Question # 84

An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay and is planning to start the marketing campaign and announce the release.

What should the agile coach do?

Options:

A.

Meet with the agile team lead to discuss ways to improve team velocity and get back on track

B.

Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins

C.

In the upcoming retrospective, discuss ways to improve sharing project status information

D.

Meet with the marketing stakeholders to explain that the team will miss the planned release date

Buy Now
Question # 85

An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features.

What should the team member do?

Options:

A.

Influence the customer

B.

Mention the idea at the next retrospective

C.

Show the customer how much time and money would be saved

D.

Present the idea at the next ceremony attended by stakeholders to obtain their input

Buy Now
Question # 86

A development team has started working on a new service but is unsure if the service fits the customer's requirements. What should the product owner do to ensure that the service will benefit the customer?

Options:

A.

Release the minimum viable product (MVP) to a group of customers and end users for their feedback.

B.

Build a prototype and review it with the targeted customer segment for their feedback.

C.

Invite a group of customers and end users to the biweekly demos to obtain feedback.

D.

Release the prototype of the software for 6 months to a pilot group of customers for feedback.

Buy Now
Question # 87

Team A is working on the second sprint of a product release Team B which is an interdependent team located on the same floor, requires extensive and frequent information to complete its sprint goal.

What should the agile team lead do?

Options:

A.

Create a central repository for information, and provide access to team B

B.

Use an information board that will be visible to all passing through the workspace

C.

Email all stakeholders with status updates

D.

Provide team B with the information on an "as needed" basis

Buy Now
Question # 88

The team is derailed by a demand from a senior manager unrelated to the project. How does the agile coach help the team?

Options:

A.

By coaching the team to outperform previous velocity

B.

By coaching the team to adhere to expectations set by the scrum master

C.

By encouraging overestimation to increase velocity

D.

By advising the team to remain committed and focused on project goals

Buy Now
Question # 89

An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.

Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? (Refer to the Risk Register Exhibit)

Options:

A.

Conduct thorough requirements analysis and validation.

B.

Allocate experienced developers and perform code reviews.

C.

Plan for sufficient support resources post-deployment.

D.

Develop comprehensive testing involving the quality assurance team.

Buy Now
Question # 90

In several recent agile team status meetings, there have been discussions about increases in costly bugs and late product deliveries, resulting in lower quality and higher costs. Team members feel they spend too much time in planning and process meetings, then feel rushed to complete their work.

How should the agile lead implement an effective and efficient solution?

Options:

A.

Review the quality assurance and control processes with the team to ensure that even new team members understand the service level agreement (SLA) made with the customer.

B.

Suggest the team commit to a 2-month trial using Kanban. Focus on delivering value to the customer using pull criteria before advancing work. The team will have planning meetings as needed with no special meetings about the process.

C.

Hire a consultant team to perform a root cause analysis, which will determine the fundamental issues from both perspectives, then meet with the team to determine the best method to get the project back on track.

D.

Work with the team to create a spike story for the next iteration to investigate the issue. Create a plan to get the project back on track and present it at the next status meeting to gain stakeholder acceptance.

Buy Now
Question # 91

Case Study

An agile project lead for a company is leading a sales team who has committed to delivering new product functionality to the customer at the end of five sprints. The agile project lead performed initial planning with the team and with the team's support has committed to the scope and deadline.

Check in with the project in three stages to answer the associated questions.

How do two additional features and more story points added by the product owner impact the team's progress and ability to complete work within the iteration, considering the burndown rate of the team has not changed? (Refer to the Case Study and End of Sprint 3 Exhibit)

Options:

A.

The scope of the items in the backlog has been increased to reflect an increase in velocity.

B.

The backlog has been increased and the velocity of the project may no longer be on track.

C.

The team has committed to additional work added to the backlog and will increase velocity.

D.

The team did not complete the backlog items at the same velocity due to external issues

Buy Now
Question # 92

A Scrum team has worked hard to reach their sprint goal, but impediments have prevented them from succeeding. The team needed help from a specialist on another team, but the specialist was on a 2-week vacation.

What should the scrum master do?

Options:

A.

At the sprint retrospective, the scrum master and development team should discuss why the team did not know the specialist was unavailable during the sprint. The scrum master should then set clear rules so situations like these can be avoided in the future.

B.

It can be very distressing for a Scrum team not to reach its sprint goals. The scrum master should hold an evaluation meeting to discuss who in the team was responsible for discovering the specialist was not available, then make an improvement task for the next sprint.

C.

The scrum master, as a servant leader, should always try to remain positive about the team's work. Even when team members’ make mistakes, there should be trust that everyone is doing their best. Engaged team members work more efficiently, and a sustainable pace is important for project success.

D.

At the sprint retrospective, the Scrum team should reflect on how the past sprint has worked out. The scrum master should facilitate an open discussion to discover the root causes for the missed sprint goals and find a way to avoid similar situations in future sprints.

Buy Now
Question # 93

A project manager noticed that a team member had been a consistently high performer until a few months ago. Recently, the team member seems distracted and is not performing well.

How should the project manager handle a review with the team member?

Options:

A.

Talk to the team member about project deliverables and how poor performance is unacceptable.

B.

Discuss performance with the team member on the project deliverables and provide constructive feedback.C Inform the learn member that this project is complex and consider moving them to another project

C.

Extend support to the team member as this is the first project in which the team member underperformed.

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: Aug 22, 2025
Questions: 476
PMI-ACP pdf

PMI-ACP PDF

$29.75  $84.99
PMI-ACP Engine

PMI-ACP Testing Engine

$33.25  $94.99
PMI-ACP PDF + Engine

PMI-ACP PDF + Testing Engine

$47.25  $134.99