Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 354

What is the responsibility of the project manager and the functional manager respectively?

Options:

A.

Oversight for an administrative area; a facet of the core business

B.

Achieving the project objectives; providing management oversight for an administrative area

C.

A facet of the core business; achieving the project objectives

D.

Both are responsible for achieving the project objectives.

Buy Now
Question # 355

Which is an example of analogous estimating?

Options:

A.

Estimates are created by individuals or groups with specialized knowledge.

B.

Estimates are created by using information about resources of previous similar projects.

C.

Estimates are created by analyzing data.

D.

Estimates are created at the task level and aggregated upwards.

Buy Now
Question # 356

What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?

Options:

A.

Project Management

B.

Program Management

C.

Portfolio Management

D.

Operations Management

Buy Now
Question # 357

The risk shared between the buyer and seller is determined by the:

Options:

A.

assumption log.

B.

quality checklist.

C.

risk register.

D.

contract type.

Buy Now
Question # 358

A quality management plan describes how the project and product scopes are managed in accordance with which of the following items?

Options:

A.

Product sponsor ' s expectation of organizational quality

B.

Historical quality standards and past organizational projects

C.

Organizational quality policies, stakeholder expectations, and historical data

D.

Organizational quality policies, standards, and methodologies

Buy Now
Question # 359

What tool or technique is used in the Collect Requirements process?

Options:

A.

Inspection

B.

Decomposition

C.

Product analysis

D.

Prototypes

Buy Now
Question # 360

Which process involves determining, documenting, and managing stakeholders ' needs and requirements to meet project objectives?

Options:

A.

Collect Requirements

B.

Plan Scope Management

C.

Define Scope

D.

Define Activities

Buy Now
Question # 361

Which set of tools and techniques is useful for estimating activity durations for the project schedule?

Options:

A.

Brainstorming, Monte Carlo simulation, analogous estimation

B.

Three-point estimation, resources leveling, iteration burndown chart

C.

Milestone charts, parametric estimation, schedule baseline

D.

Parametric estimation, three-point estimation, meetings

Buy Now
Question # 362

" Tailoring " is defined as the:

Options:

A.

effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.

B.

act of creating a project team with the specialized skills required to produce a required product or service.

C.

action taken to bring a defective or nonconforming component into compliance with requirements or specifications.

D.

adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.

Buy Now
Question # 363

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost

Options:

A.

High-level deliverables

B.

Success criteria

C.

Project objectives

D.

Phase transitions

Buy Now
Question # 364

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

Options:

A.

Change request

B.

Risk response

C.

Risk management plan

D.

Lessons learned

Buy Now
Question # 365

As the project takes place and some issues arose, the project manager (Joe) finds out that some team members were not 100% committed to the project, and some of them were underperforming.

What should the project manager have done to avoid this situation?

Options:

A.

Coupled inexperienced team members with individuals having extensive knowledge in the required field

B.

Had open and transparent planning that engages internal and external stakeholders

C.

Held regular meetings more often with team members to check on their progress and obstacles

D.

Diversified more of the project team to capture a broad range of experiences

Buy Now
Question # 366

A project veers off track due to scope creep. The project management team requests an immediate response from the major stakeholders.

What should the project manager do next to avoid project failure?

Options:

A.

Adopt a change management approach and delay the project to decide on the direction.

B.

Develop a focus group to face the issue and decide on the appropriate direction.

C.

Request a meeting with top management to state concerns about their ability to handle the situation.

D.

Delay the project by adopting a fast-fail approach, mitigating the risk of having a bigger impact on the company.

Buy Now
Question # 367

A newly developed project team is working together, building trust and adjusting its work habits to support the team What stage of the Tuckman ladder does this describe?

Options:

A.

Forming

B.

Norming

C.

Storming

D.

Performing

Buy Now
Question # 368

Which item is an input to the Define Activities process?

Options:

A.

Schedule data

B.

Activity list

C.

Risk register

D.

Scope baseline

Buy Now
Question # 369

An adaptive project manager is handling a five-sprint cycle to deliver a minimum viable product (MVP). After the third sprint, the productivity of the team drops to 30% due to a change in the way the team operates.

Which of the following changes has caused this loss in productivity?

Options:

A.

Two of the team members have been working in silos using different methods to validate their performance.

B.

The team velocity was measured in the third sprint since the tool to measure velocity was introduced only in the third sprint.

C.

The team picked up technical debt items in the third sprint as technical debt can only be picked up after completing two sprints.

D.

Two of the team members were asked to do multitasking, which they did not do in the previous two sprints.

Buy Now
Question # 370

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Options:

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Buy Now
Question # 371

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

Options:

A.

Bottom-up

B.

Three-point

C.

Parametric

D.

Analogous

Buy Now
Question # 372

What is the Project Schedule Management practice used to deliver incremental value to the customer ' ?

Options:

A.

Resource optimization

B.

Iterative scheduling with a backlog

C.

On-demand scheduling

D.

Critical path method

Buy Now
Question # 373

When planning communications management what input identifies key stakeholders?

Options:

A.

Work performance information

B.

Project schedule

C.

Project charter

D.

Work performance reports

Buy Now
Question # 374

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

Options:

A.

portfolio

B.

program

C.

selection

D.

sub portfolio

Buy Now
Question # 375

Plan Schedule Management is a process in which Knowledge Area?

