Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

CAPM Exam Dumps - PMI CAPM Questions and Answers

Question # 304

In project management, a temporary project can be:

Options:

A.

Completed without planning

B.

A routine business process

C.

Long in duration

D.

Ongoing to produce goods

Buy Now
Question # 305

A project manager oversees a project in an adaptive environment. After each iteration, which type of meeting should the project manager conduct?

Options:

A.

Iteration planning

B.

Retrospective

C.

Backlog refinement review

D.

Daily standup

Buy Now
Question # 306

Which input to the Plan Risk Management process provides information on high-level risks?

Options:

A.

Project charter

B.

Enterprise environmental factors

C.

Stakeholder register

D.

Organizational process assets

Buy Now
Question # 307

A project manager was assigned to a project to implement a manufacturing system in a food factory. The main project objective is to deliver machines that are ready to process food. The project manager decides that this particular project does not require the use of timeboxed iterations.

Which method should the project manager adopt?

Options:

A.

SAFe®

B.

Kanban

C.

Feature-driven development (FDD)

D.

Scrum

Buy Now
Question # 308

A business analyst is evaluating solutions against the expected results and logging defects along the way. The next task is to analyze the discrepancies prior to facilitating a go/no-go decision.

Which technique should be used as a starting point to uncover problem areas?

Options:

A.

Elicitation

B.

Opportunity analysis

C.

Cost-benefit analysis

D.

Feasibility analysis

Buy Now
Question # 309

A project team of telecommuters located in three different time zones regularly misses project deadlines Daily meetings often start and end with the same person talking and the rest of the team listening The project manager determines that communication among team members must be addressed.

What communication step is missing from the daily meetings?

Options:

A.

Interpersonal communication

B.

Feedback response communication

C.

Push communication

D.

Pull communication

Buy Now
Question # 310

Which tool or technique is used in the Perform Integrated Change Control process?

Options:

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

Buy Now
Question # 311

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

Options:

A.

Slack

B.

Float

C.

Lag

D.

Lead

Buy Now
Question # 312

The probability and impact matrix is primarily used to:

Options:

A.

Quantify risk issues for trends during a quality audit.

B.

Develop a risk register for risk planning.

C.

Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.

D.

Define risk and compare impacts during Perform Quantitative Risk Analysis.

Buy Now
Question # 313

Which tools and techniques will a project manager use to develop a project charter?

Options:

A.

Project manager experience, expert judgment, scope statement, and meetings

B.

Lessons learned database. Interpersonal and team skills, cost baseline, and meetings

C.

Expert judgment, data gathering. scope statement, schedule baseline, and meetings

D.

Expert judgment, data gathering. interpersonal and team skills, and meetings

Buy Now
Question # 314

For what project management process is work performance information an output?

Options:

A.

Implement Risk Responses

B.

Plan Stakeholder Engagement

C.

Monitor Stakeholder Engagement

D.

Plan Quality Management

Buy Now
Question # 315

A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?

Options:

A.

Identify the crashed project schedule to find the shortest duration to complete the project.

B.

Identify the longest activity path in the schedule with the shortest possible duration.

C.

Identify the tasks with float duration, which do not impact the duration of the project.

D.

Identify the path through the schedule with leveled resources and the shortest duration.

Buy Now
Question # 316

A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:

Options:

A.

create the project management plan.

B.

identify the project objectives.

C.

review and update stakeholder engagement.

D.

create the schedule baseline.

Buy Now
Question # 317

Which document can help a project manager to leverage historical project information?

Options:

A.

Lessons learned register

B.

Schedule baseline

C.

Work performance data

D.

Deliverable acceptance forms

Buy Now
Question # 318

A project team identifies defects that will require a modification to a tool ' s functionality. What process should the project manager follow to obtain stakeholder buy-in?

Options:

A.

Control Schedule

B.

Perform Qualitative Risk Analysis

C.

Perform Integrated Change Control

D.

