Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 154

How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?

Options:

A.

Less time spent on defining scope early on

B.

More time spent on defining scope early on

C.

Less time spent on scope management process

D.

Project scope management is the same in all projects

Buy Now
Question # 155

An adaptive project manager is migrating the company ' s new website. The project manager must work with the team to invest full capacity on this project because it is the company ' s top-ranked project in the portfolio. In order to increase throughput and provide consistent delivery, the project manager needs to assign members who are currently involved with other projects.

How should the project manager assign the team members to this project?

Options:

A.

Task switching

B.

Multitasking

C.

Prediction

D.

Full allocation

Buy Now
Question # 156

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

Options:

A.

Cost-reimbursable

B.

Time and material

C.

Fixed price or lump-sum

D.

Cost-plus-fixed-fee

Buy Now
Question # 157

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Buy Now
Question # 158

During which process does the project team receive bids and proposals?

Options:

A.

Conduct Procurements

B.

Plan Procurements

C.

Estimate Costs

D.

Control Budget

Buy Now
Question # 159

What tern describes an intentional activity to modify a nonconforming product or product component?

Options:

A.

Preventive action

B.

Corrective action

C.

Defect repair

D.

Updates

Buy Now
Question # 160

The cost benefit analysis tool is used for creating:

Options:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Buy Now
Question # 161

In which Process Group are lessons learned documented?

Options:

A.

Planning

B.

Closing

C.

Executing

D.

Initiating

Buy Now
Question # 162

Which of the following is an input to the Develop Project Charter process?

Options:

A.

Work performance information

B.

Project management plan

C.

Business case

D.

Change requests

Buy Now
Question # 163

During a project team meeting, one of the team members suggested a product functionality that would immensely benefit the customer. The project manager documents the request for later analysis.

What is this an example of?

Options:

A.

Monitoring the traceability matrix

B.

Managing the scope

C.

Maintaining the product backlog

D.

Managing the cost benefit

Buy Now
Question # 164

A project team has missed a milestone.

Which response strategy should be implemented?

Options:

A.

Communications

B.

Stakeholder

C.

Contingent

D.

Risk

Buy Now
Question # 165

When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process.

Options:

A.

Develop Schedule

B.

Define Activities

C.

Define Scope

D.

Collect Requirements

Buy Now
Question # 166

The primary purpose of the stakeholder register is to:

Options:

A.

Record stakeholder issues on the project

B.

Maintain lessons learned earlier in the project

C.

Maintain a list of all project stakeholders

D.

Document change requests and their status

Buy Now
Question # 167

Which tool or technique is used in Manage Stakeholder Expectations?

Options:

A.

Stakeholder management strategy

B.

Communication methods

C.

Issue log

D.

Change requests

Buy Now
Question # 168

The Define Scope process is in which of the following Process Groups?

Options:

A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

Buy Now
Question # 169

What risk technique is used to quantify the probability and impact of risks on project objectives?

Options:

A.

Expert judgment

B.

Risk registry

C.

Risk response planning

D.

Interviewing

Buy Now
Question # 170

Which of the following lists represents the outputs of the Monitor Communications process?

Options:

A.

Project communications, project management plan updates, project documents updates, and organizational process assets updates

B.

Work performance information, change requests, project management plan updates, and project documents updates

C.

Communications management plan, project management plan updates, work performance report, and project documents update

D.

Stakeholder engagement plan, change requests, project management plan updates, and project documents updates

Buy Now
Question # 171

A project team for a marketing company is acquiring leaflets and materials from competitors. The team is working on a project to release new products, and they are trying to get ideas on how to most efficiently market these new products.

Which activity is the project team conducting?

Options:

A.

Project execution

B.

Benchmarking

C.

Brainstorming

D.

Project initiation

Buy Now
Question # 172

A required input for Create WBS is a project:

Options:

A.

quality plan.

B.

schedule network.

C.

management document update.

D.

scope statement.

Buy Now
Question # 173

When the business objectives of an organization change, project goals need to be:

Options:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

Buy Now
Question # 174

What can a project manager review to understand the status of a project?

Options:

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

Buy Now
Question # 175

An input to the Control Quality process is:

Options:

A.

Activity attributes

B.

Quality control measurements

C.

Enterprise environmental factors

D.

Deliverables

Buy Now
Question # 176

Among all of the key stakeholders in an agile project, who is responsible for creating project requirements for the team?

Options:

A.

Scrum master

B.

Project manager

C.

Business analyst

D.

Project management office

Buy Now
Question # 177

A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.

Which modeling tool best describes this process?

Options:

A.

Traceability

B.

User interface design

C.

Use case

D.

Wireframe

Buy Now
Question # 178

Which of the following Project Communication Management processes uses performance reports as an input?

