Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 304

Stakeholder satisfaction should be managed as a key project:

Options:

A.

Benefit

B.

Initiative

C.

Objective

D.

Process

Buy Now
Question # 305

Which are the competing constraints that project manager should address when tailoring a project?

Options:

A.

Cost, scope, schedule

B.

Sponsorship, risk, quality

C.

Schedule, sponsorship, scope

D.

Resources, Quality, Communication

Buy Now
Question # 306

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

Options:

A.

Perform Quality Control

B.

Quality Metrics

C.

Perform Quality Assurance

D.

Plan Quality

Buy Now
Question # 307

During which process of Project Cost Management does a project manager produce the cost baseline?

Options:

A.

Estimate Costs

B.

Control Schedule

C.

Determine Budget

D.

Develop Project Charter

Buy Now
Question # 308

Which is an input to the Verify Scope process?

Options:

A.

Performance report

B.

Work breakdown structure (WBS)

C.

Requested changes

D.

Project management plan

Buy Now
Question # 309

When cost variance is negative and schedule variance is positive, the project is:

Options:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.

Buy Now
Question # 310

An input to the Collect Requirements process is the:

Options:

A.

stakeholder register.

B.

project management plan.

C.

project scope statement.

D.

requirements management plan.

Buy Now
Question # 311

Which is an aspect of the requirements management plan?

Options:

A.

Detailed project scope statement

B.

Creation of work breakdown strucure (WBS)

C.

Impact analysis

D.

Duration for implementation

Buy Now
Question # 312

Projects programs subsidiary portfolios.... objectives refer to?

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?

Options:

A.

Operations Management

B.

Project Management

C.

Program Management

D.

Portfolio Management

Buy Now
Question # 313

What is the definition of Direct and Manage Project Execution?

Options:

A.

Integrating all planned activities

B.

Performing the activities included in the plan

C.

Developing and maintaining the plan

D.

Execution of deliverables

Buy Now
Question # 314

Which of the following is an output of Direct and Manage Project Execution?

Options:

A.

Project management plan

B.

Change request status updates

C.

Organizational process assets updates

D.

Work performance information

Buy Now
Question # 315

What tool or technique can improve a products final characteristics?

Options:

A.

Design for X (DfX)

B.

Problem solving

C.

Process analysis

D.

Risk report

Buy Now
Question # 316

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.

Cost Plus Incentive Fee (CPIF)

B.

Fixed Price Incentive Fee (FPIF)

C.

Cost Pius Award Re (CPAF)

D.

Time and Material (TandM)

Buy Now
Question # 317

Recognition and rewards are tools and techniques of which process?

Options:

A.

Develop Team

B.

Manage Team

C.

Control Resources

D.

Plan Resource Management

Buy Now
Question # 318

Which statement is true about the project management body of knowledge?

Options:

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Buy Now
Question # 319

What is one reason why stakeholders must be identified when performing business analysis?

Options:

A.

To identify project timelines through business reviews

B.

To allow the business analyst to determine the project budget

C.

To identify who should define the business requirements for the project

D.

To determine a cost-benefit analysis for the project

Buy Now
Question # 320

Which is used to solicit proposals from prospective sellers?

Options:

A.

Procurement statement of work

B.

Resource calendars

C.

Procurement document

D.

Independent estimates

Buy Now
Question # 321

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Options:

A.

$50

B.

$100

C.

$125

D.

$175

Buy Now
Question # 322

An output of the Manage Stakeholder Engagement process is:

Options:

A.

change requests

B.

enterprise environmental factors

C.

the stakeholder management plan

D.

the change log

Buy Now
Question # 323

In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?

Options:

A.

Add this risk to the lessons learned register on project completion.

B.

Add the stakeholder to the stakeholder register and add the risk to the risk register.

C.

Make sure proper testing gets completed to minimize the risk highlighted.

D.

Ignore the risk from this stakeholder as this stakeholder never showed up at the start of the project.

Buy Now
Question # 324

A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.

Which entities will the project manager attempt to influence?

Options:

A.

The project and the organization

B.

The organization and the industry

C.

The subject matter experts and the project

D.

The change control board and the organization

Buy Now
Question # 325

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

Options:

A.

Expert judgment

B.

Forecasting methods

C.

Earned value management

D.

Analytical techniques

Buy Now
Question # 326

A technique used to determine the cause and degree of difference between baseline and actual performance is:

Options:

A.

Product analysis.

B.

Variance analysis.

C.

Document analysis,

D.

Decomposition.

Buy Now
Question # 327

In Project Cost Management, which input is exclusive to the Determine Budget process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Buy Now
Question # 328

Which tools and techniques will a project manager use to develop a project charter?

Options:

A.

Project manager experience, expert judgment, scope statement, and meetings

B.

Lessons learned database. Interpersonal and team skills, cost baseline, and meetings

C.

Expert judgment, data gathering. scope statement, schedule baseline, and meetings

D.

Expert judgment, data gathering. interpersonal and team skills, and meetings

Buy Now
Question # 329

Which of the following is an output of the Define Activities process?

Options:

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

Buy Now
Question # 330

Which output is the approved version of the time-phased project budget?

Options:

A.

Resource calendar

B.

Scope baseline

C.

Trend analysis

D.

