Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 354

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

Options:

A.

Projectized

B.

Weak matrix

C.

Functional

D.

Balanced matrix

Buy Now
Question # 355

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

Options:

A.

Informal communication

B.

Internal communication

C.

Formal communication

D.

Horizontal communication

Buy Now
Question # 356

Why is required in a project?

Options:

A.

Because a one-size-fits-all approach avoids complications and saves time.

B.

Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required.

C.

Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project.

D.

Project managers should apply every process in the PMBOK Guide to the project, so failoring is not requires.

Buy Now
Question # 357

Which Process Group ' s purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

Options:

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

Buy Now
Question # 358

Which method should be used to elicit a cross-functional requirement?

Options:

A.

Focus groups

B.

Prototyping

C.

Facilitated workshops

D.

Interviews

Buy Now
Question # 359

Which of the following is an example of an internal factor that influences the outcome of the project?

Options:

A.

Legal restrictions

B.

Financial considerations

C.

Commercial database

D.

Geographic distribution of facilities

Buy Now
Question # 360

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

Options:

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

Buy Now
Question # 361

Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

Options:

A.

Work performance data

B.

Project documents

C.

Scope baseline

D.

Requirements documentation

Buy Now
Question # 362

Which items are components of a project management plan?

Options:

A.

Change management plan, process improvement plan, and scope management plan

B.

Agreements, procurement management plan, and work performance information

C.

Schedule management plan, project schedule, and resource calendars

D.

Scope baseline, project statement of work, and requirements traceability matrix

Buy Now
Question # 363

What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?

Options:

A.

Project Cost Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Schedule Management

Buy Now
Question # 364

In the Plan Stakeholder Management process, expert judgment is used to:

Options:

A.

Provide information needed to plan appropriate ways to engage project stakeholders.

B.

Ensure comprehensive identification and listing of new stakeholders.

C.

Analyze the information needed to develop the project scope statement.

D.

Decide the level of engagement of the stakeholders at each required stage.

Buy Now
Question # 365

A risk that arises as a direct result of implementing a risk response is called a:

Options:

A.

contingent risk

B.

residual risk

C.

potential risk

D.

secondary risk

Buy Now
Question # 366

External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

Options:

A.

Customers.

B.

Business partners.

C.

Sellers.

D.

Functional managers.

Buy Now
Question # 367

The project manager is creating the communications management plan Which group of inputs Is required to begin?

Options:

A.

Work performance reports, change requests, and risk register

B.

Work performance data, project documents, and stakeholder engagement plan

C.

Project charter, project management plan, and project documents

D.

Work performance data, stakeholder register, and team management plan

Buy Now
Question # 368

What is the responsibility of the project manager and the functional manager respectively?

Options:

A.

Oversight for an administrative area; a facet of the core business

B.

Achieving the project objectives; providing management oversight for an administrative area

C.

A facet of the core business; achieving the project objectives

D.

Both are responsible for achieving the project objectives.

Buy Now
Question # 369

Expected monetary value (EMV) is computed by which equation?

Options:

A.

Value of each possible outcome multiplied by probability of occurrence

B.

Value of each possible outcome multiplied by probability of non-occurrence

C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

Buy Now
Question # 370

One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

Options:

A.

It represents how and when the project will deliver the products, services, and results defined in the project scope

B.

It creates a formal record of the project and shows the organizational commitment to the project

C.

It describes how the scope will be defined, developed, monitored, controlled and validated

D.

It provides the needs of a stakeholder or stakeholder group

Buy Now
Question # 371

During project execution, a key resource leaves the team for another job. What should the project manager do in this situation?

Options:

A.

Submit a change request for additional budget to secure a project resource.

B.

Consult with the functional manager for a replacement resource.

C.

Distribute work to other team members to reduce impact to the project schedule.

D.

Consult the risk register for an appropriate risk response.

Buy Now
Question # 372

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

Options:

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope

Buy Now
Question # 373

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

Options:

A.

Identify Risks

B.

Control Risks

C.

Plan Risk Management

D.

Plan Risk Responses

Buy Now
Question # 374

Which tool or technique is used in Close Procurements?

Options:

A.

Contract plan

B.

Procurement plan

C.

Closure process

D.

Procurement audits

Buy Now
Question # 375

An input required in Define Scope is an organizational:

Options:

A.

structure.

B.

process asset.

C.

matrix.

D.

breakdown structure.

Buy Now
Question # 376

Which of the following are outputs of define scope process in project scope management

Options:

A.

Requirements documentation and requirements traceability matrix

B.

Scope management plan and requirements management plan

C.

Project Scope statement and project documents updates

D.

Scope baseline and project documents updates

Buy Now
Question # 377

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

Options:

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

Buy Now
Question # 378

A project manager is working with the team to prepare the estimates for various work items. The team needs to compare the relative sizing of the items. What should the project manager suggest the team use?