Options:

A.

Project Scope Management

B.

Project Human Resource Management

C.

Project Integration Management

D.

Project Time Management

Buy Now
Question # 376

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

Options:

A.

Acquire Resources

B.

Control Resources

C.

Manage Team

D.

Develop Team

Buy Now
Question # 377

Which piece of information is part of the WBS Dictionary?

Options:

A.

Responsible organization

B.

Change requests

C.

Validated deliverables

D.

Organizational process assets

Buy Now
Question # 378

What tools or techniques are necessary to create the project management plan?

Options:

A.

Meetings and data analysis

B.

Expert judgment and data gathering

C.

Interpersonal skills and change control

D.

Data analysis and expert judgment

Buy Now
Question # 379

What is the project manager ' s responsibility in Project Integration Management?

Options:

A.

Ensuring that requirements-related work is clarified in the project management plan

B.

Investing sufficient effort in acquiring, managing, motivating, and empowering the project team

C.

Combining the results in all other knowledge areas, and overseeing the project as a whole

D.

Developing a strategy to ensure effective stakeholder communication

Buy Now
Question # 380

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

Options:

A.

100

B.

120

C.

1,000

D.

1,200

Buy Now
Question # 381

While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.

What should the team do to ensure that this situation is managed?

Options:

A.

Implement Appropriate Response

B.

Plan Project Risk Management

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Buy Now
Question # 382

When would resource leveling be applied to a schedule model?

Options:

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Buy Now
Question # 383

Which process should be conducted from the project inception through completion?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Buy Now
Question # 384

Which of the following change requests can bring expected future performance of the project work in line with the project management plan?

Options:

A.

Corrective action

B.

Defect repair

C.

Preventative action

D.

Probable action

Buy Now
Question # 385

During which process group is the quality policy determined?

Options:

A.

Initiating

B.

Executing

C.

Planning

D.

Controlling

Buy Now
Question # 386

Which of the following statements is true regarding project and product lifecycles?

Options:

A.

A single product lifecycle may consist of multiple project lifecycles.

B.

A product lifecycle is always shorter than the project lifecycle.

C.

A single product lifecycle can only have one project lifecycle.

D.

A single project lifecycle may consist of multiple product lifecycles.

Buy Now
Question # 387

Which of the following projects is a quality candidate for adaptive approaches?

Options:

A.

Installing new computers across offices

B.

Retrofitting an old building

C.

Upgrading an information system

D.

Designing a new suspension bridge

Buy Now
Question # 388

In project management, which document is used to start the initial risk identification?

Options:

A.

Assumption log

B.

Risk management plan

C.

Risk register

D.

Issue log

Buy Now
Question # 389

Which scenario is most desirable during the execution phase of a project?

Options:

A.

Apply and use quality controls to ensure expectations are met throughout the project

B.

Communicate quality failures to the sponsor for feedback

C.

Conduct all quality inspections at the end of the project

D.

Only correct quality issues found if it will keep you within the budget

Buy Now
Question # 390

Which action should a project manager take to ensure that the project management plan is effective and current?

Options:

A.

Conduct periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards.

D.

Complete the quality control checklist.

Buy Now
Question # 391

A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the project?

Options:

A.

Predictive

B.

Hybrid

C.

Kanban

D.

Adaptive

Buy Now
Question # 392

What is the equation to calculate cost variance (CV)?

Options:

A.

CV = EV / BAC

B.

CV = EV - AC

C.

CV = EV - BAC

D.

CV = EV / AC

Buy Now
Question # 393

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take to account for risk management n this environment’

Options:

A.

Occasionally identify evaluate, and classify risks

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Buy Now
Question # 394

A disadvantage associated with virtual teams is that they:

Options:

A.

Require communication technology that is not readily available.

B.

Create difficulties when including people with disabilities.

C.

Often cannot accommodate teams that work different hours or shifts.

D.

Create the possibility for misunderstandings to arise.

Buy Now
Question # 395

What benefit does the Manage Stakeholder Engagement process offer?

Options:

A.

Allows the project manager to increase support and minimize resistance from stakeholders

B.

Maintains or increases the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes

C.

Provides an actionable plan to interact effectively with stakeholders

D.

Enables the project team to identify the appropriate focus for engagement of each stakeholder or group of stakeholders

Buy Now
Question # 396

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.

Which type of life cycle would the project manager use in this case?

Options:

A.

Predictive life cycle

B.

Waterfall life cycle

C.

Hybrid life cycle

D.

Product life cycle

Buy Now
Question # 397

Which is an input to the Verify Scope process?

Options:

A.

Performance report

B.

Work breakdown structure (WBS)

C.

Requested changes

D.

Project management plan

Buy Now
Question # 398

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

Options:

A.

Monitor project stakeholder relationships using engaging strategies and plans

B.

Send all project documents to stakeholders each time they are modified

C.

Schedule monthly meetings with the stakeholders, including team members

D.

Engage only with the project sponsors

Buy Now
Question # 399

One of the key benefits of the Plan Human Resource Management process is that it:

Options:

A.

outlines team selection guidelines and team member responsibilities.

B.

establishes project roles and responsibilities.

C.

improves teamwork, interpersonal skills, and competencies.

D.

provides an accurate appraisal of team member performance.

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: May 21, 2026
Questions: 1320
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99