Cost baseline

Buy Now
Question # 331

A project is in the planning phase and ready for plan review and approval when a sponsor switch happens. What should the next course of action be?

Options:

A.

Plan Communications Management

B.

Plan Stakeholder Engagement

C.

Perform Integrated Change Control

D.

Perform Qualitative Risk Analysis

Buy Now
Question # 332

What is the purpose of an adaptive standup meeting?

Options:

A.

To review what work has been completed, remove impediments, and calculate velocity

B.

To ask the team what work has been completed, calculate velocity, and determine what work will be completed

C.

To ask the team what work has been completed, ask what work will be completed, and report impediments

D.

To update the burndown chart, calculate velocity, and report impediments

Buy Now
Question # 333

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

Options:

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Buy Now
Question # 334

What is one of the main purposes of the project charter?

Options:

A.

Formal authorization of the existence of the project

B.

Formal acceptance of the project management plan

C.

Formal approval of the detailed project budget

D.

Formal definilion of stakeholder roles and responsibilities

Buy Now
Question # 335

A Scrum team has a product backlog and a sprint backlog. Which of the following is a correct statement related to these artifacts?

Options:

A.

The product backlog does not contain a prioritized list of requirements.

B.

The sprint backlog contains items to be completed during the current sprint.

C.

The sprint backlog contains the list of items prioritized by the product owner.

D.

The product backlog is a subset of the sprint backlog.

Buy Now
Question # 336

An input to Close Project or Phase is:

Options:

A.

Accepted deliverables,

B.

Final products or services,

C.

Document updates,

D.

Work performance information.

Buy Now
Question # 337

A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?

Options:

A.

A diagram in which resource optimization has been applied.

B.

A diagram in which the critical path method has been applied.

C.

A diagram in which a predefined series of activities has been organized.

D.

A diagram which shows a combination of resource and time optimization.

Buy Now
Question # 338

A project team has completed the first iteration and the testing manager approved the test report, indicating that the acceptance criteria have been met. The manager of the business unit that will use the new product is asking for additional functionality before approving the rollout for their team.

What should the project manager do next?

Options:

A.

Escalate this issue to the project sponsor.

B.

Reschedule the rollout to start with another business unit.

C.

Reschedule the rollout to include the new requirements.

D.

Escalate this issue to the project management office (PMO).

Buy Now
Question # 339

The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?

Options:

A.

Technical project management skills

B.

Time management skills

C.

Strategic and business management skills

D.

Leadership skills

Buy Now
Question # 340

A project manager needs information to finish their work on the project charter for a clinical trial.

Which procedure is used to obtain the requirements information?

Options:

A.

Forecasting

B.

Simulations

C.

Elicitation

D.

Quantitative analysis

Buy Now
Question # 341

Which characteristic defines the Delphi technique of group decision-making?

Options:

A.

The participants must use their expertise to determine the best option.

B.

The decision is based on eliminating the options that are too expensive.

C.

The decision is based on a predefined algorithm and the highest score.

D.

The participants must create a list of options, rank them, and then vote.

Buy Now
Question # 342

What specific quality considerations should be examined while completing Quality Management plan?

Options:

A.

Risk registerB Stakeholder engagement

B.

Continuous improvement

C.

Standards and regulatory compliance

Buy Now
Question # 343

Which of the following Process Groups covers all nine Project Management Knowledge Areas?

Options:

A.

Executing

B.

Monitoring and Controlling

C.

Planning

D.

Initiating

Buy Now
Question # 344

Identify Risks is part of which Process Group?

Options:

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Buy Now
Question # 345

Which of the following is an input to Develop Human Resource Plan?

Options:

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

Buy Now
Question # 346

The staffing management plan is part of the:

Options:

A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

Buy Now
Question # 347

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

Options:

A.

Bottom-up

B.

Three-point

C.

Parametric

D.

Analogous

Buy Now
Question # 348

Which of the following projects is a quality candidate for adaptive approaches?

Options:

A.

Installing new computers across offices

B.

Retrofitting an old building

C.

Upgrading an information system

D.

Designing a new suspension bridge

Buy Now
Question # 349

Due to new market conditions a five-year project......need to be updated

Due to new market conditions a five-year project requires a full revision of project objectives. Which components to the stakeholder engagement plan need to be updated?

Options:

A.

Scope and impact of change to stakeholders

B.

Project scope and stakeholders goals

C.

Engagement level of key stakeholders

D.

Stakeholders expectations for the project

Buy Now
Question # 350

In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?

Options:

A.

Use a lightweight cost estimation due to the nature of angile projects.

B.

Use a detailed cost estimation for agile projects.

C.

Retrieve a dudget from a previous project and create a baseline of this project based on it.

D.

Use a detailed work breakdown structure (WBS) to get cost estimation.

Buy Now
Question # 351

Which of the following is an output from Control Scope?

Options:

A.

Change requests

B.

Variance analysis

C.

Accepted deliverables

D.

Requirements documentation

Buy Now
Question # 352

The chart below is an example of a:

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Buy Now
Question # 353

An employee was hired to work on ongoing, repetitive activities in the accounting department. The employee ' s duties are managing and controlling day-to-day activities. Which type of managing is the employee performing?

Options:

A.

Strategic

B.

Finance

C.

Project

D.

Operations

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: Jul 5, 2026
Questions: 1326
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99