Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMI-ACP Exam Dumps - PMI Agile Questions and Answers

Question # 4

What should the agile team do next?

Options:

A.

Ensure that the product owner reviews the acceptance criteria for delivered user stories.

B.

Augment the quality assurance and continuous integration processes for delivery.

C.

Approach the relevant developers and testers regarding quality issues in upcoming iterations.

D.

Ask the product owner to define the entire scope of delivery two to three iterations in advance.

Buy Now
Question # 5

After completing the release plan, the team realizes that the project is very likely to have a negative ROI.

What should the team do?

Options:

A.

Prioritize the backlog, and remove low-priority stories from the release plan to ensure a positive ROI

B.

Replace some team members to reduce the release costs and minimize a negative ROI

C.

Perform a root-cause analysis to remove waste from the delivery process and increase the ROI

D.

Communicate the risk of a negative ROI to the stakeholders, and update the release plan

Buy Now
Question # 6

In a Scrum team, who should be responsible for the budget and release plans?

Options:

A.

The Scrum Master assigns someone on the team to handle the budget, and the Product Owner is responsible for release plans

B.

The finance department is responsible for the budget, and the Product Owner is responsible for release plans

C.

The Scrum team as a whole, as they are self-organizing and share accountability

D.

The Product Owner is responsible for both the budget and the release plans

Buy Now
Question # 7

A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to compete in the marketplace.

What analysis should the team use to understand the issues?

Options:

A.

Risk management

B.

Variance and trend

C.

Kano model

D.

Fishbone diagram

Buy Now
Question # 8

What was the determining factor?

Options:

A.

Size and priority

B.

Minimum marketable features

C.

Release plan

D.

Sprint mapping

Buy Now
Question # 9

A team member starts discussing a project roadblock during a daily coordination meeting. The team discusses details of the impediment, which takes up most of the meeting time.

What should the agile facilitator do?

Options:

A.

Dismiss the rest of the team from the meeting to focus on the problem reported by the team member

B.

Ask the team member to wait to discuss until the next daily coordination meeting, the team needs to review the current status.

C.

Inform the team that the meeting will be extended so there is time to hear what the team member is reporting

D.

Stop the team politely and suggest scheduling another meeting to discuss this specific matter.

Buy Now
Question # 10

Options:

A.

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.

B.

A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.

C.

A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.

D.

A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.

Buy Now
Question # 11

What should the team have done to prevent this?

Options:

A.

Reprioritized requirements prior to committing to iteration work

B.

Ensured that requirements remained stable during the iteration cycle

C.

Had stakeholders focus on items created after the product backlog was initially built

D.

Worked on features rather than a set of components

Buy Now
Question # 12

A member of a project ' s development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work, and to rely on outside specialists, is impacting team velocity.

What should the agile team lead do?

Options:

A.

Send the member to training

B.

Ask the outside specialists if database administration is required from the team

C.

Send one member to training only after asking the team if there is an issue with the current workflow

D.

Wait until all members of the team can attend training

Buy Now
Question # 13

What should the agile practitioner do?

Options:

A.

Ask the opinion of key stakeholders and the client to ensure the correct approach is being used

B.

Work with the team to use this approach and request a quality assurance iteration after every three iterations

C.

Propose to completely eliminate test automation, since this is a quality assurance function

D.

Suggest merging the quality assurance and delivery teams to enhance each iteration ' s test-automation levels and reduce redundancy

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: May 21, 2026
Questions: 481
PMI-ACP pdf

PMI-ACP PDF

$25.5  $84.99
PMI-ACP Engine

PMI-ACP Testing Engine

$28.5  $94.99
PMI-ACP PDF + Engine

PMI-ACP PDF + Testing Engine

$40.5  $134.99