Options:

A.

Project task estimation

B.

Dependency planning

C.

Story point estimation

D.

Sprint planning

Buy Now
Question # 379

Which is the communication method used in the Report Performance process?

Options:

A.

Expert judgment

B.

Project management methodology

C.

Stakeholder analysis

D.

Status review meetings

Buy Now
Question # 380

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

Options:

A.

enterprise environmental factors.

B.

organizational process assets.

C.

project management plan,

D.

project funding requirements.

Buy Now
Question # 381

What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?

Options:

A.

Expert judgment

B.

Interpersonal skills

C.

Team agreements

D.

Communication skills

Buy Now
Question # 382

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

Options:

A.

Collect Requirements.

B.

Conduct Procurements.

C.

Estimate Activity Durations.

D.

Estimate Activity Resources.

Buy Now
Question # 383

Which project risk listed in the table below is most likely to occur?

Options:

A.

1

B.

2

C.

3

D.

4

Buy Now
Question # 384

Which component of the project management plan should be updated if a change occurs?

Options:

A.

Project charter

B.

Project baseline

C.

Assumption log

D.

Schedule forecast

Buy Now
Question # 385

How can a project manager evaluate project team development?

Options:

A.

Produce team performance assessments.

B.

Hold weekly meetings to engage every member

C.

Complete a personal skill assessment on each team member

D.

Provide recognition awards to team members

Buy Now
Question # 386

The progressive detailing of the project management plan is called:

Options:

A.

expert judgment.

B.

rolling wave planning.

C.

work performance information.

D.

specification.

Buy Now
Question # 387

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

Options:

A.

Cost management plan

B.

Quality management plan

C.

Communications management plan

D.

Risk management plan

Buy Now
Question # 388

A project manager should document the escalation path for unresolved project risks in the:

Options:

A.

Change control plan

B.

Stakeholder register

C.

Risk log

D.

Communications management plan

Buy Now
Question # 389

What do top project managers do to maximize their sphere of influence within a project team?

Options:

A.

Consider management standards, economic factors, and sustainability strategies

B.

Contribute knowledge and expertise to others within the profession

C.

C Address political and strategic issues that impact the project ' s viability or quality

D.

D Demonstrate superior relationship and communication skills while displaying a positive attitude

Buy Now
Question # 390

During the requirements verification process, stakeholders are finding many errors in the requirements definition. What could the business analyst have done to avoid these errors?

Options:

A.

Asked the stakeholders to write the requirements themselves

B.

Included the project manager in the elicitation sessions

C.

Confirmed the elicitation results after sessions

D.

Updated the requirements traceability matrix

Buy Now
Question # 391

The project team of a predictive project is following the requirements traceability matrix to ensure the deliverables align with customer expectations. If the project had been an adaptive project, the project team would use a different artifact to ensure the deliverables align with customer expectations. What should the project team use in an adaptive project?

Options:

A.

Business case

B.

Product backlog

C.

Milestone list

D.

Product management plan

Buy Now
Question # 392

In the Control Quality process, which tools and techniques can be applied to verify deliverable?

Options:

A.

Statistical sampling, inspection, and meetings

B.

Lessons learned register, control charts, and product evaluation

C.

Checklists, retrospective documents, and approved change requests

D.

Black box tests, questionnaires and surveys, and lessons learned register

Buy Now
Question # 393

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

Options:

A.

Plan Risk Responses

B.

Manage Stakeholder Expectations

C.

Define Scope

D.

Report Performance

Buy Now
Question # 394

A project manager is reviewing a few techniques that can be used to evaluate solution results. The intent is to uncover whether the solution responds properly to unintended cases.

Which evaluation technique should be used here?

Options:

A.

Exploratory testing

B.

Integration testing

C.

User acceptance testing

D.

Day-in-the-life testing

Buy Now
Question # 395

What provides information regarding the ways people, teams, and organizational units behave?

Options:

A.

Organizational chart

B.

Organizational theory

C.

Organizational structure

D.

Organizational behavior

Buy Now
Question # 396

A project team member is estimating the cost of activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

Options:

A.

Bottom-up estimating

B.

Three-point estimating

C.

Analogous estimating

D.

Parametric estimating

Buy Now
Question # 397

During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three)

Options:

A.

End user

B.

Product owner

C.

Subject matter experts (SMEs)

D.

Project sponsor

E.

Project team

Buy Now
Question # 398

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

Options:

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Buy Now
Question # 399

When is a Salience Model used?

Options:

A.

In a work breakdown structure (WBS)

B.

During quality assurance

C.

In stakeholder analysis

D.

During quality control (QC)

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Jul 5, 2026
Questions: 1326
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99