Question # 64

An organization strives hard to accelerate value delivery by improving product design, development, and transition activities. What ways of working should the organization discontinue to become an effective player?

Options:

A.

Leverage continuous feedback from customers to seamlessly align delivery with requirements.

B.

Define software functionality by relying on the developers' experience designing similar system

C.

Engage end users in user acceptance testing to ensure the product meets their expectations.

D.

Educate end users and other stakeholders to understand desired outcomes through user stories.

Buy Now
Question # 65

The amount of information captured in the project's defects is varying within the development team. Team members are becoming frustrated with the defect quality inconsistencies and the frequent clarification required.

What should be done to address the issue?

Options:

A.

Stop the current iteration to discuss defect quality issues and explore solutions.

B.

Discuss and explore solutions in the next planning meeting and take corrective actions as required.

C.

Generate insights at the next retrospective and adjust processes as decided by the team.

D.

Assign corrective actions to the backlog for the team to identify the mandatory defect information.

Buy Now
Question # 66

An agile team is having difficulties in obtaining the participation of a true user to be a part of their team. In the absence of a true user, the development manager steps in to act as a proxy for the user.

What can the agile team do to improve value delivery in the absence of a true user?

Options:

A.

Improve the velocity of each iteration.

B.

Add a variety of skilled programmers and expert testers to the team.

C.

Reduce the length of each iteration.

D.

Add a variety of users, such as business analysts and domain experts, to the team.

Buy Now
Question # 67

What should a learn consider when calculating the effort needed to complete a product backlog?

Options:

A.

The increase in velocity and cost

B.

A buffer in the sprint to mitigate unexpected risks

C.

Assigning extra points to each task to allow time for changes

D.

Stories describing infrastructure tasks and analysis tasks

Buy Now
Question # 68

After some iterations, the agile practitioner observes that the team is self-organizing in small knowledge silos. Which action should be taken regarding the team's behavior?

Options:

A.

Raise the concern to upper management.

B.

Establish rules for the team to avoid this situation.

C.

Reorganize the team aiming to force the behaviors.

D.

Advise the team of the risks and invite them to change.

Buy Now
Question # 69

HOTSPOT

Organizations that implement agile project management focus on upgrading existing products and services through cost reductions, time savings, or quality enhancements for existing customers (i.e., operational agility). Organizations need to realize that the major financial gains from agile project management will result from the practice of what? (Select answer from dropdown)

Options:

Buy Now
Question # 70

An agile lead is working on a project to build a new product that will bring substantial business value to a company. Company executives want to present the first release at an important industry fair the following month. The agile lead started the project the previous month, and the team planned the release to take 8 iterations. For the past 4 iterations, work has been performed as planned and on time. In the current iteration, however, one team member will be out for the remainder of the project. Without this team member, velocity would drop 30%.

What should the agile lead do to ensure the release will be on time for the fair?

Options:

A.

Reduce the scope of the release to meet the deadline.

B.

Deliver as many features as possible based on the new velocity.

C.

Extend the project timeline to accommodate the missing team member.

D.

Hire a new team member to replace the missing one.

Buy Now
Question # 71

Part way through a project, several team members are in conflict over whether or not a deliverable has been properly completed. How should the agile leader reduce this conflict?

Options:

A.

Facilitate team agreement on the definition of done (DoD) during the chartering process.

B.

Motivate the team durinq Tuckman's "storminq" phase.

C.

Ensure the product owner is grooming the backlog so user stories are clearly written.

D.

Ensure epics are broken down into smaller user stories for clarity.

Buy Now
Question # 72

A product owner is responsible for a new product. The internal customer questions using an agile approach because they need a product that works without any bugs or missing features once it is launched.

What should the product owner do?

Options:

A.

Plan regular retrospectives with the development team to continuously improve processes to eliminate any potential issues with the product.

B.

Apply an agile approach to write the specifications in an incremental way and develop the product once the final specifications are agreed upon.

C.

Set up test-driven development to focus on customer requirements and eliminate issues in the software as testing progresses,

D.

Ask the customer to provide additional representatives to help test and evaluate the product for early and frequent feedback.

Buy Now
Question # 73

A food company seeks additional business-to-business (B2B) revenues from some customers by

implementing purchase order (PO) functionality. To achieve this, the agile project team is exploring PO integration options (see item #3 in Exhibit A), as the product increment (PI) planning process is underway.

What should the project team do next?

Options:

A.

Use agile estimation techniques like planning poker or relative sizing for collaborative assessment.

B.

Break down the feature into smaller tasks or user stories for better assessment and incremental delivery.

C.

Analyze current system requirements and dependencies, including integration levels and regulatory compliance.

D.

Refer to past performance and historical data from similar projects to identity potential risks and challenges.

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: Aug 22, 2025
Questions: 476
PMI-ACP pdf

PMI-ACP PDF

$29.75  $84.99
PMI-ACP Engine

PMI-ACP Testing Engine

$33.25  $94.99
PMI-ACP PDF + Engine

PMI-ACP PDF + Testing Engine

$47.25  $134.99