Control Scope

Buy Now
Question # 319

A project manager has the task of determining the deliverables for a six-month project using a predictive approach. How should the project manager determine which processes to include in the project management plan?

Options:

A.

Follow organizational methodology and produce all required deliverables.

B.

Discuss the processes and deliverables needed to meet the project objectives with the team.

C.

Identify the processes and deliverables for only the current phase first.

D.

Integrate hybrid approach processes and deliverables to meet the short delivery timeline.

Buy Now
Question # 320

Which Process Group typically consumes the bulk of a project ' s budget?

Options:

A.

Monitoring and Controlling

B.

Executing

C.

Planning

D.

Initiating

Buy Now
Question # 321

Which of the following is an output of the Perform Integrated Change Control process?

Options:

A.

Cost-benefit analysis

B.

Updated project charter

C.

Approved change request

D.

Multicriteria decision analysis

Buy Now
Question # 322

A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a traditional project delivered using a linear delivery approach? (Choose three)

Options:

A.

Many expected simple scope change requests

B.

Few expected simple scope change requests

C.

Routine and repetitive activities

D.

Collocated project teams

E.

Use of established templates

Buy Now
Question # 323

A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?

Options:

A.

0.88

B.

1.12

C.

0.58

D.

1.58

Buy Now
Question # 324

The project manager is working in the Resource Management process. Which items may the project manager need to include in the team charter?

Options:

A.

Cultural norms, roles and responsibilities, and organizational chart

B.

Assumption logs, resource calendars and training schedule

C.

Communication guidelines, conflict resolution process, and team agreements

D.

Company policies, recognition plan, and roles and responsibilities

Buy Now
Question # 325

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

Options:

A.

1

B.

0.4

C.

0.5

D.

0.8

Buy Now
Question # 326

The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

Options:

A.

Least cost

B.

Qualifications only

C.

Sole source

D.

Fixed budget

Buy Now
Question # 327

A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?

Options:

A.

Engage customer earlier

B.

Conduct quality audits

C.

Validate Scope

D.

Validate quality requirements

Buy Now
Question # 328

What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives ' ?

Options:

A.

Executing

B.

Planning

C.

Initiating

D.

Monitoring and Controlling

Buy Now
Question # 329

Perform Quantitative Risk Analysis focuses on:

Options:

A.

compiling a list of known risks and preparing responses to them.

B.

assessing the probability of occurrence and Impact for every risk in the risk register.

C.

evaluating the contingency and management reserves required for the project.

D.

analyzing numerically the impact of individual risks on the overall project ' s time and cost objectives.

Buy Now
Question # 330

The Perform Quality Assurance process occurs in which Process Group?

Options:

A.

Executing

B.

Monitoring and Controlling

C.

Initiating

D.

Planning

Buy Now
Question # 331

What is an example of an emerging trend in procurement management?

Options:

A.

Online technology enable projects to postpone ordering long lead items until the items are needed

B.

Online technologies allow a project ' s progress to be viewed by all stakeholders to build better relations

C.

Online procurement tools provide buyers with multiple sources to advertise to sellers.

D.

Online procurement tools provide sellers with designated sources for procurement documents and the resources to complete them.

Buy Now
Question # 332

The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

Options:

A.

stakeholder management strategy.

B.

communications management plan,

C.

stakeholder register,

D.

performance report.

Buy Now
Question # 333

Which of the following set of elements is part of an effective communications management plan?

Options:

A.

Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information

B.

Phone book directory, stakeholder communication requirements, project charter, glossary of common terminology

C.

Organizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology

D.

Glossary of common terminology, constraints denved from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan

Buy Now
Question # 334

Organizational theory is a tool used in which Project Human Resource Management process?

Options:

A.

Manage Project Team

B.

Acquire Project Team

C.

Develop Project Team

D.

Plan Human Resource Management

Buy Now
Question # 335

A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

Options:

A.

mitigate

B.

accept

C.

transfer

D.

avoid

Buy Now
Question # 336

Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

Options:

A.

organizational skills

B.

technical skills

C.

communication skills

D.

hard skills

Buy Now
Question # 337

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

Options:

A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

Buy Now
Question # 338

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Buy Now
Question # 339

What estimating technique is used when there is limited information?

Options:

A.

Analogous estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Three-point estimating

Buy Now
Question # 340

Which Control Quality tool is also known as an arrow diagram?

Options:

A.

Matrix diagram

B.

Affinity diagram

C.

Tree diagram

D.

Activity network diagram

Buy Now
Question # 341

Which type of analysis would be used for the Plan Quality process?

Options:

A.

Schedule

B.

Checklist

C.

Assumption

D.

Cost-Benefit

Buy Now
Question # 342

Which Process Group and Knowledge Area include the Sequence Activities process?

Options:

A.

Executing Process Group and Project Time Management

B.

Executing Process Group and Project Cost Management

C.

Planning Process Group and Project Time Management

D.

Planning Process Group and Project Cost Management

Buy Now
Question # 343

The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?

Options:

A.

If the operation team members were trained externally

B.

If the transition process was agreed upon during the build

C.

If the end-user documentation was more thorough

D.

If the operations manager was invited to all sprint reviews

Buy Now
Question # 344

Which process occurs within the Monitoring and Controlling Process Group?

Options:

A.

Control Costs

B.

Plan Quality

C.

Perform Quantitative Risk Analysis

D.

Determine Budget

Buy Now
Question # 345

What tool or technique can improve a products final characteristics?

Options:

A.

Design for X (DfX)

B.

Problem solving

C.

Process analysis

D.

Risk report

Buy Now
Question # 346

Which is a method of prototyping that creates a functioning representation of the final finished product to the user?

Options:

A.

Low-fidelity prototyping

B.

High-fidelity prototyping

C.

Data prototyping

D.

Report prototyping

Buy Now
Question # 347

Which of these is true of project integration management?

Options:

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

Buy Now
Question # 348

Quality metrics are an output of which process?

Options:

A.

Plan Quality

B.

Perform Quality Control

C.

Perform Quality Assurance

D.

Perform Qualitative Risk Analysis

Buy Now
Question # 349

Which of the following are three inputs to the risk register?

Options:

A.

Risk register updates, stakeholder register, and quality management plan

B.

Communication management plan, enterprise environmental factors, and activity duration estimates

C.

Risk management plan, activity cost estimates, and project documents

D.

Project scope statement, organizational process assets, and scope baseline

Buy Now
Question # 350

On a clinical trial project, the project manager is worried about maintaining control of the project. The project manager decides to use a requirements traceability matrix.

What is the advantage of using this tool?

Options:

A.

Scope creep will be prevented.

B.

Resource allocation will be kept to a minimum.

C.

Project closure will be established.

D.

Project costs will be controlled.

Buy Now
Question # 351

The scope management plan is a subsidiary of which project document?

Options:

A.

Schedule management plan

B.

Project management plan

C.

Quality management plan

D.

Resource management plan

Buy Now
Question # 352

A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues.

Which method should be used in this situation?

Options:

A.

SAFe®, as it does not allow for scaling work across different teams in the organization.

B.

Extreme Programming (XP), as it does not allow for moving on to new items until the existing items are finished.

C.

Kanban, because the team does not start new work until the existing work is finished.

D.

Scrum, as it allows for completing the whole architecture up front without leaving any technical debt for the future.

Buy Now
Question # 353

The project sponsor wants to know when an in-flight adaptive project will be done. Which of the following metrics will help the team to predict how much longer the project will take?

Options:

A.

Risk burnup and control chart

B.

Customer satisfaction index and workload

C.

Average burndown and velocity

D.

Average velocity and cycle time

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)
Last Update: May 21, 2026
Questions: 1320
CAPM pdf

CAPM PDF

$25.5  $84.99
CAPM Engine

CAPM Testing Engine

$28.5  $94.99
CAPM PDF + Engine

CAPM PDF + Testing Engine

$40.5  $134.99