Options:

A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

Buy Now
Question # 179

The procurement process that documents agreements and related documentation for future reference is known as:

Options:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Buy Now
Question # 180

A project team working on an automobile manufacturing project is detailing the parts needed for a car door design. The door is composed of several parts that have to be developed in sequence, as the frame is needed before other parts can be designed and built. What activity is the team involved in?

Options:

A.

Creating a work breakdown structure (WBS)

B.

Identifying risks and issues in the project

C.

Developing a stakeholder engagement plan

D.

Developing a communications management plan

Buy Now
Question # 181

A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract Is this?

Options:

A.

Time and material (T8M)

B.

Fixed price incentive fee (FPIF)

C.

Cost plus fixed fee (CPFF)

D.

Cost plus award fee (CPAF)

Buy Now
Question # 182

The component of the risk management plan that documents how risk activities will be recorded is called:

Options:

A.

tracking

B.

scoping

C.

timing

D.

defining

Buy Now
Question # 183

Match the project life cycle type with its corresponding definition.

Options:

Buy Now
Question # 184

Which action should a project manager take to ensure that the project management plan is effective and current?

Options:

A.

Conduct periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards.

D.

Complete the quality control checklist.

Buy Now
Question # 185

Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

Options:

A.

Control chart

B.

Flowchart

C.

Checksheet

D.

Pareto diagram

Buy Now
Question # 186

Once the make-or-buy analysis is completed, which document defines the project delivery method?

Options:

A.

Procurement statement of work (SOW)

B.

Procurement strategy

C.

Terms of reference

D.

Change request

Buy Now
Question # 187

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

Options:

A.

Enhance

B.

Share

C.

Exploit

D.

Accept

Buy Now
Question # 188

Which sentence summarizes the salience model?

Options:

A.

Classifies stakeholders based on assessment of their power, urgency and legitimacy

B.

A chart in which the Stakeholders are ropiosented as dots according to then level ol power and influence

C.

A three-dimensional model that ran be useful to engage the stakeholder community

D.

Classifies stakeholders and the project toam by the impact of their work in the project

Buy Now
Question # 189

During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project ' s components. What should be included in the WBS?

Options:

A.

Activity dependencies

B.

Work package risks

C.

Description of work

D.

Resource estimates

Buy Now
Question # 190

A project manager held a meeting and listed all team members ' ideas for improving the product on a white board. What data gathering technique did the project manager apply?

Options:

A.

Focus groups

B.

Interviews

C.

Brainstorming

D.

Delphi technique

Buy Now
Question # 191

What can the project manager find among the factors that could lead a project to be tailored

Options:

A.

Company Culture

B.

Return on investment

C.

Earned Value

D.

Schedule Performance Index

Buy Now
Question # 192

A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?

Options:

A.

Iteration planning

B.

Retrospective

C.

Backlog refinement review

D.

Daily standup

Buy Now
Question # 193

In complex projects/ initiating processes should be completed:

Options:

A.

Within a work package.

B.

In each phase of the project.

C.

To estimate schedule constraints.

D.

To estimate resource allocations.

Buy Now
Question # 194

Which of the following is a narrative description of products, services, or results to be delivered by a project?

Options:

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

Buy Now
Question # 195

Which of the following investigates the likelihood that each specific risk will occur?

Options:

A.

Risk register

B.

Risk audits

C.

Risk urgency assessment

D.

Risk probability and impact assessment

Buy Now
Question # 196

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?

Options:

A.

-2,000

B.

0

C.

1,000

D.

2,000

Buy Now
Question # 197

Projects are separated into phases or subprojects; these phases include:

Options:

A.

feasibility study, concept development, design, and prototype.

B.

initiate, plan, execute, and monitor.

C.

Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.

D.

Identify Stakeholders, develop concept, build, and test.

Buy Now
Question # 198

Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?

Options:

A.

Project

B.

Functional

C.

Program

D.

Portfolio

Buy Now
Question # 199

A project team is closing out a phase and updating the organizational knowledge base What organizational process asset (OPA) will the team update?

Options:

A.

Traceability matrixB Lessons learned

B.

Change control proceduresD Resource availability

Buy Now
Question # 200

Which process determines the risks that may affect the project and documents their characteristics?

Options:

A.

Control Risks

B.

Plan Risk Management

C.

Plan Risk Responses

D.

Identify Risks

Buy Now
Question # 201

A project team is working on a new driverless vehicle and is organizing a workshop with experts to analyze the data received from the prototype. Who should the project manager invite to provide expert advice?

Options:

A.

The subject matter experts (SMEs) identified in the stakeholder register

B.

The senior experts with high status in the academic community

C.

The major stakeholders nominated by the project sponsor

D.

The usual review participants holding recognized certifications

Buy Now
Question # 202

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

Options:

A.

Develop Schedule

B.

Control Schedule

C.

Estimate Activity Durations

D.

Define Activities

Buy Now
Question # 203

A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

Options:

A.

8

B.

18

C.

36

D.

40

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Jul 5, 2026
Questions: 1326
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99