Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMI-ACP Exam Dumps - PMI Agile Questions and Answers

Question # 114

A new agile project leader habitually becomes involved in the work from a support perspective and uses information radiators to ensure that all actions to remove impediments are visible to the team.

What is the agile project leader doing?

Options:

A.

Practicing the servant leadership style of working with an agile team

B.

Building a collaborative teamwork culture

C.

Following a participatory decision-making model

D.

Adopting the practice of receiving feedback that will facilitate team improvement

Buy Now
Question # 115

There is a debate within the organization on whether projects need to be agile or waterfall. Some agile terms and principles are understood differently by the key stakeholders and this delays the decision-making process.

How should the scrum master proceed?

Options:

A.

Allow stakeholders to discuss without the scrum master ' s intervention.

B.

Recommend an external facilitator as no one in the organization is able to eliminate this roadblock.

C.

Facilitate a face-to-face discussion and have stakeholders agree to shift to agile for future projects.

D.

Organize training sessions to create awareness around the agile values for stakeholders.

Buy Now
Question # 116

An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?

Options:

A.

Conduct a requirements gathering workshop.

B.

Deliver the basic requirements iteratively.

C.

Have the product owner fill out the requirements backlog.

D.

Have the stakeholders fill out the backlog before starting the project.

Buy Now
Question # 117

An agile practitioner notices that team members are disengaged. As a result, the team ' s velocity has decreased. What should the agile practitioner do to get the team back on track?

Options:

A.

Escalate the issue to the project sponsor.

B.

Remove stories to increase velocity.

C.

Hold a stand-up to address the issue.

D.

Facilitate a team retrospective.

Buy Now
Question # 118

A Product Owner new to the role is very enthusiastic about an agile project with an energetic team.

What should be done first to ensure successful delivery of the product?

Options:

A.

Hold a meeting with the team and the Product Owner to develop the team charter, working agreement, guiding principles, and product vision

B.

Ask the Product Owner to create the project vision and charter, and then discuss the guiding principles with the team

C.

Hold a meeting during which the team can present the project charter, high-level project plan, and team values to the Product Owner

D.

Send the Product Owner to formal Product Owner training where the Product Owner can learn how to create a product vision

Buy Now
Question # 119

A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.

What strategy should be used to deliver it successfully?

Options:

A.

Talk with the old project manager to learn about the problems they encountered and the lessons learned.

B.

Suggest organizing a meeting in order to analyze the situation and work to find a strategy.

C.

Analyze all defects and change requests carefully to understand their root causes and act accordingly.

D.

Suggest an iterative approach including timely engagement of all key stakeholders and hold regular review meetings.

Buy Now
Question # 120

What should the team do?

Options:

A.

Work longer hours to complete more of the support backlog.

B.

Work support tickets in the order in which they were received.

C.

Place tickets on hold until the team completes an analysis of the backlog to identify and resolve systemic issues.

D.

Add members to the support team.

Buy Now
Question # 121

After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered.

What should the agile practitioner do?

Options:

A.

Calculate velocity based on completed sprints and triangulate the remaining work on the backlog to commit to an accurate schedule.

B.

Decompose the product backlog into user stories with tasks/acceptance criteria and estimate to commit to an accurate schedule.

C.

Use analogous estimating techniques based on projects with a similar velocity.

D.

Provide a delivery range based on the team ' s estimated velocity.

Buy Now
Question # 122

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.

What should the product owner do next?

Options:

A.

Obtain approval from the change control board to discontinue the component

B.

Ask the team to continue developing the component

C.

Ask the team to discontinue developing the component

D.

Request the sponsor ' s formal approval to discontinue the component

Buy Now
Question # 123

The lead developer informed the team that they have learned of some possible integration challenges in creating customer dashboards using the architecture the team has chosen.

What should an agile practitioner do?

Options:

A.

Conduct an architectural spike immediately to decide how the functionality will be determined.

B.

Work with the product owner to avoid the risk by determining if their requirements could be met with reporting or a similar functionality.

C.

Continue the priority defined by the product owner on the backlog for the functionality they determined to be the highest priority.

D.

Identify this as a risk, decide on the response, and prioritize spike to determine the solution on the product backlog.

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: May 22, 2026
Questions: 481
PMI-ACP pdf

PMI-ACP PDF

$25.5  $84.99
PMI-ACP Engine

PMI-ACP Testing Engine

$28.5  $94.99
PMI-ACP PDF + Engine

PMI-ACP PDF + Testing Engine

$40.5  $134.99