PMI-ACP Exam Dumps - PMI Agile Questions and Answers

Question # 104

What should the project team do next?

Options:

A.

Estimate the project team ' s capacity.

B.

Determine how much work can be delivered.

C.

Calculate how much work will fit into the next iteration.

D.

Estimate items in the product backlog.

Buy Now
Question # 105

How can an agile project manager ensure that all stakeholders have a clear understanding of the release plan by the end of a release planning meeting? (Choose two.)

Options:

A.

Stated understanding of the release goal

B.

Complete vision of the end product

C.

Timeline of the project

D.

List of the user stories that will be part of the next releases

E.

Complete roadmap of the next iterations

Buy Now
Question # 106

What is a benefit of this meeting?

Options:

A.

The team will learn how its contribution will create product value

B.

It will enable team acceptance of client priorities

C.

It will enable the team to see the entire project in one glance

D.

It will enable the team to ask any questions to the customer upfront

Buy Now
Question # 107

An agile development team is working on a digital transformation project and is facing challenges in obtaining consistent feedback from stakeholders who are dispersed around the world. The product owner is under pressure as this lack of engagement has led to prolonged decision-making cycles and has adversely affected the outcomes of sprints.

How should the team improve stakeholder engagement to help ensure timely feedback and better decision-making? (Refer to Stakeholder Power/Interest Grid)

Options:

A.

Implement a dynamic feedback platform leveraging collaboration tools, accommodating diverse schedules and enabling stakeholders to provide feedback asynchronously.

B.

Establish a rotating stakeholder committee composed of representatives from different regions and departments, ensuring diverse perspectives are considered in decision-making processes.

C.

Enforce a strict policy requiring stakeholders to attend weekly synchronous feedback sessions, leveraging technology to accommodate various time zones and scheduling conflicts.

D.

Appoint regional liaison officers responsible for coordinating stakeholder interactions within their respective time zones, facilitating regular communication and feedback exchange.

Buy Now
Question # 108

How should the project team address this issue?

Options:

A.

Suggest pair programming during the retrospective.

B.

Ask the product owner to re-prioritize the user stories at the next retrospective.

C.

Re-estimate the story points with team members at the next iteration planning meeting.

D.

Assign less complex user stories to the inexperienced software engineer at the next iteration planning meeting.

Buy Now
Question # 109

During backlog refinement, the team uses an online planning poker tool for estimation. The junior developers change their number of story points after they see the estimations provided by the developers. The junior developers state that the reason for this is that they do not have enough experience and do not want to be blamed for sizing it wrong.

What should the scrum master do?

Options:

A.

Ask the developers to keep their estimation so that the team is transparent with their level of understanding of work.

B.

Agree with the team to keep their estimation as the final number of story points will be the average of all team members.

C.

Propose to consider the estimations of only senior developers and have the junior developers learn from them.

D.

Encourage the team to keep their estimation as this will help surface different constraints and assumptions that others might have missed.

Buy Now
Question # 110

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)

Options:

A.

Work with the team to establish goals for the product at the beginning of each scheduled iteration.

B.

Send the team the latest version of the release plan so they can provide feedback.

C.

Invite the customer to the sprint planning meeting to explain what is deemed most critical to their business.

D.

Ensure all iteration goals are fully developed at the beginning of the project.

E.

Refine the product backlog and identify the Minimum Viable Product

Buy Now
Question # 111

An agile project leader notices that the team ' s velocity has decreased. In examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses.

What can happen as a result?

Options:

A.

The team will be unable to understand the iteration ' s status

B.

The team will be unable to judge the project design ' s validity

C.

The team cannot give accurate updates to management

D.

Team collaboration cannot be measured effectively

Buy Now
Question # 112

A new CIO advocates an agile framework for new IT projects, but the team has reservations. How should the CIO ensure that the team will be aligned with this?

Options:

A.

Obtain executive team buy-in by conducting a meeting to present the advantages of agile principles and processes.

B.

Issue a memo of understanding that agile principles should be implemented for all new projects.

C.

Introduce agile principles and processes, then make the change an experiment to obtain buy-in.

D.

Require all staff and management to attend agile training and adhere to its principles.

Buy Now
Question # 113

What should be proposed to the team?

Options:

A.

Have other team developers attend training to learn database skills.

B.

Monitor the retrospectives of two additional sprints before taking action.

C.

Plan fewer stories for the sprint to reduce the database engineers ' workload.

D.

Ask the Scrum Master to work with the product owner to remove backlog stories that have database dependency.

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: May 22, 2026