Question # 54

Which of the following actions should a project team implement to minimize human and ecological health impacts through material selection while pursuing MRc2: Reduce Embodied Carbon?

Options:

A.

Avoid materials imported over long distances

B.

Select products with ISO-verified Type III Environmental Product Declarations

C.

Select materials that provide only basic recycling information

Buy Now
Question # 55

Which of the following strategies under LTc2: Equitable Development, Option 3: Equitable Construction helps achieve the goal of enhancing the economic and social vitality of a community?

Options:

A.

Providing job-related skills training through a registered apprenticeship program

B.

Establishing affordable housing units within the project

C.

Engaging local business owners in the project design process

Buy Now
Question # 56

A project team is working on a mixed-use development aiming to achieve LEED certification. The client wishes to limit on-site combustion as a strategy for future electrification readiness. The building will include residential units, retail spaces, and a central heating system.

Which of the following strategies should the project team implement to support the goal of electrification readiness and limit on-site combustion?

Options:

A.

Include electric vehicle charging stations in the parking area

B.

Utilize a high-efficiency gas boiler for space heating

C.

Implement a solar thermal system for hot water supply

Buy Now
Question # 57

Which of the following methods is the referenced standard for demonstrating compliance with EQp2: Fundamental Air Quality?

Options:

A.

ASHRAE 55-2010

B.

ASHRAE Guideline 44

C.

ASHRAE 62.1-2022

D.

ASHRAE 90.1-2010

Buy Now
Question # 58

Which of the following strategies can be used to achieve a point in Innovation Credit, Innovation, Option 1.Innovation?

Options:

A.

Achieve 60% reduction in outdoor water use

B.

Implement an employee engagement and education plan

C.

Use on site renewable energy for 8% of the total energy needs

D.

Purchase green power for 100% of the total project energy use

Buy Now
Question # 59

A hospital certified underLEED V5in 2018 is designing and constructing a 21,000 ft² (1,950.96 m²) vertical addition, plus vegetated terraces and a mechanical penthouse.

The original hospital achieved the Gold certification level and was built with the capacity to add three floors—levels six through eight—to the top of the structure. This addition requires partial demolition of the roof and the floor below.

The project is designed to be architecturally cohesive with the existing building façade and is targeting Platinum certification under LEED v5.

The campus is in a dense urban area adjacent to several bus stops, a light-rail transit station within a 2,500 ft. (762 m) walking distance, and a bicycle docking point at the main entrance to the property. An on-campus shuttle service connects patients, visitors, and staff from the parking areas to each medical building and the light-rail station.

The healthcare campus has existing infrastructure; therefore, no new roads, sidewalks, parking structures, or ground-level landscaping will be installed.

The new floors have separate mechanical systems in the penthouse, but piping for public and patient restrooms, janitor closets, and staff break rooms connects directly to the main hospital plumbing system.

The newly installed medical equipment uses gas, steam, and chilled water supplied by the campus central plant.

Based on the project description, which of the following credits can be achieved with all available points awarded?

Options:

A.

LTc3: Compact and Connected Development

B.

EAc1: Electrification

C.

WEc2: Enhanced Water Efficiency

Buy Now
Question # 60

A school project is located in a basin. Snow melts in the spring on the nearby mountains which replenishes the local water supply. The nearby highways are sometimes closed during the winter due to the winter storm. What is the top priority the project team should focus on?

Options:

A.

Use ground source heat pump

B.

Install efficient plumbing fixtures

C.

Ergonomics design for classrooms and computer rooms

D.

Purchase all materials locally to minimize road transportation

Buy Now
Question # 61

Sustainable Sites Credit, Site Assessment requires evaluation of

Options:

A.

soils, archeology, hydrology

B.

topography, hydrology, human use

C.

vegetation, topography, archaeology

D.

human health effects, climate, land value

Buy Now
Question # 62

To achieve SSc6: Light Pollution Reduction using the Backlight, Uplight, and Glare (BUG) Rating Method, projects must demonstrate that all luminaires:

Options:

A.

Meet acceptable fixture ratings for the project’s Model Lighting Ordinance (MLO) lighting zone

B.

Have a minimum correlated color temperature of 3,500 K

C.

Are mounted at least three mounting heights from the lighting boundary

D.

Are full-cutoff fixtures

Buy Now
Question # 63

The LEED AP is leading the first design charrette for a new LEED project with the project ' s owners. What document should be used to record the project goals to be used throughout the design of the project?

Options:

A.

Owner ' s Project Requirements (OPR)

B.

Owner ' s list of wants and needs

C.

Criteria for contractor selection

D.

Basis of Design (BOD)

Buy Now
Exam Code: LEED-AP-BD+C
Exam Name: LEED AP Building Design + Construction (LEED v5 AP BD+C)
Last Update: Nov 23, 2026
Questions: 454
LEED-AP-BD+C pdf

LEED-AP-BD+C PDF

$22.5  $89.99
LEED-AP-BD+C Engine

LEED-AP-BD+C Testing Engine

$25  $99.99
LEED-AP-BD+C PDF + Engine

LEED-AP-BD+C PDF + Testing Engine

$35  $139.99