PMI-ACP Exam Dumps - PMI Agile Questions and Answers

Question # 124

A global subscription-based service is pursuing enterprise agility across digital product development teams. Product teams release updates frequently, but customer usage data and support trends are reviewed only at the end of each quarter. As a result, several low-adoption features continue to receive investment while customer churn gradually increases. Leadership wants the product teams to respond more quickly to changing customer behavior.

What should the agile practitioner recommend?

Options:

A.

Schedule monthly executive reviews to assess customer usage and feedback to support investment decisions.

B.

Integrate customer usage analytics into feature prioritization processes to adjust investment decisions.

C.

Delegate feature prioritization decisions to regional business managers based on customer usage analytics.

D.

Increase the number of features delivered each quarter to drive customer usage and improve overall satisfaction.

Buy Now
Question # 125

Two similar stories A and B are estimated at 3 story points. Story C is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.

What should the agile practitioner do?

Options:

A.

Assign story B more than 8 story points to provide a better estimate

B.

Add points to story B’s iteration to account for the error but keep story B at 3 points

C.

Assign more resources to story B to bring it in line with the estimate

D.

Reestimate all stories including values for A, B, and C

Buy Now
Question # 126

The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during meetings. What should the project lead do to encourage the team members to express themselves?

Options:

A.

Emphasize rules that need to be respected during meetings.

B.

Allow team members to talk when they feel comfortable without any pressure.

C.

Organize separate meetings with each individual team member.

D.

Create a safe environment for discussions during meetings.

Buy Now
Question # 127

A new project is under way and the team is using the Kanban method. One of the team members raised a specific issue related to a programming language that the team member faced in previous projects.

What should the project leader do to handle the issue?

Options:

A.

Include the issue in the risk log.

B.

Monitor the issue in a notation system.

C.

Ask the team member to take full ownership of the issue.

D.

Advise the team member to add the issue to the board.

Buy Now
Question # 128

The project lead of a newly created Agile project delivery team realizes that there are gaps in the knowledge of some team members. The lack of specific skills will add risk to the project delivery if the project becomes too dependent on specific resources for complete delivery.

What should the project lead do to address the gaps and develop a high-performing team?

Options:

A.

Ask each team member to document their solutions extensively in a knowledge repository for knowledge exchange between the team.

B.

Pair team members and ensure review of technical deliverables by partners in each sprint before integration of the solution.

C.

Create an environment of continued learning by providing opportunities for team members to develop their skills as generalized specialists.

D.

Replace the team members with highly qualified individuals that have experience in the specific technologies required for completing delivery.

Buy Now
Question # 129

How should the agile team lead respond?

Options:

A.

Emphasize to the stakeholder that a common, detailed vision will better ensure team understanding of the project.

B.

Personally meet with the stakeholder to understand their requirements, and then share the vision with the team.

C.

Work with the team to create a vision from the stakeholder ' s supplied requirements.

D.

Explain to the team that creating a vision is not critical in agile projects, as requirements may change over time.

Buy Now
Question # 130

More details for a story are required before the upcoming sprint planning meeting.

What should the Scrum Master do?

Options:

A.

Email the product owner requesting detailed story specifications and wait for a response

B.

Gather the details from the team members before sprint planning

C.

Schedule a story grooming session with the product owner before sprint planning

D.

Conduct a planning poker session with the team

Buy Now
Question # 131

In Scrum, the responsibilities of the project manager are shared among the product owner, scrum master, and development team. Why are responsibilities shared among the three roles?

Options:

A.

" Inspect and adapt " are two of the three pillars in Scrum. The roles in Scrum are divided among the product owner, scrum master, and development team in a way that makes it possible to inspect the efficiency and adapt the way responsibilities are shared to maximize efficiency if needed.

B.

Scrum is a collaboration framework that encourages the Scrum team - the product owner, scrum master, and development team - to collaborate in a way that fosters fast value creation with respect for each team member ' s opinions and individual preferences.

C.

The product owner is responsible for the product backlog and long-term plans, the scrum master is responsible for the Scrum process, and the development team is responsible for the sprint backlog and progress toward the sprint goal. This facilitates clear accountability and effective value creation.

D.

The product owner is responsible for the product and sprint backlog. The scrum master follows up on progress, and the development team estimates and decomposes the backlog items into manageable pieces. This ensures each person has the roles they are best at and feel most comfortable with.

Buy Now
Question # 132

A diverse team can sometimes create misunderstandings and conflict, leading team members to isolate. How can an agile project manager promote effective communication and collaboration among team members with diverse backgrounds and perspectives?

Options:

A.

Reduce emotions by emphasizing areas of agreement rather than areas of difference.

B.

Create a shared vision for the team and use techniques to increase empathy and positive interaction.

C.

Coach the team to focus on areas of agreement and the company ' s profitability.

D.

Confront the team and follow the formal procedures as described in the project management plan.

Buy Now
Question # 133

During a backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog.

What should the team do?

Options:

A.

Add this threshold requirement request as acceptance criteria in all impacted stories

B.

Create a spike story to analyze the impact of the threshold requirement on current stories

C.

Conduct design planning session to review the performance threshold requirement

D.

Identify the tasks for the new performance threshold requirement

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: May 22, 2026
Questions: 481
PMI-ACP pdf

PMI-ACP PDF

$25.5  $84.99
PMI-ACP Engine

PMI-ACP Testing Engine

$28.5  $94.99
PMI-ACP PDF + Engine

PMI-ACP PDF + Testing Engine

$40.5  $134.99