Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
Which tool or technique is used in the Perform Integrated Change Control process?
The process of identifying and documenting relationships among the project activities is known as:
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Which input to the Plan Risk Management process provides information on high-level risks?
A project manager should document the escalation path for unresolved project risks in the:
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
Which process involves developing an approximation of the monetary resources needed to complete project activities?
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
Which of the following is a strategy to deal with positive risks or opportunities?
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Which input will be used when tasked with developing the human resource plan?
A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?
The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?
Which of the following are outputs from the process of creating a work breakdown structure (WBS)?
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
In a project using agile methodology, who may perform the quality control activities?
A project has an estimated duration of 10 months with a total budget of US$220,000. At the end of the fifth month, it is estimated that at completion, the project will incur US$250,000. If the actual cost (AC) calculated is US$150,000, what is the earned value (EV) of the project?
Given the following information.
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A.
Activity D follows Activity C.
How long will it take to complete the project?
When managing costs in an agile environment, what should a project manager consider?
A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?
What can increase the complexity of the Manage Stakeholder Engagement process?
A project manager needs to demonstrate that the project meets quality standards and success criteria. For that reason, the project manager is defining the quality objectives of the project, the quality tools that will be used, and quality metrics for the project deliverables.
Which process is the project manager executing?
Which term refers to the work performed to deliver results with specified features and functions?
Which are examples of processes that may be used once or at predefined points in the project life cycle?
Which is the tool or technique that is used to obtain the list of activities from the work packages?
Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
The features and functions that characterize a result, product, or service can refer to: