Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

LEED-AP-BD+C Exam Dumps - USGBC Leadership in Energy and Environmental Design (LEED) Questions and Answers

Question # 34

For a whole building energy simulation approach, what should be identical for the base building and the proposed building?

Options:

Buy Now
Question # 35

A project has total waste of 20 tons (18.1 tonnes) that includes the following:

· 8 tons (7.3 tonnes) of recycled demolition steel and concrete

· 2 tons (1.8 tonnes) of trees cleared from the site

. 3 tons (2.7 tonnes) of commingled scrap with 40% diverted

. 6 tons (5.4 tonnes) of used furniture donated to a non-profit organization

· 1 ton (0.9 tonnes) of removed carpet and ceiling tiles sent back to the manufacturer

What is the percentage of diverted waste for Materials and Resources Credit, Construction and Demolition Waste

Management?

Options:

A.

60%

B.

75%

C.

90%

D.

100%

Buy Now
Question # 36

A commercial new construction project consists of mixed space usage. When deciding which LEED rating system to use, the LEED AP should follow which of the following rules?

Options:

A.

If a rating system is appropriate for less than 50% of the gross area of the LEED project space then the rating system must not be used

B.

If a rating system is appropriate for more than 50% of the gross floor area of LEED project space, then that rating system must be used

C.

If a rating system is appropriate for 30% to 60% of the gross floor area, the project team must independently assess their situation and decide which rating system is most applicable

D.

If a rating system is appropriate for 40% to 60% of the gross floor area, the project team must independently assess their situation and decide which rating system is most applicable

Buy Now
Question # 37

The material cost for a project is $100,000. What is the minimum material value needed to achieve Materials and Resources Credit, Building Disclosure and Optimization, Sourcing of Raw Materials, Option 2. Leadership Extraction

Practices?

Options:

A.

$10,000

B.

$12,500

C.

$22,500

D.

$25,000

Buy Now
Question # 38

Large commercial buildings are most often dominated by

Options:

A.

internal loads

B.

lighting loads

C.

external loads

D.

envelope loads

Buy Now
Question # 39

A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%. Which alternative analyses should the team run to check different impact measurements?

Options:

A.

Change the orientation of the design case building

B.

Optimize the slab depth of the design case building

C.

Decrease the gross floor area of the baseline building

D.

Increase the wall mass and types of windows in the baseline building

Buy Now
Question # 40

In the energy modeling of a building envelope, which of the following U-values should be considered as an assembly U-value?

Options:

A.

Wall

B.

Steel

C.

Glass

D.

Concrete

Buy Now
Question # 41

Which principal areas must the LEED AP focus on to attain the Integrative Process Credit, Integrative Process?

Options:

A.

Materials and resources

B.

Location and site selection

C.

Regional priority and innovation

D.

Energy and water related systems

Buy Now
Question # 42

To achieve the Sustainable Sites Credit, Light Pollution Reduction, Option 1. BUG Rating Method, projects must demonstrate:

Options:

A.

All luminaires have full cutoff fixtures

B.

All luminaires are mounted at least three mounting heights from the lighting boundary

C.

All luminaires have a minimum color temperature of 3500 K

D.

All luminaires meet acceptable fixture ratings for the project’s Model Lighting Ordinance (MLO) lighting zone

Buy Now
Question # 43

A project team is using the whole building simulation model to quantify the percentage of energy savings for the project. Which of the following should remain the same for both the baseline building and the proposed building?

Options:

A.

Building operating schedule and occupancy hours

B.

Building operating schedule and total window area

C.

Building envelope construction and occupancy hours

D.

Total window area and building envelope construction

Buy Now
Exam Code: LEED-AP-BD+C
Exam Name: LEED AP Building Design + Construction (LEED AP BD+C)
Last Update: Aug 24, 2026
Questions: 404
LEED-AP-BD+C pdf

LEED-AP-BD+C PDF

$25.5  $84.99
LEED-AP-BD+C Engine

LEED-AP-BD+C Testing Engine

$28.5  $94.99
LEED-AP-BD+C PDF + Engine

LEED-AP-BD+C PDF + Testing Engine

$40.5  $134.99