

D.

A-C-E-G

Buy Now
Question # 389

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Question # 390

Which action is included in the Control Costs process?

Options:

A.

Identify how the project costs will be planned, structured, and controlled

B.

Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.

Develop an approximation of the monetary resources needed to complete project activities

D.

Monitor cost performance to isolate and understand variances from the approved cost baseline

Buy Now
Question # 391

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

Options:

A.

Update

B.

Preventive action

C.

Defect repair

D.

Corrective action

Buy Now
Question # 392

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

Options:

A.

Salience

B.

Influence/impact

C.

Power/interest

D.

Power/influence

Buy Now
Question # 393

Which stakeholder approves a project's result?

Options:

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Buy Now
Question # 394

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

Options:

A.

100

B.

120

C.

1,000

D.

1,200

Buy Now
Question # 395

The zero duration of milestones in project planning occurs because milestones:

Options:

A.

Are unpredictable and challenge the Plan Schedule Management process.

B.

Occur at random times in the project plans.

C.

Represent a moment in time such as a significant project point or event.

D.

Represent both significant and insignificant points in the project and are difficult to anticipate.

Buy Now
Question # 396

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

Options:

A.

0.03

B.

0.06

C.

0.10

D.

0.50

Buy Now
Question # 397

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?

Options:

A.

0.83

B.

0.9

C.

1.11

D.

1.33

Buy Now
Question # 398

Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

Options:

A.

Available organizational assets

B.

Project staff assignments

C.

Interpersonal skills

D.

Enterprise environmental factors

Buy Now
Question # 399

The following is a network diagram for a project.

The total float for the project is how many days?

Options:

A.

3

B.

5

C.

7

D.

9

Buy Now
Question # 400

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Options:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

Buy Now
Question # 401

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

Options:

A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

Buy Now
Question # 402

The following is a network diagram for a project.

The total float for the project is how many days?

Options:

A.

5

B.

9

C.

12

D.

14

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Aug 22, 2025
Questions: 1330
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99