Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 204

Plan Communications Management develops an approach and plan for project communications based on stakeholders ' needs and requirements and:

Options:

A.

Available organizational assets

B.

Project staff assignments

C.

Interpersonal skills

D.

Enterprise environmental factors

Buy Now
Question # 205

Which of the following is used as input to prepare a cost management plan?

Options:

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Buy Now
Question # 206

Which actions should a project manager follow to manage stakeholders?

Options:

A.

Identify the key stakeholders and keep them informed at all times.

B.

Identify the stakeholders, planning, managing and monitoring their engagement

C.

Meet and keep informed any person related to the project, at all times

D.

Identify the stakeholders and monitor their level of satisfaction

Buy Now
Question # 207

In an agile and adaptive project, which scope management entity invokes stakeholder engagement?

Options:

A.

Collect Requirements

B.

Create work breakdown structure (WBS)

C.

Plan Scope Management

D.

Scope Baseline

Buy Now
Question # 208

Which is one of the major outputs of Sequence Activities?

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS) update

C.

Project schedule network diagram

D.

Mandatory dependencies list

Buy Now
Question # 209

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?

Options:

A.

0.8

B.

1

C.

1.25

D.

1.8

Buy Now
Question # 210

Stakeholder identification and engagement should begin during what phase of the project?

Options:

A.

After the project management plan is completed

B.

After the stakeholder engagement plan is completed

C.

As soon as the project charter has been approved

D.

After the communications management plan is completed

Buy Now
Question # 211

Under which circumstances should multiple projects be grouped in a program?

Options:

A.

When they are needed to accomplish a set of goals and objectives for an organization

B.

When they have the same project manager and the same organizational unit

C.

When they have the same scope, budget, and schedule

D.

When they are from the same unit of the organization

Buy Now
Question # 212

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

Options:

A.

Crashing

B.

Fast tracking

C.

Leads and lags adjustment

D.

Parallel task development

Buy Now
Question # 213

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

Options:

A.

Control Schedule

B.

Define Activities

C.

Develop Schedule

D.

Estimate Activity Resources

Buy Now
Question # 214

Which statement correctly describes the value of a business case?

Options:

A.

It provides the necessary information to determine if a project is worth the required investment.

B.

It provides for alternative dispute resolution procedures in event of contract default.

C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D.

It is used to help a project manager understand the scope of commercial advantages.

Buy Now
Question # 215

Conflict should be best addressed in which manner?

Options:

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Buy Now
Question # 216

Which Process Group includes the Manage Stakeholder Engagement process?

Options:

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Initiating

Buy Now
Question # 217

In a demonstration meeting with a customer, the project team presented deliverables that were considered ready for customer use. The team based the results on a checklist of all the required criteria for the project.

Which of the following elements is the team using?

Options:

A.

Definition of ready (DoR)

B.

Burndown chart

C.

Backlog refinement

D.

Definition of done (DoD)

Buy Now
Question # 218

Which characteristic do projects and operational work share in common?

Options:

A.

Performed by systems

B.

Constrained by limited resources

C.

Repetitiveness

D.

Uniqueness

Buy Now
Question # 219

Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?

Options:

A.

Leadership management

B.

Technical project management

C.

Strategic management

D.

Business management

Buy Now
Question # 220

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

Options:

A.

Procurement statement of work

B.

Purchase order

C.

Source selection criteria

D.

Bidder conference

Buy Now
Question # 221

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

Options:

A.

Decomposition

B.

Benchmarking

C.

Inspection

D.

Checklist analysis

Buy Now
Question # 222

A project management office manages a number of aspects including the:

Options:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Buy Now
Question # 223

Funding limit reconciliation is a tool and technique used in which process?

Options:

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

Buy Now
Question # 224

An input to the Estimate Activity Resources process is:

Options:

A.

Activity resource requirements.

B.

Published estimating data.

C.

Resource calendars.

D.

Resource breakdown structure (RBS).

Buy Now
Question # 225

An input used in developing the communications management plan is:

Options:

A.

Communication models.

B.

Enterprise environmental factors.

C.

Organizational communications,

D.

Organizational cultures and styles.

Buy Now
Question # 226

Work performance information and cost forecasts are outputs of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

Buy Now
Question # 227

The project manager released a report. A few stakeholders express the view that the report should not have been directed to them.

Which of the 5Cs of written communications does the project manager need to address?

Options:

A.

Correct grammar and spelling

B.

Concise expression and elimination of excess words

C.

Clear purpose and expression directed to the needs of the reader

D.

Coherent logical flow of ideas

Buy Now
Question # 228

A product owner wants to ensure that the project ' s requirements, including product requirements, are met and validated. To do this project manager wants.

Match each process to its definition.

