A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI’s Talent Triangle best relates to this need to improve?
A project manager needs to request outside support......manager need to create
A project manager needs to request outside support for a statement ot work (SOW) that is not precise. Which kind of contract does the project manager need to create?
A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues.
Which method should be used in this situation?
Which of the following documents allows the project manager to assess risks that may require near term action?
Which of the following tools and techniques is used in the Verify Scope process?
Which of the following statements is true regarding project and product lifecycles?
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:
Which of the following Process Groups covers all nine Project Management Knowledge Areas?
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
Which of the following is a tool or technique of the Define Activities process?
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
The process of identifying the stakeholders' information needs is completed during:
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
Which of the following is a tool and technique used in the Develop Schedule process?
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?
In which process might a project manager use risk reassessment as a tool and technique?
Which of the following reduces the probability of potential consequences of project risk events?
The key benefit of the Monitoring and Controlling Process Group is the ability to:
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
In which process is a project manager identified and given the authority to apply resources to project activities?
Which of the following correctly explains the term "progressive elaboration'?
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
Documented identification of a flaw in a project component together with a recommendation is termed a:
In which domain of project management would a Pareto chart provide useful information?
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
The milestone list is an input to which process from the Planning Process Group?