Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: Board70

PMI-ACP Exam Dumps - PMI Agile Questions and Answers

Question # 114

When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?

Options:

A.

High-risk and high-value

B.

High-risk and low-value

C.

Low-risk and low-value

D.

Low-risk and high-value

Buy Now
Question # 115

A key resource is switching between projects to obtain more visibility and acclaim. However, project work has grown and become a burden.

What should the agile project leader do?

Options:

A.

Add more resources to projects to ensure work sharing.

B.

Encourage the resource to undergo time management training.

C.

Ask management to ensure that the resource is available to only one project at a time.

D.

Allow the resource to continue switching between projects to deliver high customer value.

Buy Now
Question # 116

What information should a project team include in an extended stakeholder report to ensure that all current and future stakeholders are aware of the frequent updates?

Options:

A.

Team capacity and competence profiles

B.

A list of tools used for implementation

C.

A list of open technical issues

D.

Up-to-date project radiators

Buy Now
Question # 117

A team is transitioning from a predictive approach to an agile approach Historically, the team has delivered work products that did not meet customer expectations.

What agile practice can help the team to alleviate this?

Options:

A.

Test-driven development (TDD)

B.

Clear definition of done and regular demos

C.

Collaborative team planning games

D.

Consistent team velocity

Buy Now
Question # 118

During the retrospective meeting, it is revealed that an external dependency is causing a reoccurring impact. The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.

What should the scrum master do now?

Options:

A.

Guide the development team to accept and adapt to the existing situation by finding sustainable workarounds.

B.

Assure that the development team plans the scope of work with this risk absorbed in the estimation.

C.

Establish a communications channel with the external team and monitor the implementation of the external task.

D.

Collect empirical data and influence upper management to be accountable for end-to-end. cross-team delivery.

Buy Now
Question # 119

The team is considering committing to 44 story points for the upcoming sprint. Based on the

velocity chart, what advice should the scrum master offer the team?

Options:

A.

Reduce the commitment to 40 story points to ensure a higher chance of meeting the commitment.

B.

Maintain a commitment of 46 story points, representing the most frequently completed velocity.

C.

Increase the commitment to 48 story points to push the team toward higher performance.

D.

Commit to 44 story points as it aligns with the team's average velocity for completed story points.

Buy Now
Question # 120

A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to compete in the marketplace

What analysis should the team use to understand the issues?

Options:

A.

Risk management

B.

Variance and trend

C.

Kano model

D.

Fishbone diagram

Buy Now
Question # 121

A software company is developing an accounting software system to market to customers. The team has been working on the project for six weeks and has great velocity. One of the major stakeholders approached the scrum master and asked for a bi-weekly status report because they feel they are not being properly updated.

How should the scrum master respond to this request?

A Inform the stakeholder that all updates are provided in the sprint review sessions and encourage them to attend

B. Create and update bi-weekly project status reports for the stakeholder who requested the report.

C. Escalate this to the stakeholder's supervisor because this is an unreasonable request.

D. Ignore the stakeholder's request and continue working on the project as they have been for the past six weeks.

Options:

Buy Now
Question # 122

An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action.

What should the team do?

Options:

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

Buy Now
Question # 123

An agile team lead is assigned to a project that must ensure data security. What should the team lead do to guarantee that security, as a non-functional requirement, is managed throughout the project?

Options:

A.

Include security concerns on the agenda for every meeting.

B.

Request that a security expert be added to the team.

C.

Add security as a non-functional requirement to the risk register, and review regularly.

D.

Ensure that planning and prioritizing includes consideration of security requirements.

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: Aug 22, 2025
Questions: 476
PMI-ACP pdf

PMI-ACP PDF

$25.5  $84.99
PMI-ACP Engine

PMI-ACP Testing Engine

$28.5  $94.99
PMI-ACP PDF + Engine

PMI-ACP PDF + Testing Engine

$40.5  $134.99