A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).
What should the team tell the sponsor at this point in the planning process?
A Scrum team is refining product backlog items for the next sprint in a project. The product owner does not agree with the changes.
Can the product owner reject changes to a product backlog?
A seven-member agile team ' s composition varies considerably in age, gender, culture, personality type, and professional background. When planning a team-building event, what type of interpersonal skills should the project leader use?
An agile lead has been assigned to a project to develop an innovative digital device for a consumer products company. The company asked the agile lead to use a Scrum approach to product development. The product owner has worked on Scrum projects before and is excited about the value Scrum will bring to the company.
What should the scrum master do first?
A project team identifies a number of technical challenges with features in the next sprint.
What should they do?
On a complex project with a large degree of uncertainty, the team’s velocity is declining. Upon testing, it is discovered that many of the work items reported as complete are not meeting the stakeholders ' requirements.
Which of the following could help resolve the incomplete work?
A new Scrum team is struggling with the various ceremonies of Scrum. Among other things, the product owner and stakeholders find the technical architecture and design presentations during sprint reviews less than informative.
What should the team do?
A project team has been working on five data source integrations. They have allocated one tester for each data source. One of the testers is on emergency leave for personal reasons, so the project
deliverables could not be completed on time.
How should the project team improve during their retrospective for future implementations?
An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables; however, issues arise when the deliverables are integrated. What should the agile practitioner do?
A project team member expresses frustration about the length of time it takes to make decisions for a complex project. Approvals need to happen at many levels in the company.
What should the team lead do to improve decision quality and reduce the time required to make decisions?