Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PMI-ACP Exam Dumps - PMI Agile Questions and Answers

Question # 94

A team member on a self-directed team is concerned that a feature the customer wants is outside of what the team will be able to deliver. What should the team member do next?

Options:

A.

Escalate the concern to the project sponsor for necessary action

B.

Adjust the feature to make it work as needed

C.

Work directly with the customer to arrive at a suitable compromise

D.

Log this into the risk register and inform the team at the next standup meeting

Buy Now
Question # 95

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?

Options:

A.

Capture risks and make them visible, and use a burn down chart to focus on reducing risks early in the project.

B.

Ask the scrum master to extend the sprint's duration to allow more time to work through technical issues.

C.

Place the impacted stories on the story board, and use daily stand ups to make the product owner aware of the technical issues.

D.

Seek guidance from the development manager

Buy Now
Question # 96

An experienced product owner presents the epics and corresponding stones during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.

What should the agile team do?

Options:

A.

Evaluate how much can be delivered based on the Scrum Master's estimation

B.

Identify a set of user stones based on the team's velocity

C.

Initiate an estimation session

D.

Consult historical data for project completion

Buy Now
Question # 97

A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?

Options:

A.

Lead time

B.

Team velocity

C.

Burndown rate

D.

Earned value (EV)

Buy Now
Question # 98

Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project.

How should the agile practitioner explain to senior management the benefits of this approach?

Options:

A.

It ensures a consistent level of detail is available in the project schedule

B.

It prevents a wasteful buildup of requirements inventory that may never be processed

C.

It provides a concrete definition of project scope, cost and duration

D.

It allows the team to lock down the stories to be included in a release

Buy Now
Question # 99

An event management team is following an agile approach to prepare for an upcoming conference. The regional sales manager, from where the conference is to be held, contacts the team with a number of questions about the company's booth.

What should the team do?

Options:

A.

Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.

B.

Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.

C.

Invite the regional sales manager to the next iteration review to share the progress.

D.

Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.

Buy Now
Question # 100

An agile coach is facing a dilemma: On one hand, there is a requirement that is vital and will consume all capacity of the team. On the other hand, there are some chore-related tasks that will improve the team's ability to produce results. The team insists on implementing these tasks since they will increase efficiency.

What should the agile coach do?

Options:

A.

Characterize chores as low priority since they do not add obvious value to the product

B.

Delegate chore-related tasks to another team.

C.

Escalate the issue to the shareholders/steering committee.

D.

Get the product owner and team to meet to prioritize the work.

Buy Now
Question # 101

A graphic designer on an agile team does not attend most meetings. When asked the reason for not attending, the designer told the agile practitioner that the scrum master could represent them in meetings if needed. The team is frustrated and does not agree with this approach.

Which conflict resolution method would work best in this scenario?

Options:

A.

Avoidance

B.

Forcing

C.

Accommodation

D.

Collaborating

Buy Now
Question # 102

An agile project manager is planning the initial scope, schedule and cost range estimates on a new project. The team will be using Kanban to control work.

What metrics should the team use to measure performance?

Options:

A.

Lead time, throughput and due date performance

B.

Work in progress limits Kanban board, and time boxes

C.

Work item types, sprint cadences, and defect classes

D.

Burndown charts, scatter diagrams, and throughput

Buy Now
Question # 103

During a project's last iteration, an agile team struggled with a feature's delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated.

What should the agile project leader have done to avoid this situation?

Options:

A.

Provided just-in-time training of the required skill to specific team members

B.

Lowered the feature's priority until a team member acquired the skill to build it

C.

Assigned the feature to another agile team that had members with the required skills

D.

Ensured that the team was comprised of cross-functional, generalized specialists

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: Oct 6, 2025
Questions: 476
PMI-ACP pdf

PMI-ACP PDF

$29.75  $84.99
PMI-ACP Engine

PMI-ACP Testing Engine

$33.25  $94.99
PMI-ACP PDF + Engine

PMI-ACP PDF + Testing Engine

$47.25  $134.99