Weekend Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: bigdisc65

PMI-ACP Exam Dumps - PMI Agile Questions and Answers

Question # 44

During the project initiation stage, a team has estimated story points for all user stories. When the project team explained the minimum marketable feature (MMF), however, they were not confident that the solution would actually work.

What can the team do to better manage this situation?

Options:

A.

Deliver the minimum marketable feature (MMF) to customers for feedback.

B.

Write acceptance criteria for each business requirement to conduct proper testing.

C.

Develop test cases based on user stories.

D.

Ask the customer to provide acceptance criteria before developing the user stories.

Buy Now
Question # 45

During a sprint review the product owner identifies a required improvement for a feature's user interface (UI) delivered during the sprint What should the product owner do next?

Options:

A.

Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer

B.

Create a user story for this new improvement and prioritize it for the next sprint

C.

Document it as a requirement creep

D.

Ask the team to take on additional story points to improve the UI

Buy Now
Question # 46

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted, there is no value to the customers during this iteration.

What must the agile practitioner do?

Options:

A.

Add the new change request as a new user story in the product backlog for the upcoming iteration

B.

Evaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value C. Recommend cancelling the current iteration and plan the change request into the next iteration.

C.

Recommend that the product owner add this change request as a user story to the backlog for the current iteration

Buy Now
Question # 47

An agile lead has been assigned to a project to develop an innovative digital device for a consumer products company. The company asked the agile lead to use a Scrum approach to product development. The product owner has worked on Scrum projects before and is excited about the value Scrum will bring to the company.

What should the scrum master do first?

Options:

A.

Build a product roadmapthat shows the features and releases.B Request an existing cross-functional team be dedicated to the project

B.

Obtain specific product requirements from a customer focus group.

C.

Develop a project budget based on the project charter.

Buy Now
Question # 48

A mature agile team welcomes a new member Due to poor experiences with a previous team, the new member is reluctant to communicate.

What should the agile project leader do?

Options:

A.

Bring up the new member's impediments at the next meeting to demonstrate team support of input

B.

Assure the new member that inputs on impediments are valued and demonstrate this at the next meeting

C.

Have a senior lead work with the new member to avoid a negative impact on team productivity

D.

Privately work with the new member to address any impediments

Buy Now
Question # 49

An agile team has received several new features to be added to the product backlog. The team is struggling to provide a reasonable estimate for feature development due to a lack of experience.

How should an experienced agile practitioner assist the team?

Options:

A.

Add a task to the product backlog to allow the team time to investigate and experiment prior to estimating.

B.

Add a task to the product backlog to allow the team to apply a wideband Delphi estimation technique.

C.

Add a task to the product backlog to allow the team to apply planning poker to estimate the effort.

D.

Add a task to the product backlog to allow the team to apply a three-point estimation technique.

Buy Now
Question # 50

During sprints, the development team members are frequently invited to various meetings to provide technical opinions, consuming the team's working time and causing compliance issues. Which action should the scrum master take to address this situation?

Options:

A.

Request additional resources to prevent compliance issues while still fostering a collaborative workplace.

B.

Escalate the concern to the product owner and request that they prioritize the development work.

C.

Designate a single team member to attend the meetings and establish a capacity buffer for each sprint.

D.

Reject all external meetings for the development team so they can fully focus on their sprint tasks.

Buy Now
Question # 51

An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?

Options:

A.

Conduct a requirements gathering workshop.

B.

Deliver the basic requirements iteratively.

C.

Have the product owner fill out the requirements backlog.

D.

Have the stakeholders fill out the backlog before starling the project.

Buy Now
Question # 52

During sprint retrospectives, some team members are very vocal and tend to dominate the conversation, while others are more reserved and less likely to participate. What should the scrum master do?

Options:

A.

Encourage all team members to participate, and have them type their retrospective feedback into the agile lifecycle management tool.

B.

Ask more specific questions during the retrospectives.

C.

Use retrospective techniques, such as silent writing, clustering, and dot voting to field feedback prior to discussion by the team.

D.

Ask team members to email feedback that can be summarized in a spreadsheet for the team.

Buy Now
Question # 53

After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings.

What should the product owner do to resolve this?

Options:

A.

Ask the development team to address the issue since it is in their domain.

B.

Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan.

C.

Meet with the team and stakeholders to address rework and rewrite stories as needed.

D.

Cancel the current sprint, and meet with stakeholders to reassess the project's validity.

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: Oct 6, 2025
Questions: 476
PMI-ACP pdf

PMI-ACP PDF

$29.75  $84.99
PMI-ACP Engine

PMI-ACP Testing Engine

$33.25  $94.99
PMI-ACP PDF + Engine

PMI-ACP PDF + Testing Engine

$47.25  $134.99