Options:

Buy Now
Question # 229

What three strategies are used to respond to threats?

Options:

A.

Escalate, accept, and mitigate

B.

Accept share, and avoid

C.

Escalate, transfer, and exploit

D.

Mitigate, accept, and prioritize

Buy Now
Question # 230

A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?

Options:

A.

Elicit product requirements.

B.

Verify product functionality.

C.

Manage the project schedule.

D.

Allocate project resources.

Buy Now
Question # 231

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

Options:

A.

Smooth/accommodate

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Force/direct

Buy Now
Question # 232

Which tool is used to develop technical details within the project management plan?

Options:

A.

Expert judgment

B.

Project management methodology

C.

Project management information system (PMIS)

D.

Project selection methods

Buy Now
Question # 233

A project is delivering an integrated solution to an external client on a fixed-price contract. The project has a significant technical component and has a dedicated technical project manager working with a business program manager and the client ' s project manager. The technical lead is requesting two new developers.

Which plan should the project manager use to identify who is responsible for finding the budget for additional developers?

Options:

A.

Cost management plan

B.

Business management plan

C.

Stakeholder engagement plan

D.

Resource management plan

Buy Now
Question # 234

Match the life cycle type to when its requirements are defined.

Options:

Buy Now
Question # 235

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

Options:

A.

organizational skills

B.

technical skills

C.

communication skills

D.

hard skills

Buy Now
Question # 236

In the basic communication model, which term refers to the method that is used to convey the message?

Options:

A.

Decode

B.

Encode

C.

Medium

D.

Noise

Buy Now
Question # 237

A tool or technique used in the Control Procurements process is:

Options:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

Buy Now
Question # 238

Which of the following describes the similarities of the process groups and project life cycle?

Options:

A.

The life cycle involves three project management process groups.

B.

Both provide a basic framework to manage the project.

C.

Each project must have a life cycle and all processes in the five process groups.

D.

The project life cycle is managed by executing the processes within the five process groups.

Buy Now
Question # 239

Which schedule network analysis technique modifies the project schedule to account for limited resources?

Options:

A.

Human resource planning

B.

Fast tracking

C.

Critical chain method

D.

Rolling wave planning

Buy Now
Question # 240

A business analyst needs to ensure the project team understands the most critical roles and responsibilities within the requirements change process. Which responsibility is the most important?

Options:

A.

Analyzing the change

B.

Approving the change

C.

Reviewing the change

D.

Discussing the change

Buy Now
Question # 241

Which of the following is provided by the critical path method?

Options:

A.

Schedule float

B.

Earned value (EV)

C.

Total float

D.

Schedule value

Buy Now
Question # 242

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

Options:

A.

ends.

B.

begins.

C.

delays.

D.

deviates.

Buy Now
Question # 243

One of the tools and techniques of the Manage Project Team process is:

Options:

A.

organization charts.

B.

ground rules.

C.

organizational theory,

D.

conflict management.

Buy Now
Question # 244

A construction project is underway, and during... tasks impacted the painting work

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job What kind ot relationship between the tasks impacted the painting work?

Options:

A.

Finish-to-Finish (FF)

B.

Start-to-Finish (SF)

C.

Finish-to-Start(FS)

D.

Start-to-Slart(SS)

Buy Now
Question # 245

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000

B.

US$9500

C.

US$10,000

D.

US$12,500

Buy Now
Question # 246

Which Perform Quality Control tool graphically represents how various elements of a system interrelate?

Options:

A.

Control chart

B.

Flowchart

C.

Run chart

D.

Pareto chart

Buy Now
Question # 247

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

Options:

A.

Uniform

B.

Continuous

C.

Discrete

D.

Linear

Buy Now
Question # 248

Why is tailoring in a project necessary?

Options:

A.

Requirements keep changing.

B.

An artifact must be produced.

C.

A tool or technique is required.

D.

Each project is unique.

Buy Now
Question # 249

Which of the following is contained within the communications management plan?

Options:

A.

An organizational chart

B.

Glossary of common terminology

C.

Organizational process assets

D.

Enterprise environmental factors

Buy Now
Question # 250

Which of the following is used as an input to prepare a cost management plan?

Options:

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Buy Now
Question # 251

The ability to influence cost is greatest during which stages of the project?

Options:

A.

Early

B.

Middle

C.

Late

D.

Completion

Buy Now
Question # 252

Which of the following tools or techniques is used for Estimate Activity Durations?

Options:

A.

Critical path method

B.

Rolling wave planning

C.

Precedence diagramming method

D.

Parametric estimating

Buy Now
Question # 253

The following is a network diagram for a project.

How many possible paths are identified for this project?

Options:

A.

3

B.

4

C.

6

D.

7

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Jul 5, 2026
Questions: 1326
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99